Cokal Limited · ASX:CKA

Cokal — Investor Presentation (August 2026)

21 slides from Cokal's investor presentation, Aug 13, 2026

  1. Slide 1: Investor Presentation August 2026

    For personal use only AUGUST 20 26

  2. Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer This presentation has been prepared by Cokal Limited (the Company or CKA). The information contained in this presentation is a professional opinion only and is given in good faith. The material in this presentation (“material”) is not and does not constitute an o

  3. Slide 3: Agenda

    Agenda 1 For personal use only Assets , Background & Market Overview 2 Key Highlights 3 BBM – Production, Infrastructure & Underground Update 4 TBAR – Geological Model, Drilling Exploration & Budget 5 BBM West Block – Data Summary & Exploration Plan

  4. Slide 4: Capital Structure and Market Snapshot

    COKAL | Capital Structure and Market Snapshot ASX-listed metallurgical coal developer — key market metrics For personal use only A SX C O D E SH A RE S O N I SSU E SH A RE P R IC E CKA A$0.06 1,078.9m as at 12th August 2026 M A RK ET C A P N ET DEB T EN T ER P RI SE V A L UE A$64.7m A$47m A$111.7m 1

  5. Slide 5: Indonesian Metallurgical Coal Platform

    COKAL | Indonesian Metallurgical Coal Platform 52,000+ ha | 4 metallurgical coal assets + integrated logistics | Central Kalimantan COKAL LIMITED For personal use only ASX: CKA BBM TBAR BSN BBP AAK 60% 75% 60% 75% 100% 14,980 ha 18,850 ha Logistics FL A GS HIP DE V EL O P M EN T 13,050 ha 5,000 ha E

  6. Slide 6: Strong Shareholders. Strategic Partners. Proven Execution.

    COKAL | Strong Shareholders. Strategic Partners. Proven Execution. A strategic ecosystem positioned to accelerate BBM from development to scaled production COKAL LIMITED For personal use only ASX: CKA L O N G- T E RM A L IGN E D S T RA T E G IC IN DO N E SI A N S HA R EH O L DE RS G L OB A L M E T C

  7. Slide 7: Management Overview

    Management Overview BBM 2 0 26 | EX EC U TI O N D ESP IT E IN DU ST RY - WI DE R KA B C O N ST RA I N TS Ramp-up under mining contractor; haul road upgrade with For personal use only Petrosea underway C ONTEXT Nationwide RKAB overhaul The Indonesian Government overhauled RKAB approvals in 2026, mate

  8. Slide 8: June Quarter 2026 – Key Highlights

    June Quarter 2026 – Key Highlights Quarterly report for the twelve months ending 30 June 2026, released 31 July 2026 BBM | Key Milestones Delivered For personal use only Revised RKAB 2026 RKAB A P P RO V E D A P P RO V E D Additional 2026 production allocation secured (post quarterly release Mining

  9. Slide 9: BBM Mining Operations

    BBM MINING OPERATIONS BB M | P RO D UC T IO N RA M P - U P For personal use only C Y2 02 6 2 02 7+ P ERM ITTE D Q 1 20 27 60–80kt 1.0Mtpa 6.0Mtpa¹ RKAB-constrained Fleet uplift Production ramp-up Approved capacity production; mining fleet Additional mining fleet towards the near-term underpinning lo

  10. Slide 10: BBM 3-Year Production Plan (2026–2028)

    BBM 3-Year Production Plan (2026–2028) Coking coal ramp-up with PCI product introduced from 2028 SALEABLE PRODUCTION BY YEAR (Kt) 900 Production Plan 2026 (Y01) 2027 (Y02) 2028 (Y03) 800 For personal use only OB Coking (bcm) 1,530,000 13,503,911 22,496,316 55 700 Coal Coking (t) 60,000 522,183 830,0

  11. Slide 11: Strategic Infrastructure – Mine-to-Market Platform

    Strategic Infrastructure | Building the Mine-to-Market Platform – Infrastructure Update Additional activities report – May 2026 P O R T L O G I S T I C S C O R R ID O R 96km pit-to-port haul road For personal use only 52km ALL-WEATHER HAUL ROAD 1 Currently accessible with further development and upg

  12. Slide 12: BBM Underground Mining – Preparation Update

    BBM Underground Mining – Preparation Update A NEW PRODUCTION PLATFORM TO SUPPORT BBM'S LONG-TERM GROWTH UNDERGROUND MINING | NEXT PHASE OF BBM GROWTH TRANSACTION RECAP For personal use only PARTNERSHIP PT Cipta Bersama Indonesia Tbk (CBI) — underground operation at Pit 1 of BBM, at zero cost to Coka

  13. Slide 13: TBAR Initial Geological Model, Potential Deposit & Target Drilling

    For personal use only SEC TION TBAR Initial Geological Model, Potential Deposit & Target Drilling Exploration Cokal 75% interest and project manager | 18,850 ha contiguous to BBM | Exploration plan August 2026

  14. Slide 14: TBAR – Initial Geological Model

    TBAR – Initial Geological Model ▪ Based on outcrop data, coal outcrops with thickness > 1m are interpreted as a single target seam similar to seam J in BBM, distributed from west to east and north-east. For personal use only ▪ 13 outcrops have been modelled; the model is built with a “normal” struct

  15. Slide 15: TBAR – Drill Plan Open Pit

    TBAR – Drill Plan Open Pit Open hole drilling, coring and geophysical logging – all holes suitable as points of measurement for JORC Resource estimation; drilling to commence once IPPKH exploration approvals are obtained For personal use only

  16. Slide 16: TBAR – Initial Pitshell Optimisation & Coal Structure

    TBAR – Initial Pitshell Optimisation & Coal Structure OPT Waste MBcm Coal MTon SR SCC050 18.24 1.2 14.98 For personal use only SCC040 25.07 1.5 17.13 SCC030 33.22 1.7 19.42 SCC020 40.11 1.9 21.16 SCC010 49.06 2.1 23.30 SCC000 65.67 2.5 26.71 SCC-010 74.84 2.6 28.42 SCC-020 91.32 2.9 31.26 SCC-030 10

  17. Slide 17: TBAR – Additional Underground Exploration Drillplan

    TBAR – Additional Underground Exploration Drillplan For personal use only

  18. Slide 18: BBM West Block

    For personal use only SEC TION BBM WEST BLOCK Exploration Data Summary & Forward Plan — August 2026 West Block 6,983 ha of the 14,980 ha BBM IUP | 86 coal outcrops identified

  19. Slide 19: BBM West Block – Block Area & Geological Setting

    BBM West Block – Block Area & Geological Setting KEY HIGHLIGHT — STRATEGIC JV OPPORTUNITY BBM is in discussions with a leading Indonesian conglomerate regarding a potential strategic joint venture to develop and operate the BBM West Block. The proposed partnership is aimed at accelerating developmen

  20. Slide 20: BBM West Block – Coal Quality & Exploration Plan

    BBM West Block – Coal Quality & Exploration Plan EXPLORATION PLAN ▪ Apply for the IPPKH exploration permit – the area is located on Restricted Production Forest; IPPKH exploration period is 2 years. For personal use only ▪ Topographic mapping across the West Block. ▪ Exploration drilling program for

  21. Slide 21: Cokal Ltd

    Cokal Ltd For personal use only SYDNEY JAKARTA Level 5, 56 Pitt Street The Bellezza Office Tower, 21 Floor, Unit 3 & 5 Sydney NSW 2000, Australia Arteri Permata Hijau, Jalan Mayjen Soepeno Kav 34 Domenic Martino — DMartino@cokal.com.au Permata Hijau, Kebayoran Lama Jakarta Selatan 10210, Indonesia K