Cokal Limited · ASX:CKA

Cokal — Shareholder Meeting (November 2026)

17 slides from Cokal's shareholder meeting presentation, Nov 26, 2026

  1. Slide 1: Resilient in a tough year. Ready to grow…

    Slide 1: Resilient in a tough year. Ready to grow…

    ANNUAL GENERAL MEETING 2026 Resilient in a tough year. Ready to grow… Review of FY2026 (year ended 30 June 2026) and priorities for the year ahead Cokal Limited | ASX: CKA | ACN 082 541 437

  2. Slide 2: Important Information and Disclaimer

    Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer This presentation has been prepared by Cokal Limited (the Company or CKA). The information contained in this presentation is a professional opinion only and is given in good faith. The material in this presentation (“material”) is not and does not constitute an o

  3. Slide 3: Today's meeting

    Slide 3: Today's meeting

    AGENDA Today's meeting 1 Chairman's address Reflections on FY2026 and the road ahead 2 Assets and strategy Four Central Kalimantan projects and the BSN logistics arm 3 Market review 2026 metallurgical coal prices and the demand outlook 4 Operations review RKAB disruption, coal sales, 2027 production

  4. Slide 4: Chairman's address: Regulatory delays slowed progress, but foundations for growth are in place

    Slide 4: Chairman's address: Regulatory delays slowed progress, but foundations for growth are in place

    CHAIRMAN'S ADDRESS Regulatory delays slowed progress, but the foundations for growth are now in place “ Regulatory change The new annual RKAB approval process was the main source of delay. Cokal remained in compliance throughout. Coal prices have recovered significantly since last year and Non-dilut

  5. Slide 5: Four Central Kalimantan projects and a logistics arm, anchored by flagship BBM

    Slide 5: Four Central Kalimantan projects and a logistics arm, anchored by flagship BBM

    ASSETS AND STRATEGY Four Central Kalimantan projects and a logistics arm, anchored by flagship BBM TBAR BBP 75% 18,850 ha 60% 13,050 ha Exploration-stage project adjoining BBM's Production and Operation IUP valid to southern boundary. Stage 1 drilling plan June 2033, plus Exploration IPPKH and final

  6. Slide 6: Met coal prices strengthened through 2026 on supply disruption and India demand

    Slide 6: Met coal prices strengthened through 2026 on supply disruption and India demand

    MARKET REVIEW Met coal prices strengthened through 2026 on supply disruption and India demand Premium low vol coking coal price, 2026 (US$/t, FOB Australia)* PLV FOB Australia in Nov 2026, up ~US$261/t ~US$66/t on a year earlier 261 237 244 227 US$265/t PLV CFR China peak in late Jun 2026, highest s

  7. Slide 7: Mining restarted in FY2026, but two RKAB approval pauses interrupted the ramp-up

    Slide 7: Mining restarted in FY2026, but two RKAB approval pauses interrupted the ramp-up

    OPERATIONS REVIEW Mining restarted in FY2026, but two RKAB approval pauses interrupted the ramp-up OCT 2025 DEC 2025 JAN 2026 JUN QUARTER 30 JUN 2026 SEP – OCT 2026 1 2 3 4 5 6 New annual RKAB rule HML appointed Explosives magazine Phase 1 restart after Second suspension Phase 2 approved, approved R

  8. Slide 8: Coal sales resumed in FY2026, with further shipments targeted for November and December

    Slide 8: Coal sales resumed in FY2026, with further shipments targeted for November and December

    OPERATIONS REVIEW Coal sales resumed in FY2026, with further shipments targeted for November and December FY2026 Sales Oct – Nov Sales Nov -Dec Sales Domestic sales, plus first export shipment after Phase 2 RKAB approval received; operations Further domestic and export shipments targeted Phase 1 RKA

  9. Slide 9: Petrosea haul road earthworks are ahead of plan

    Slide 9: Petrosea haul road earthworks are ahead of plan

    OPERATIONS REVIEW Petrosea haul road earthworks are ahead of plan 633,763 m³ 154% 3 Mtpa 434k m³ Segment B earthworks achieved, Of planned volume (410,926 m³) Design capacity of the 96 km all- Jul–Oct 2026 output, 68% of the Dec-25 to Oct-26 over the same period weather pit-to-port haul road Dec-25

  10. Slide 10: 2027 production plan: ramp-up within approved RKAB volumes

    Slide 10: 2027 production plan: ramp-up within approved RKAB volumes

    2027 PRODUCTION PLAN 2027 production plan: ramp-up within approved RKAB volumes Subject to RKAB approval: The 2027 production plan is subject to approval of the 2027 RKAB. Actual production and sales will not exceed the volumes approved. Monthly production plan, 2027 (tonnes) Basis of the plan Cokin

  11. Slide 11: Three options could add tonnes beyond BBM's open pit: underground, BBM West and TBAR

    Slide 11: Three options could add tonnes beyond BBM's open pit: underground, BBM West and TBAR

    GROWTH PIPELINE Three options could add tonnes beyond BBM's open pit: underground, BBM West and TBAR BBM UNDERGROUND | PIT 1 BBM WEST BLOCK | PROPOSED TBAR | 75% OWNED Funded and operated by CBI Possible exploration upside Stage 1 drilling plan finalized Nil 40% 2027 Upside 50 holes 17 km Developmen

  12. Slide 12: TBAR: premium coking coal potential beside BBM, ready for exploration drilling

    Slide 12: TBAR: premium coking coal potential beside BBM, ready for exploration drilling

    TBAR EXPLORATION PLAN TBAR: premium coking coal potential beside BBM, ready for exploration drilling THE ASSET | 75% OWNED Coking coal potential beside BBM 58 70 km Coal outcrops mapped, To Batu Tuhup Jetty on seams to ~2 m BBM's haul road • 18,850 ha Exploration IUP in Murung Raya, Central Kalimant

  13. Slide 13: Exploration plan: staged drilling to define a Resource and support a Production IUP

    Slide 13: Exploration plan: staged drilling to define a Resource and support a Production IUP

    TBAR EXPLORATION PLAN Exploration plan: staged drilling to define a Resource and support a Production IUP DRILLING PROGRAMME | THREE STAGES EXPLORATION | Budget – Funding - Timeline ~156 holes, ~20,100 m in total ~4,500 m ~10,600 m ~5,000 m 01 02 03 Stage 1: ~50 holes, first Stage 2: ~10 deep holes

  14. Slide 14: FY2026 steady revenue generated despite the RKAB-related disruptions

    Slide 14: FY2026 steady revenue generated despite the RKAB-related disruptions

    FINANCIAL RESULTS FY2026 steady revenue generated despite the RKAB- related disruptions Revenue and other income Revenue/other income and net loss, five years to 30 June (US$M) US$3.74M FY2025: US$3.38M 9.8 11.0 9.8 9.3 Net loss for the year 7.1 US$11.0M FY2025: US$9.8M 3.7 3.4 3.7 Basic loss per sh

  15. Slide 15: Post financial year-end ICT amendments defer the US$20M capital repayment to January 2030

    Slide 15: Post financial year-end ICT amendments defer the US$20M capital repayment to January 2030

    BALANCE SHEET AND FUNDING Post financial year-end ICT amendments defer the US$20M capital repayment to January 2030 ICT amendments agreed after year end US$20M Capital Sum repayment deferred from 15 Jan 2027 to 15 Jan 2030 Deferred monthly fees pushed to 1 Jan 2028, accruing 10% p.a. interest ICT's

  16. Slide 16: Priorities for the year ahead: lift BBM output, finish the logistics backbone and add resources

    Slide 16: Priorities for the year ahead: lift BBM output, finish the logistics backbone and add resources

    OUTLOOK Priorities for the year ahead: lift BBM output, finish the logistics backbone and add resources Expand BBM Complete the Add tonnes and Secure sales and Growth options production infrastructure & resources funding under evaluation logistics backbone • Coal wash plant: under • Ramp up within a

  17. Slide 17: Cokal Limited

    Slide 17: Cokal Limited

    Cokal Limited Level 5, 56 Pitt Street, Sydney NSW 2000 +61 2 8823 3177 www.cokal.com.au