Ameren Corporation · NYSE:AEE

Ameren — Evercore ISI Utility Conference 2025

36 slides from Ameren's conference presentation, Jan 9, 2025

  1. Slide 1: Powering a Reliable, Sustainable Tomorrow

    Powering a Reliable, Sustainable Tomorrow Evercore ISI Utility Conference Jan. 9, 2025

  2. Slide 2: Cautionary Statements

    Cautionary Statements Use of Non-GAAP Financial Measures In this presentation, Ameren has presented adjusted earnings per share, which is a non-GAAP measure and may not be comparable to those of other companies. A reconciliation of GAAP to non-GAAP information is included in this presentation. Gener

  3. Slide 3: Company Description

    Company Description Fully rate-regulated electric and natural gas utility Ameren Businesses 2.5M electric Ameren Missouri customers • Electric transmission, distribution, and generation business and a natural gas distribution business in Missouri regulated by MoPSC 0.9M gas • Serves 1.3 million elec

  4. Slide 4: Our Strategic Plan

    Our Strategic Plan INVEST ENHANCE OPTIMIZE Enhance regulatory Invest in rate regulated Optimize operating frameworks and advocate energy infrastructure performance for responsible policies To capitalize on opportunities to benefit our customers, communities, shareholders and the environment Evercore

  5. Slide 5: Our Value Proposition for Customers, Shareholders and the Environment

    Our Value Proposition for Customers, Shareholders and the Environment Attractive dividend Strong long-term and long-term dividend growth Attractive total growth outlook outlook return potential • Expect 6% to 8% EPS CAGR 2024-20281,2 • Annualized equivalent dividend rate of • Track record of deliver

  6. Slide 6: Our Sustainability Value Proposition

    Our Sustainability Value Proposition ENVIRONMENTAL STEWARDSHIP SOCIAL IMPACT • Responsibly transitioning to a cleaner and more diverse portfolio • Delivered value to customers in 2023 while focused on safety ‒ Target carbon reductions from 2005 levels: 60% by 2030; 85% by 2040; net ‒ Ameren-supplied

  7. Slide 7: Strong Track Record of EPS and Dividend Growth

    Strong Track Record of EPS and Dividend Growth Weather-Normalized Adjusted Dividends Paid per Share3 Total Shareholder Earnings per Diluted Share1 and Payout as a % of WN EPS Return $4.50 +112% or $2.80 ~+58% 2013 to 2023 $4.62 180% $4.25 ~7.8% CAGR 2013 to 2023 $4.41 $2.60 $2.68 | 58% , 2013 to 202

  8. Slide 8: Expect to Deliver Strong Long-Term EPS and Dividend Growth

    Expect to Deliver Strong Long-Term EPS and Dividend Growth • Expect 2024 adjusted1 EPS in a range of $4.55 to $4.692 – Midpoint represents 6.2% EPS growth compared to 2023 original guidance midpoint of $4.35 Long-term EPS • Expect 2025 EPS in a range of $4.85 to $5.052 – Midpoint represents 7.1% EPS

  9. Slide 9: Strategically Allocated Rate Base Growth

    Strategically Allocated Rate Base Growth1 Increased five-year infrastructure investment plan by $2.2B2 $21.9 Billion of Regulated Infrastructure Investment 2023 to 2028E Regulated Five-Year Rate 2024-2028 Infrastructure Rate Base3,4 Base CAGR4,5 Ameren Illinois ($ billions) Ameren Illinois $36.4 Ele

  10. Slide 10: Expected 2024-2028 Funding Plan

    Expected 2024-2028 Funding Plan1 • Cash from Operations – ~$2 billion of income tax deferrals and tax asset utilization • Income tax deferrals primarily driven by capital expenditures • Includes utilization of ~$60 million of federal and state tax credit carryforwards at year- end 2023 • 15% corpora

  11. Slide 11: Ameren Missouri New Generation on the Energy Grid

    Ameren Missouri New Generation on the Energy Grid Reliable, Affordable Energy Through a Cleaner Balanced Energy Portfolio Anticipated Energy Generation Agreement Facility Size Developer CCN Status In-Service Center Type Type Date Ameren Approved Mar. Vandalia1 50 MW Solar Self-Build Q4 2025 Missouri

  12. Slide 12: MISO Long-Range Transmission Planning Projects

    MISO Long-Range Transmission Planning Projects Enhancing Reliability and Lowering Customer Costs • MISO approved Tranche 2.1 projects estimated to cost $21.8 billion1 – Portfolio focuses on creating high-voltage transmission highways within the MISO region to maximize value based on land use, line d

  13. Slide 13: Robust Customer Growth Opportunities

    Robust Customer Growth Opportunities Facilitating Growth in Our Region While Delivering Value for All Customers • Robust pipeline of potential customers conducting formal engineering reviews Expanding Economic Development Pipeline of locations in our territory Represents Tens of Thousands of MW • At

  14. Slide 14: Investing in the Energy Grid

    Investing in the Energy Grid • Investing to modernize energy grid, making it cleaner, safer, more reliable, resilient and secure – Ameren Missouri Smart Energy Plan filed with the MoPSC supporting infrastructure investment to 2023-2028E Regulated modernize the grid Infrastructure Rate Base3 – Expect

  15. Slide 15: Robust Investment Opportunities Across All Businesses Over Next Decade

    Robust Investment Opportunities Across All Businesses Over Next Decade1 Modernizing the grid and investing in cleaner generation Investment Plan 2024-2028 $55B+ ($ billions) $21.9 Strong Pipeline of Regulated Infrastructure Investments $4.1 2024-2033 $1.8 • Modernize electric and gas transmission an

  16. Slide 16: Financial and Regulatory Updates

    Financial and Regulatory Updates Ameren Transmission Monopole Tower 2024

  17. Slide 17: 2024 Adjusted Earnings Analysis for Nine Months Ended Sep. 30

    2024 Adjusted3 Earnings Analysis for Nine Months Ended Sep. 30 ↑ Ameren Missouri earnings — Increased investments in infrastructure eligible for PISA and AFUDC: +$0.11 — New electric service rates effective July 9, 2023: +$0.09 Adjusted Diluted EPS2 — Higher electric retail sales: ~+$0.05 YTD Sep. 2

  18. Slide 18: 2025 Earnings Guidance: Key Drivers & Assumptions vs. 2024

    2025 Earnings Guidance: Key Drivers & Assumptions vs. 20241 Midpoint represents ~7% EPS growth compared to 2024 adjusted guidance midpoint of $4.62 ↑ New electric service rates effective by June 1 ↑ Higher investments in infrastructure eligible for PISA including rebased in new rates:~+$0.16 Ameren

  19. Slide 19: Missouri Regulatory Matters

    Missouri Regulatory Matters 2024 Missouri Electric Rate Review Filing • $446 million annual revenue increase request filed June 2024 with MoPSC Docket: ER-2024-0319 – Test year ended Mar. 31, 2024, with certain pro-forma adjustments through Dec. 31, Ameren 2024 MoPSC Staff - Key Components Missouri

  20. Slide 20: Illinois Regulatory Matters

    Illinois Regulatory Matters Electric Distribution Reconciliation for 2023 • In Dec. 2024, ICC approved a $158 million reconciliation adjustment to the 2023 revenue requirement reflecting actual Average Rate Base costs December 2024 Order vs. Proposed Positions – Based on 2023 year-end rate base of $

  21. Slide 21: Illinois Regulatory Matters (cont'd)

    Illinois Regulatory Matters (cont’d) Natural Gas Distribution • In Jan. 2025, requested a $140 million annual base rate increase – 2026 future test year – 10.7% allowed return on equity and 52% common equity ratio – $3.3 billion rate base; estimated year-end 2025 plus estimated average 2026 rate bas

  22. Slide 22: Credit Ratings and Financing Activity

    Credit Ratings3 and Financing Activity External Debt Balances Debt Financing Date Issuance Issuer Rate Type Maturity As of Sep. 30, 2024 $ in millions Moody's S&P (in 2024) ($M) Jan. 9 Ameren Missouri $350 5.25% First Mortgage Bonds 2054 Ameren Corporation (Issuer: Baa1/BBB+) Apr. 4 Ameren Missouri

  23. Slide 23: Summary

    Summary Expect 2024 adjusted diluted EPS to be in a range of $4.55 to $4.691 Expect 2025 diluted EPS to be in a range of $4.85 to $5.051 Successfully executing our strategy; well-positioned for future growth • Focused on delivering a reliable and sustainable energy future in a responsible manner Str

  24. Slide 24: Appendix

    Appendix Ameren Missouri’s Montgomery Community Solar Energy Center in service March 2022

  25. Slide 25: Four Regulatory Frameworks

    Four Regulatory Frameworks FERC-regulated: Formula ratemaking Ameren • Allowed ROE is 10.48%, including MISO participation adder of 50 basis points; ~56% average equity ratio Transmission • Rates reset each Jan. 1 based on forward-looking calculation with annual reconciliation ICC-regulated: Future

  26. Slide 26: Missouri Integrated Resource Plan filed with MoPSC Sep. 2023

    Missouri Integrated Resource Plan filed with MoPSC Sep. 20233 Least-cost approach to reliably meet customer energy needs in an environmentally responsible manner • Carbon emissions1: Targets substantial reductions; 60% by 2030, 85% by 2040 and net-zero by 2045 • Coal: All energy centers retired by 2

  27. Slide 27: Rush Island Energy Center Retirement

    Rush Island Energy Center Retirement • Rush Island Energy Center retired on Oct. 15, 2024 – Necessary transmission and system upgrades identified by the MISO grid reliability study nearing completion – 100% of impacted employees offered a new position within the company – Return on rate base, relate

  28. Slide 28: Ameren Illinois Electric Distribution Multi-Year Rate Plan Performance Metrics

    Ameren Illinois Electric Distribution Multi-Year Rate Plan Performance Metrics Adjustment / Metric Description Incentive (+/- bps) Improve System Average Interruption Duration Index (SAIDI) systemwide; improve interruption and 1. Reliability duration outages (SAIDI, SAIFI, CEMI, and CELID) in enviro

  29. Slide 29: Long-Term Debt Maturities and Interest Rates

    Long-Term Debt Maturities and Interest Rates Issuer 20241 2025 2026 2027 2028 $350 million 3.65% senior unsecured notes $450 million 2.50% $500 million 1.95% $450 million 1.75% Ameren Corp. senior unsecured notes senior unsecured notes senior unsecured notes $600 million 5.70% senior unsecured notes

  30. Slide 30: GAAP to Adjusted Earnings Reconciliation

    GAAP to Adjusted Earnings Reconciliation Three Months Ended Nine Months Ended Sep. 30, Sep. 30, (in millions, except per share amounts) 2023 2024 2023 2024 GAAP Earnings / Diluted EPS $ 493 $ 1.87 $ 456 $1.70 $ 994 $ 3.78 $ 975 $3.65 Charge for additional mitigation relief for Rush Island Energy Cen

  31. Slide 31: GAAP to Adjusted Earnings Per Share Reconciliations

    GAAP to Adjusted Earnings Per Share Reconciliations Year Ended Dec. 31, 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 GAAP Earnings / Diluted EPS $1.18 $2.40 $2.59 $2.68 $2.14 $3.32 $3.35 $3.50 $3.84 $4.14 $4.38 Exclude results from discontinued operations 0.87 — (0.01) — — — — — — — — Less

  32. Slide 32: Weather-Normalized Earnings per Share Reconciliations

    Weather-Normalized Earnings per Share Reconciliations Year Ended Dec. 31, 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Adjusted1 Diluted EPS $2.10 $2.40 $2.56 $2.68 $2.83 $3.37 $3.35 $3.50 $3.84 $4.14 $4.38 Ameren Missouri weather impact 0.03 0.05 (0.04) 0.16 (0.07) 0.43 0.04 (0.05) 0.02 0

  33. Slide 33: Ameren's Estimated Coal-Related Revenues in 2023

    Ameren’s Estimated Coal-Related Revenues in 2023 Return on Investment Revenues Cost Recovery3 Revenues $1.97B1 x $1.97B1 x ($98M x $466M + 51.9%2 x 48.1% x 25%) / (1 $171M x $131M + 9.59%2 = 3.93% = - 25%) 17%1 = $265M = $98M $37M $33M $29M $862M $7,500M 14% Return on Interest Tax Expense Property F

  34. Slide 34: Investor Relations Calendar

    Investor Relations Calendar JAN. 2025 FEBRUARY 2025 SUN. MON. TUES. WED. THUR. FRI. SAT. SUN. MON. TUES. WED. THUR. FRI. SAT. 1 2 3 4 ` 1 5 6 7 8 9 10 11 2 3 4 5 6 7 8 Evercore ISI Conf. 12 13 14 15 16 17 18 9 10 11 12 13 14 15 Quiet Q4 2024 Period Earnings Begins Conf. Call 19 20 21 22 23 24 25 16

  35. Slide 35: Select Regulatory and Legislative Matters

    Select Regulatory and Legislative Matters Missouri Public Service Commission • Pending electric rate review filling: Docket No. ER-2024-0319 • Order approving CCN for Castle Bluff Energy Center: EA-2024-0237 • Pending gas rate review filing: Docket No. GR-2024-0369 • Order approving multi-project CC

  36. Slide 36: Glossary of Terms and Abbreviations

    Glossary of Terms and Abbreviations AFUDC – Allowance for funds used during construction IRP – Integrated resource plan ATXI – Ameren Transmission Company of Illinois LRTP – Long Range Transmission Planning B – Billion LT – Long-term BOD – Board of Directors M – Million bps – Basis points MEEIA – Mi