Compania de Minas Buenaventura SAA — Compañía de Minas Buenaventura — Q2 2025 Earnings Presentation
11 slides from Compania de Minas Buenaventura SAA's earnings presentation, Jul 25, 2025
Slide 1: 2Q25 Earnings Results Conference Call
2Q25 Earnings Results Conference Call
Slide 2: Cautionary Statement
Cautionary Statement This presentation contains certain information that may constitute forward-looking information under applicable U.S. securities legislation, including but not limited to information about costs applicable to sales, general and administrative expenses; production volumes; current
Executing Our Strategy: Strong Performance, Growth and Financial Discipline EBITDA Direct Operations Consolidated Production (1) 2Q25 CAPEX related to In US$ millions 10.3 +28% San Gabriel was US$ 82M Cu (kton) 38% 13.2 38% 256 4.0 Cash Position: US$ 589M 39% 35% 202 Ag (MOz) 3.6 -11% Debt: US$ 860M
Free cash flow generation(1) 2Q25 Cash generation 2Q25 EBITDA to FCF reconciliation In US$ millions In US$ millions 134 130 648 -6 -110 -2 -26 -1 -82 506 52 -82 -0 -82 -121 -3 -2 -59 Operations Financing Dividends Final Cash flow Activities Received Cash 2Q25 Cash flow Beginning Investing Dividends
Slide 6: San Gabriel: Steady progress towards first gold bar in 4Q25
San Gabriel: Steady progress towards first gold bar in 4Q25 Highlights Project Milestones Commissioning plan in Commissioning Primary Water Filter Comm. 2Q25 CAPEX was implementation Plan Crusher CIL Dam Plant CompleteGold Bar US$ 82M 4Q24 1Q25 2Q25 3Q25 4Q25 Total cumulative CAPEX US$ 588M Team in
Slide 7: San Gabriel: 88% complete, preparing for ramp-up
San Gabriel: 88% complete, preparing for ramp-up Crushing area Processing Plant: Conveyor ✓ 100% progress of Primary Crusher mechanical works Milling area ✓ 100% progress of SAG and Ball mills mechanical works ✓ 98% progress of CIL tanks CIL tanks mechanical works Oxygen Plant 7
Slide 8: San Gabriel: 88% complete, preparing for ramp-up
San Gabriel: 88% complete, preparing for ramp-up Crushing area Milling area Oxygen Plant CIL tanks Processing Plant: ✓ 100% progress of Primary Crusher E&S works Conveyor ✓ 79% progress of SAG and Ball mills E&S works ✓ 88% progress of CIL tanks E&I works 8
Closing Remarks We are committed to our strategy: Stable and continuous production at our flagships. We are making 1 progress with optimization efforts to increase throughput and are continuously evaluating our operating portfolio. Exploration is part of our DNA: We are strongly committed to explora
Slide 11: Q&A
Bucnave NTURA Q&A
Source: 6ix earnings call
More decks from Compania de Minas Buenaventura SAA