Skeena Resources Limited · TSX:SKE

Skeena Resources — Investor Presentation (August 2026)

29 slides from Skeena Resources's investor presentation, August 2026

  1. Slide 1: Developing the Next Tier 1 Gold & Silver Mine

    Developing the Next Tier 1 Gold & Silver Mine Corporate Presentation August 2026 TSX: SKE | NYSE: SKE www.skeenagoldsilver.com

  2. Slide 2: Forward Looking Statements

    Forward Certain statements and information contained or incorporated by reference in this presentation constitute “forward -looking information” and “forward -looking statements” Looking within the meaning of applicable Canadian and United States securities legislation (collectively, “forward -looki

  3. Slide 3: Eskay Creek is a Cashflow Focused Gold & Silver Mine

    Eskay Creek is a Cashflow Focused Gold & Silver Mine Large -Scale Gold & High Low Operating Major Construction Project Optimization Silver Production Gold Grade Costs Underway Underway 5.5 gpt AuEq in years 1 -5 & US$687 per oz AISC (1,2,3) 450,000 AuEq oz produced On schedule for initial Updated 43

  4. Slide 4: Delivering on Our Commitments With a Strong Start to the Year

    Delivering on Our Commitments With a Strong Start to the Year Q2 2026 Updated Project Capital Cost from Prior 2023 Estimate Q2 2026 Updated 2026 capital cost estimate to US$659 Completed Comprehensive million, from the 2023 DFS estimate of US$560 Refinancing Strategy to Optimize million. Changes in

  5. Slide 5: Existing Infrastructure Provides Substantial Cost Savings

    Projects Existing TAHLTAN TERRITORY SADDLE Operations Newmont Infrastructure RED CHRIS Provides Substantial SCHAFT CREEK Teck Newmont Cost Savings GALORE CREEK Teck COAST MOUNTAIN HYDRO FACILITY Access & transport SNIP + Connected via Highway 37 for all -weather access Skeena KSM Seabridge BRUCEJACK

  6. Slide 6: Exceptional Economics Drive Cashflow & Fast Payback

    Exceptional Economics Payback (Years) (2) Drive Cashflow & 1.2 < 8 months < 7 months Fast Payback $14,000 NPV(5%) $CAD IRR 138% 140% Annual Financial Metrics (Years 1 -10) at $12,000 Spot Prices ($ CAD ) 97% 120% $10,000 100% $8,000 $ 2.0 Billion $1.8 Billion 80% (1) Annual EBITDA (1) $6,000 Annual

  7. Slide 7: Front Loaded Production Profile Driven by Grade

    Front Loaded Production Profile 800 Opportunities to backfill Driven by Grade 700 6.2 gpt 6.0 gpt production profile with satellite deposits in the area 5.5 gpt 600 5.1 gpt 4.6 gpt 2023 DFS Estimates 4.2 gpt 4.0 gpt 500 450,000oz 5.5 gpt gold 2.4 gpt 2.6 gpt 400 Elevated annual gold Elevated gold 1.

  8. Slide 8: Project Execution Schedule

    Project H1 - 25 H2 - 25 H1 - 26 H2 - 26 H1 - 27 H2 -27 Execution PERMANENT Initial Tie ins Permanent Power Complete Schedule POWER TAILINGS DAM & WATER MANAGEMENT Pre -stripping Commences Initial Fleet Mobilized Ore Mining Commences MINING PROCESS PLANT 92 % Complete (detailed) Engineering Long Lead

  9. Slide 9: Project Substantially De-risked; Over 60% Complete

    Project Substantially Project Progress at June 30, 2026 was 62% complete De -risked; Over 60% Bulk earthworks • Pre-stripping activities have totaled +3 million tonnes of material moved. Complete & mining • Open pit mining will continue in 2026 to produce construction rock and in Q4, commence ore mi

  10. Slide 10: Accretive Refinancing Strategy Optimizes Capital Structure

    Accretive Refinancing “ At Skeena, we continue to redefine what's possible in the mining Strategy Optimizes industry. As the first pre - revenue -generating company to issue a public high -yield bond, we’ve demonstrated the market’s confidence Capital Structure in the exceptional future cash -flow p

  11. Slide 11: World Class Gold Grade & Scale

    World Class Gold Top global open -pit gold mines by grade ( gpt ) (3) Grade & Scale Kekura (Highland Gold) Eskay Creek (Y1-5) Salares Norte (Gold Fields) 5.4 5.5 7.0 Meliadine (Agnico Eagle) 5.3 Kyzyl (Solidcore) 5.1 Eskay Creek 3.6 Veduga (Solidcore) 3.4 PROVEN & PROBABLE GOLD RESERVES Loulo (Barri

  12. Slide 12: Eskay Creek is Canada's Largest Silver Mine

    Eskay Creek is Top global primary silver production (2) Canada’s Largest Saucito (Fresnillo) Cannington (South32) San Julian (Fresnillo) 11.8 12.7 14.5 Silver Mine Pirquitas (SSR Mining) Uchucchacua (Buenaventura) Juanicipio (Fresnillo's 56% stake) 10.5 10.5 10.4 Fresnillo (Fresnillo) 10.2 Eskay Cre

  13. Slide 13: Open pit with mill building in background

    Open pit with mill building in background July 2026 13

  14. Slide 14: Mining in the Pit

    Mining in the Pit July 2026 14

  15. Slide 15: Conveyor Footings & Crusher Installation

    Conveyor Footings & Crusher Installation June 2026 – Primary crusher to coarse ore stockpile conveyor July 2026 – primary crusher body installation 15

  16. Slide 16: Coarse Ore Stockpile Reclaim Tunnel

    Coarse Ore Stockpile Reclaim Tunnel July 2026 16

  17. Slide 17: Process Plant - Interiors

    Process Plant - Interiors June 2026 – SAG mill July 2026 – flotation cells 17

  18. Slide 18: Mechanical Installation – Process Plant

    Mechanical Installation – Process Plant July 2026 – Isamills (tertiary and concentrate regrind) June 2026 – Regrind cyclone 18

  19. Slide 19: Mechanical Installation – Process Plant

    Mechanical Installation – Process Plant July 2026 – Jameson cleaner flotation cells July 2026 – scavenger flotation cells 19

  20. Slide 20: Volcano Creek Substation

    Volcano Creek Substation June 2026 – transformer in place 20

  21. Slide 21: New Employee Camp

    New Employee Camp July 2026 – module installation 21

  22. Slide 22: Significant Re-rate Ahead as Eskay Creek Achieves Production

    Significant Re -rate Ahead as Eskay Creek Artemis Gold (1) Lundin Gold (1) 2026E production: 297k oz Au Achieves Production 2026E EBITDA: C$1.3 billion Market cap of C$9.6B 2026E production: 511k oz Au 2026E EBITDA : C $2.3 billion Market cap of C$22.3B (1) Skeena Gold & Silver Alamos Gold (1) INCRE

  23. Slide 23: Strong Shareholder Support

    Strong Shareholder Support Research Coverage Shareholders Helikon Investments Ltd. 12.8% Insiders Agentis Michael Gray Deutsche Balaton AG 8.8% Retail/Public 4% BMO Andrew Mikitchook 20% CIBC Luke Bertozzi Van Eck 6.7% TD Wayne Lam KGH Ltd. 5.2% Canaccord Jeremy Hoy Vanguard Group 3.3% Desjardins Al

  24. Slide 24: Connect with Investor Relations

    Connect with Investor Relations For more insights info@skeenagold.com Follow us on social: TSX: SKE | NYSE: SKE www.skeenagoldsilver.com

  25. Slide 25: Our Track Record of Delivering on Commitments in our Journey to Production

    Our Track Record of Delivering on Commitments in our Journey to 2026 -2027 Production 2023 -2025 2019 -2022 2016 -2018 Received all permits for construction Improved Definitive Feasibility Study Full scale construction Secured project financing Publish updated NI 43-101 to Upgraded resource commitme

  26. Slide 26: A BC Leadership Team

    A BC Leadership Team Deep development expertise with the correct management Andrew team in place Walter Coles Randy Reichert Nalaine Morin Executive Chairman Chief Executive Officer MacRitchie SVP, Environment & Chief Financial Officer Social Affairs Kanako Galina Meleger Ryan Maloney Kyle Foster An

  27. Slide 27: Mineral Reserves & Mineral Resource Estimates

    Mineral Reserves & Mineral Resource Estimates Eskay Creek Resources & Reserves – Pit -constrained (as of December 31, 2023) Tonnes Au Ag AuEq Au oz Ag oz AuEq Oz (Mt) (gpt) (gpt) (gpt ) (Moz) (Moz) (Moz) Mineral Reserves Proven 28.0 3.0 80.9 4.1 2.7 72.7 3.7 Probable 11.9 1.8 40.1 2.3 0.7 15.3 0.9 T

  28. Slide 28: Mineral Resource Estimate

    Mineral Resource Estimate Eskay Creek Resources – Underground (as of December 31, 2023) Tonnes Au Ag AuEq Au oz Ag oz AuEq Oz (000) (gpt) (gpt) (gpt ) (Koz) (Koz) (Koz) Mineral Resources Measured 834 5.3 142.6 7.3 142 3,830 196 Indicated 988 4.1 55.7 4.9 131 1,768 156 Total Measured + Indicated Reso

  29. Slide 29: Non-IFRS Measures

    Non -IFRS Measures Non -IFRS Measures This presentation refers to various non -IFRS measures, such as “AISC", “total cash costs per ounce sold”, “average realized pric e per ounce sold” and “free cash flow”. These measures do not have a standardized meaning prescribed by IFRS as an indicator of perf

Skeena Resources — Investor Presentation (August 2026) on 6ix