  1. Slide 1: December 2024 Quarterly Update

    DECEMBER 2024 QUARTERLY UPDATE ASX Code: AMI 29 January 2025 rsonal use only

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS This presentation has been prepared by Aurelia Metals Limited (‘AMI’ or the ‘Company’). It should By its very nature, production and exploration for gold and base metals is a high risk business and is not rsonal use only not be considered as an offer or invitation to subsc

  3. Slide 3: December 2024 Quarter Highlights

    DECEMBER 2024 QUARTER HIGHLIGHTS Strong underlying operating performance rsonal use only Uplift in peak operating First concentrate from performance Federation ore Balance sheet strength Growth pathways maintained continue to be progressed DECEMBER 2024 QUARTERLY | 29 JANUARY 2025 | PAGE 3

  4. Slide 4: Group Production and Costs

    GROUP PRODUCTION AND COSTS Production and cost guidance on track rsonal use only Measure Unit Sep 24 Dec 24 Dec 24 FY25 Qtr Qtr YTD Guidance3 Gold produced koz 10.5 11.0 21.5 40 – 50 Copper produced kt 1.2 0.7 1.9 2.5 – 3.5 Zinc produced kt 2.3 3.8 6.1 14 – 20 Lead produced kt 3.1 4.2 7.3 13 – 19 Gr

  5. Slide 5: Sustainability

    SUSTAINABILITY Safeguarding our social licence to operate rsonal use only Group Total Recordable Injury Frequency Group Recordable Environmental Rate (TRIFR) - 12 month moving average Incident Frequency Rate (REIFR) - 12 month moving average 15 4 3 10 2 5 1 0 0 Sep-24 Dec-23 Dec-24 Mar-24 Jun-24 Dec

  6. Slide 6: Peak

    PEAK Development metres Executing to plan and guidance rsonal use only 915 • Development rate step change in progress 777 730 724 Mar 24 Qtr Jun 24 Qtr Sep 24 Qtr Dec 24 Qtr • Targeting further increase above 1,000m/qtr Mining unit cost / tonne • Mining unit costs trending lower 140 $134/t $129/t $1

  7. Slide 7: Federation

    FEDERATION Ramping up development and mining activity rsonal use only ✓ Mine development tracking ahead of plan ✓ Infill drilling continues to inform ramp-up profile ✓ Major surface works now complete ✓ Project remains within approved budget ✓ First concentrate production and sales Photo: Primary ve

  8. Slide 8: Exploration

    EXPLORATION Regional programs continue to focus on growth rsonal use only • Programs finalised at Kairos, Hercules, New Cobar and Jubilee North, all achieving significant copper intercepts1 • Surface drilling recommenced at Federation West (North Offset) to assess the potential for extension of the

  9. Slide 9: Developing Our Growth Options

    DEVELOPING OUR GROWTH OPTIONS Federation Mine rsonal use only • First concentrate production achieved1 • Ramp up to commercial production underway Great Cobar Study • Study work progressing • Final Investment Decision due this half Peak Plant Expansion • Permitting for throughput expansion progressi

  10. Slide 10: Balance Sheet

    BALANCE SHEET Consistent operating cash flow from Peak key to maintaining balance sheet strength rsonal use only Group cash A$M1 ~38 ~135 20.6 0.6 103.2 (19.2) 96.7 (2.7) (2.2) (2.4) (1.1) Sep-24 Peak Dargues Growth Exploration Corp, Tax, Care & Financing Dec-24 Loan Total cash bal. ops ops capital

  11. Slide 11: Key Focus Areas

    KEY FOCUS AREAS Focused on expanding margins, cash flows and developing copper growth options rsonal use only Ramp up Federation to commercial production Drive Peak development rates higher Maximise cash generation through volumes and costs Progress Peak expansion & Great Cobar studies to FID Explor

  12. Slide 12: Contact

    Photo: First concentrate from Federation ore, December 2024 rsonal use only CONTACT T: +61 7 3180 5000 E: office@aureliametals.com.au Level 17, 144 Edward Street BRISBANE QLD 4000 GPO Box 7 BRISBANE QLD 4001 aureliametals.com