  1. Slide 1: Q2-2025 Results

    Q2-2025 RESULTS 14 AUGUST 2025 www.amaroqminerals.com | AMRQ Amaroq Ltd. is a Greenland-focused mining company engaged in the identification, acquisition, exploration and development of gold and strategic metals properties in Greenland.

  2. Slide 2: Disclaimer and Technical Information

    DISCLAIMER AND TECHNICAL INFORMATION The information contained herein has been provided solely for information purposes and does not purport to be comprehensive or contain all the information that may be required by recipients to evaluate Amaroq Ltd (the “Company”). The presentation and the informat

  3. Slide 3: Q2 2025 Results Presenters

    Q2 2025 RESULTS PRESENTERS Eldur Olafsson Ellert Arnarson Ed Westropp CEO CFO Head of BD and Corporate Affairs Slide: 2 Amaroq: Q2 2025 Presentation

  4. Slide 4: Amaroq Minerals Today

    Malmbjerg Black Angel Mo/Cu AMAROQ MINERALS TODAY Zn/Ag/Pb The Premier Gateway to Greenland’s Resource Potential Disko Ni/Cu/PGE Skaergaard Au/Pd/Pt Nalunaq A/S Greenland Gold Production and Exploration Gardaq A/S Maniitsoq Strategic Minerals Ni/Cu/Co JV Suliaq ApS Mining and Logistical Services Kva

  5. Slide 5: Q2-2025 Highlights

    Q2-2025 HIGHLIGHTS Maiden revenue, significant operational progress at the Nalunaq mine and oversubscribed £45m fundraise Continuation of trial mining, First gold exports were Sequential improvement in on-going construction and completed in Q2, generating processing plant rates commissioning of the

  6. Slide 6: Q2 2025 Financial Results

    Q2 2025 FINANCIAL RESULTS Canadian $ Millions Q2 2025 Q1 2025 Capital Assets 200.8 183.5 - Construction in Progress 195.3 177.7 Prepaid expenses and others 10.2 9.0 Supplies Inventory 6.1 5.7 Metals Inventory 9.2 7.8 Escrow for Environmental Rehabilitation 7.3 7.1 6-month ended 3-month ended Selecte

  7. Slide 7: Liquidity and Assets

    LIQUIDITY AND ASSETS Canadian $ Millions 30 June 2025 31 March 2025 Cash on hand 86.0 16.7 Undrawn Credit Facilities 8.9 23.7 Trade payables and accrued liabilities (19.8) (17.0) Short Term Liquidity 75.1 23.4 Total Assets 342.0 252.1 Equity Ratio 80.0% 78.3% Investment in Gardaq Joint Venture 14.2

  8. Slide 8: Nalunaq A/S

    NALUNAQ A/S Commissioning of Greenland’s Newest Mine Mine Metrics 484koz Au 30g/t Au Updated Mineral Resource Resource Grade 151koz Au 300tpd Maiden Indicated Resource Targeted Mining Rate LHOS 150 - ~50% Mining Method Head Count (Greenlandic) ~350koz Au ~10 Years Historical Production Mine Life 30

  9. Slide 9: 2025 Exploration Programme Outline

    2025 EXPLORATION PROGRAMME OUTLINE MINTURN Cu/Au Exploration Towards Scout Resource Drilling Copper Belt Target Drilling Programme Generation UKALEQ GARDINER TARGET NORTH REE/Nb Exploration NANOQ TARGET WEST ILLERFISSALIK JOSVA VAGAR RIDGE EAGLE’S NEST STENDALEN Stendalen Cu/Ni/Co Exploration Naluna

  10. Slide 10: Creation of West Greenland Hub

    Additional Regional Growth Opportunities CREATION OF WEST GREENLAND HUB Au Au Located within an active high potential exploration district REE BLACK ANGEL Kangerluarsuk (Zn, Pb, Ag) Former producing high grade room and pillar mine with significant in situ infrastructure and >176,000m of core drillin

  11. Slide 11: Suliaq ApS – Formation of Specialist Mining Services

    SULIAQ APS – FORMATION OF SPECIALIST MINING SERVICES The Key Tools to Unlock Mineral Potential in a New Frontier Management team and Drill Rigs Board Epiroc/Sandvik Surface Equipment Mining Fleet 120-man Remote Marine Vessels Camps Amaroq: Q2 2025 Presentation

  12. Slide 12: Imeq ApS

    IMEQ ApS Project progressing to pre-feasibility publication in Q4-25 H2 2025 activities: • Request approval for Trial Pits (Jul 25) Nalunaq Mine Hydro Benefits • Trial pit investigations (Aug/Sep 25) CAPEX Investment into Greenland @45M DKK • Finalise Design • Solicit binding offers for turbine, gen

  13. Slide 13: Outlook

    OUTLOOK Good operational progress has continued into Q3-25 – de-risking full capacity by YE 25 Continued up-time in mine As a result of bringing Enhanced liquidity position forward certain construction development coupled with has enabled acceleration of processing rates of ~145 t/d and commissionin

  14. Slide 14: Q&A

    Q&A Slide: 13 Amaroq: Q2 2025 Presentation

  15. Slide 15: Contact Us

    www.amaroqminerals.com CONTACT US AMAROQ LTD 3400 One First Canadian Place, PO Box 130, Toronto, On, M5X 1A4, Canada Eldur Olafsson, Chief Executive Officer AIM, TSXV, Nasdaq: AMRQ