man antam Corporate Overview antam

Slide 3: Antam At A Glance
Corporate Overview Antam At A Glance Sales Breakdown FY 2011 1% z Antam is a vertically integrated, export‐ Coal and Bauxite oriented, diversified mining and metals company 39% Gold, Silver 36% and Precious Ferronickel z We undertake all activities from Metals exploration, excavation, processing Ser

Slide 4: Business Strategy
Corporate Overview Business Strategy Focus On Core z Focus on segments that it knows best: Nickel, Gold and Bauxite Business z Adding value by moving away from selling raw materials and increasing processing activities z Expanding capacity to increase cash generation and lower unit Creating costs Su

Slide 5: Mine Operations
Corporate Overview Mine Operations Bauxite Ferronickel Location: Tayan Location: Pomalaa Coal Location: Sarolangun Exploration Unit and Head Nickel Ore Office Location: Pomalaa, Tapunopaka and Location: Jakarta Buli Logam Mulia Precious Metals Gold Gold Processing and Refinery Nickel Bauxite Locatio

Slide 6: Exploration Operations
Corporate Overview Exploration Operations IRON ORE BAUXITE (KALIMANTAN) GOLD (SULAWESI) GOLD (PAPUA) (KALIMANTAN) Location: Tayan, Munggu Pasir and Mempawah Location: Central Location: Mao, Batuisi, Karosa Location: Bintang and Landak (West Kalimantan) Kalimantan (West Sulawesi) and Mountains Activi

Slide 7: Significant Reserves and Resources in Strategic Locations
Corporate Overview Significant Reserves and Resources in Strategic Locations Saprolite Nickel Gold Ore ‘000 wmt ‘000 dmt 5,125 397350.0 4,834 4,450 4,246 306,300 317,200 4,058 3,838 3,026 2,940 155,450 125,800 145,300 947 887 55,100 56,400 50,350 54,200 2007 2008 2009 2010 1H2011 2007 2008 2009 2010

Slide 8: Corporate Performance
man antam Corporate Performance antam

Slide 9: Performance Highlights: Ferronickel
Performance Highlights Ferronickel Antam’s FY11 ferronickel production reached 19,690 TNi, exceeding the internal target of 18,000 TNi Antam’s FY11 ferronickel sales of 19,527 TNi was higher than the internal target of 18,500 TNi Ferronickel Production (TNi) Ferronickel Sales (TNi) 20,000 20,000

Slide 10: Performance Highlights: Nickel Ore
Performance Highlights Nickel Ore Antam’s FY11 nickel ore production amounted to 7.96 million wmt, higher than the internal target of 7.76 million wmt In 2011, nickel ore sales of 6.34 million wmt was higher than the internal target of 6.28 million wmt Nickel Ore Production (‘000 wmt) Nickel Ore

Slide 11: Performance Highlights: Gold
Performance Highlights Gold Antam’s gold production in 2011 amounted to 2,667 kg, or 88% of 2011 internal target of 3,025 kg. In 2011, gold sales volume reached 8,009 kg, higher than the internal target of 5,820 kg Gold Production (kg) Gold Sales (kg) 4,000 4,000 15,000 15,000 12,893 2,791 2,833

Slide 12: Financial Performance Highlights
Financial Performance Highlights Solid Revenue Healthy Margins Rp Bn 40 % Gross Margin Operating Margin Net Margin 12000 12,000 10,346 34 9,592 35 8,711 8,744 28 29 30 8000 8,000 22 25 19 19 19 20 15 14 14 4,000 4000 15 10 7 7 5 0 2008 2009 2010 2011 0 2008 2009 2010 2011 Strong Revenues Supported w

Slide 13: Development Roadmap
man antam Development Roadmap antam

Slide 14: Development Roadmap Overview
Development Roadmap Overview Location Processing / Smelting End Product Pomalaa Pomalaa FeNi Nickel Ore Buli FeNi Halmahera* Tapunopaka Mandiodo NPI* Nickel Pig Iron Pongkor Gold bars and Gold Ore Logam Mulia manufacturing Cibaliung product Chemical Grade Tayan Tayan CGA* Alumina Bauxite Ore Smelter

Slide 15: Downstream Development Projects
Development Roadmap Downstream Development Projects South Kalimantan Sponge Iron Project/Meratus Jaya Iron and Steel Ironmaking smelter Nickel Capacity: 315,000 tonnes of sponge iron pa Bauxite Completion: 2012 Estimated Project Cost: US$150 million Iron Antam Share: 34% (66% is owned by PT Krakatau

Slide 16: Tayan CGA Project
Development Roadmap Tayan CGA Project Groundbreaking of Tayan CGA Project Antam’s US$450 million Tayan CGA project will produce 300,000 tons of CGA per year for export to Japan and domestic consumption. CGA is used in the manufacturing process of high tech products such as IC chips and LCD scree

Slide 17: East Halmahera Ferronickel Project
Development Roadmap East Halmahera Ferronickel Project Groundbreaking of East Halmahera FeNi Project Project Location Location of the Project • Antam’s East Halmahera FeNi Project will add value to Antam’s On Site Activities vast nickel reserves through processing of saprolite nickel ores into 27,00

Slide 18: Key Strengths
ma antam Key Strengths antam

Slide 19: Key Strengths
Key Strengths 1 2 Significant Reserves High Quality and and Resources in Diversified Products and Strategic Locations Markets 8 3 Solid and Long Term and High Strong Operational and Quality Financial Performance Customer Base 7 4 Highly Experienced Vertically Integrated Management and Strong Operati

Slide 20: Thank You
antam Thank You antam

Slide 21: Disclaimer
Disclaimer This presentation and/or other documents have been written and presented by Antam. The materials and information in the presentations and other documents are for informational purposes only, and are not an offer or solicitation for the purchase or sale of any securities or financial instr
Source: Internet Archive copy of demo.antam.com
More decks from PT ANTAM (Persero) Tbk
H1 2024 Earnings Presentation18 slides · August 2024
Investor Presentation (2024)20 slides · 2024
9M 2023 Earnings Presentation19 slides · November 2023
Mandiri Investment Forum 202217 slides · Feb 10, 2022
Investor Presentation (March 2021)9 slides · Mar 8, 2021
Investor Presentation (November 2019)23 slides · November 2019