Sunrise Energy Metals Limited · ASX:SRL

Sunrise Energy Metals — Shareholder Meeting (October 2023)

18 slides from Sunrise Energy Metals's shareholder meeting presentation, October 2023

  1. Slide 1: Metals for the energy transition

    Metals for the energy transition Annual General Meeting October 2023

  2. Slide 2: Cautionary statement

    Cautionary statement Certain statements in this news release constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements involve known and unknown risks, uncertainties and other factors, which may cause actual results, pe

  3. Slide 3: Sunrise Project

    ~ > =="—s Sunrise Project - A 7]

  4. Slide 4: Sunrise Battery Materials Complex

    Sunrise Battery Materials Complex Resource Sunrise Ni-Co-Sc 1Mt Ni, 160kt Co and 30kt Sc deposit 50-year mine life (avg c. 1.75% NiEq yr 1-10) Development-ready Permitted, excellent community support BFS and piloting complete, mining lease granted Products Ni/Co sulphate and scandium C1 cash cost -$

  5. Slide 5: How Sunrise delivers value

    How Sunrise delivers value ESG Supply chain Geopolitics  Designed to run on 100% renewable  Integrated mining-to-refining reduces  Australia is a safe and stable power supply chain fragmentation and avoids jurisdiction for development offshore processing  Approximately 60% of the operation’s  G

  6. Slide 6: Large ore body with low mining risk

    Large ore body with low mining risk • A shallow deposit (40m depth) with simple, free- dig mining • Enough nickel and cobalt to support c. 1.2 – 1.6TWh of battery production capacity over the life of mine • A single ore body that can be processed with minimal ore transport 6 Scale illustration demon

  7. Slide 7: Bankable feasibility study results – first 25 years

    Bankable feasibility study results – first 25 years Annual Production1 Returns Capex and Payback Nickel: 21.3 ktpa NPV8: US$1.2 billion US$1.8 billion Cobalt: 4.4 ktpa IRR: 15.4% <5 years Cash Flow Cash Cost Mine Life EBITDA: US$10.8 billion Negative US$0.80/lb Ni after 50-year mine life Avg FCF (po

  8. Slide 8: Sunrise plant layout

    Sunrise plant layout • Conventional 4th Gen PAL design – numerous projects are being delivered successfully and quickly Refining • Sunrise design and engineering was supported by Fluor and ENFI as the Metal extraction lead FEED design and engineering contractors • The refinery incorporates a recycli

  9. Slide 9: Procurement and pre-construction activities

    Procurement and pre-construction activities • Procurement on long-lead items has commenced, with two autoclaves (>3mtpa capacity) delivered to Australia • Option to readily increase PAL feed by ~20% against current plan based on autoclave capacity • Capital for de-bottlenecking in Yr4 is estimated a

  10. Slide 10: Emissions profile

    Emissions profile Carbon intensity of nickel production (Scope 1-3) (kg CO2 / kg Nickel in sulphate) • Approximately 60% of Sunrise’s power requirements are Nickel Pig Iron (EAF) supplied from co-gen at the acid plant – the balance from renewable power Nickel Pig Iron (RKEF) • HPAL is relatively car

  11. Slide 11: By 2030 there will be approx. 200Mtpa of tailings waste from nickel hydromet operations

    • By 2030 there will be approx. 200Mtpa of tailings waste from nickel hydromet operations, in a region prone to earthquakes, high rainfall and direct community impacts • Local fisheries are already significantly impacted • The mining industry has been here before: Ok Tedi, Grasberg, Ramu, Bougainvil

  12. Slide 12: The US battery landscape by 2030

    The US battery landscape by 2030 By 2030: • there will be ~30 cell manufacturing plants in the US supporting auto assembly, • these plants will have a nameplate capacity of c. 980GWh pa, and • this supports production of 10m EVs annually, equivalent to total US light vehicle production in 2022 These

  13. Slide 13: Nickel and cobalt determines IRA eligibility

    Nickel and cobalt determines IRA eligibility Gr • The US Inflation Reduction Act (16%) grants up to $3,750 per electric vehicle as a tax rebate for batteries Cu (12%) containing a minimum % by value IRA Qualifying Percentages for Critical Minerals of “Constituent Materials” that are 2023 2024 2025 2

  14. Slide 14: Nickel is a problem for the US

    Nickel is a problem for the US • The US must acknowledge its geological constraints and prioritise Nickel ore reserves and mineral resources (mt contained Ni) • Exploration is important but will take decades to deliver – the US must work with its allies Australia 13.5 • Nickel laterite resources are

  15. Slide 15: The IRA – building a house with no foundations?

    The IRA – building a house with no foundations? North American EV supply chain spending announced since passage of Inflation Reduction Act ($ billion) Battery manufacturing 42.8 EV manufacturing 11.2 Battery component production 8.4 Multiple categories 4.4 Battery recycling 3.5 Raw materials 1.3 Sou

  16. Slide 16: Investment summary

    Investment summary Australia’s most advanced nickel-cobalt-scandium project with a 50-year mine life Fully integrated from mine to battery chemicals with an average annual metal-equivalent production of 21.3kt of nickel and 4.4kt of cobalt (as sulphate) Sustainably designed to operate on 100% renewa

  17. Slide 17: Corporate snapshot

    Corporate snapshot Board Senior Management Robert Friedland Jiang Zhaobai Sam Riggall Eric Finlayson Stefanie Loader Trevor Eton Ben Stockdale Melanie Leydin Co-chair & Non- Co-Chair and Non- Managing Director Non-Executive Lead Independent Non-Executive Chief Financial Company Secretary Executive D

  18. Slide 18: Corporate Investors

    Corporate Investors Ben Stockdale (CFO) Craig Sainsbury +61 3 9797 6700 craig.sainsbury@automiocgroup.com.au

Sunrise Energy Metals — Shareholder Meeting (October 2023) on 6ix