Irb Infrastructure Developers Limited · NSE:IRB

Irb Infrastructure Developers — Investor Presentation (September 2018)

36 slides from Irb Infrastructure Developers's investor presentation, September 2018

  1. Slide 1: Corporate Presentation September 2018

    Corporate Presentation September 2018

  2. Slide 2: Disclaimer

    Disclaimer This presentation has been prepared by IRB Infrastructure Developers Limited (the “Company”) solely for your information and for your use and may not be taken away, reproduced, redistributed or passed on, directly or indirectly, to any other person (whether within or outside your organiza

  3. Slide 3: Contents

    Contents Sr. No Particulars 1 Key Highlights for September 2018 quarter 2 Consolidated Financial Results as on September 30, 2018 3 Strong Financial track record 4 BOT Toll Revenue Comparative 5 Toll Performance 6 Other Operational BOT Projects 7 BOT Projects under implementation 8 BOT Project under

  4. Slide 4: Key Highlights during Q2FY2019

    Key Highlights during Q2FY2019* Revenue* EBITDA* PAT*# For Q2FY19 has gone up to Rs.14,854 mn For Q2FY19 has gone up to Rs 1,730 For Q2FY19 has gone up to Rs. 7,233 Mn from Rs. 12,416 Mn registering a growth of Mn from Rs. 1,311 Mn registering a from Rs. 6,153 Mn registering a growth of 20% over Q2F

  5. Slide 5: Consolidated Financial Results

    Consolidated Financial Results Amount in Rs Mn For the Period Ended September 2018 (Quarter) September 2017 (Quarter) Particulars Total All Segments Construction Segment BOT Segment Total All Segments Construction Segment BOT Segment Amt % Amt % Amt % Amt % Amt % Amt % Total Income 14,854.36 100.00

  6. Slide 6: Consolidated Financial Results

    Consolidated Financial Results Amount in Rs Mn For the Period Ended September 2018 (6 Months) September 2017 (6 Months) Particulars Total All Segments Construction Segment BOT Segment Total All Segments Construction Segment BOT Segment Amt % Amt % Amt % Amt % Amt % Amt % Total Income 30,686.76 100.0

  7. Slide 7: Consolidated Financial Results

    Consolidated Financial Results Amount in Rs Mn For the Period Ended September 2018 (Quarter) June 2018 (Quarter) Particulars Total All Segments Construction Segment BOT Segment Total All Segments Construction Segment BOT Segment Amt % Amt % Amt % Amt % Amt % Amt % Total Income 14,854.36 100.00 9,645

  8. Slide 8: Strong Financial Track Record Consolidated Financials

    Strong Financial Track Record Consolidated Financials Revenue EBITDA 70,000 35,000 31,715 59,691 58,628 60,000 30,000 27,874 28,480 52,551 50,000 25,000 23,247 39,605 Rs. in Mn 40,000 Rs.in Mn 20,000 30,687 15,153 30,000 15,000 20,000 10,000 10,000 5,000 - - FY 2015 FY 2016 FY 2017 FY 2018 H1FY2019

  9. Slide 9: Strong Financial Track Record Consolidated Financials

    Strong Financial Track Record Consolidated Financials Net Worth & ROE Net Debt & Net Debt to Equity Ratio BOT Assets Capital Employed & ROCE 235,000 219,551 218,976 221,666 210,000 185,000 171,632 160,000 143,879 Rs. in Mn 135,000 110,000 85,000 60,000 35,000 10,000 FY 2015 FY 2016 FY 2017 FY 2018 H

  10. Slide 10: BOT Toll Revenue Comparative

    BOT Toll Revenue Comparative Amount in Rs Mn Sr. Name of the Project FY 2015 FY 2016 FY 2017 FY 2018 Q2 - FY 2018 Q2 - FY 2019 H1 – FY 2018 H1 – FY 2019 No. 1 Mumbai - Pune BOT Project 5,673 6,331 6,819 9,016 2,134 2,148 4,412 4,457 2 Ahmedabad – Vadodara 1,566 2,187 3,309 3,808 865 982 1,781 2,024

  11. Slide 11: BOT Toll Revenue Comparative

    BOT Toll Revenue Comparative Amount in Rs Mn • Due to closure of Mumbra bypass, which acts as the last mile connectivity to NH 4 with NH3 and NH8, there has been significant diversion of heavy traffic since May 18. The Mumbra Bypass was remain closed up to mid of September 2018 and thereafter again

  12. Slide 12: BOT Toll Revenue Comparative

    BOT Toll Revenue Comparative Amount in Rs Mn 12

  13. Slide 13: Toll Performance (1/4)

    Toll Performance (1/4) Ahmadabad Vadodara Name of Ahmedabad  Interest rate successfully reduced by 2.25% to the Project Vadodara 9.25% on aggregate debt of Rs 33bn, resulting in Client NHAI Rs 0.7bn savings annually State Gujarat  Robust growth in traffic being witnessed which, Length of the Proje

  14. Slide 14: Toll Performance (2/4)

    Toll Performance (2/4) Agra Etawah Name of the Project Agra – Etawah  Effective 20th Jan 2018, Agra Lucknow Expressway has Client NHAI started tolling at concessionary rate of 75% State Uttar Pradesh Length (In Kms) 124.52  We are witnessing some bit of traffic diversion because Project Cost in Rs

  15. Slide 15: Toll Performance (3/4)

    Toll Perfomance (3/4) Solapur Yedeshi: Solapur Kaithal - Rajasthan  Project performing inline with expectation even with 93% Name of the Project Yedeshi Border tolling as on date.  Robust traffic mix as well as growth momentum bodes Client NHAI NHAI well for good return profile of the asset. State

  16. Slide 16: Toll Performance (4/4)

    Toll Performance (4/4) Kishangarh Name of the Project Udaipur Gujarat Border Gulabpura Chittorgarh Gulabpura Client NHAI NHAI NHAI State Rajasthan / Gujarat Rajasthan Rajasthan Project Cost in Rs. Mn 20,879 20,900 15,260 Debt / Unsecured Loan O/S as on 6,145 4,603 2,695 Sept 30, 2018 (Rs. Mn ) Premi

  17. Slide 17: Other Operational BOT Projects

    Other Operational BOT Projects Mumbai Name of the Project Thane Ghodbunder Pune - Solapur Pune - Nashik Pune Client MSRDC MSRDC MOSRT&H MOSRT&H State Maharashtra Maharashtra Maharashtra Maharashtra Length of the Project 206.0 14.9 26.0 29.8 (In Kms) Project Cost in Rs. 13,016 2,462 630 737 Mn Debt /

  18. Slide 18: BOT Projects Under Implementation

    BOT Projects Under Implementation Goa / Karnataka Border Yedeshi Name of the Project to Kundapur Aurangabad Client NHAI NHAI State Karnataka Maharashtra Length of the Project (In Kms) 189.6 189.1 Project Cost in Rs. Mn 28,390 33,770 Debt / Unsecured Loan Outstanding as on Sept 30, 2018 13,081 17,018

  19. Slide 19: BOT Project under Financial Closure Stage

    BOT Project under Financial Closure Stage Particulars Hapur Moradabad Name of the Project Six Laning of Hapur Bypass (Km 50.000) to Moradabad (Km 149.867) Section of NH 9 in the State of Uttar Pradesh (length 99.867 km) under NHDP Phase V on BOT (toll) Basis. Client NHAI State Uttar Pradesh Type of

  20. Slide 20: Financial Closure achieved for HAM Projects

    Financial Closure achieved for HAM Projects Rs in Mil Name of the Project Four laning of Puducherry (Km. Four laning of Poondiyankuppam Construction of Eight lane Vadodara Kim 29.000) to Poondiyankuppam (Km. (to Sattanathapuram (Design Ch. Expressway from Km 355.00 to Km 67.000) Section of NH-45A (N

  21. Slide 21: IRB's BOT Road Portfolio

    IRB’s BOT Road Portfolio BOT / HAM Portfolio – Km & Lane Km BOT / HAM Portfolio – State wise % Rajasthan 23% Haryana 8% Karnataka 9% Uttar Pradesh 15% Gujarat Tamil Nadu 13% 4% Maharashtra 28% BOT / HAM Portfolio – State wise Lane Km Lane KM under development 5,401 Lane Kms Lanes KM operational 3,34

  22. Slide 22: Strong EPC Order Book

    Strong EPC Order Book Order book As on Sept 30, 2018 Amount Order Book* Composition in Rs. Mn Ongoing BOT Projects 50,579 BOT/HAM Projects - Construction yet to commence 81,610 Total 132,189 •Order Book as of a particular date consists of unbilled revenue from the uncompleted portions of our “existi

  23. Slide 23: EPC Performance

    EPC Performance Revenue & YoY Growth PAT and Return Ratios EBITDA & Margin Networth and D:E Ratio Figures for H1FY 2019 are not annualized. 23

  24. Slide 24: Equity Commitment

    Equity Commitment Amount in Rs Mn FY 2019 FY 2020 FY 2021 Name of the Project Estimated Estimated Estimated Agra Etawah 3,108 - - Udaipur - RJ Border 953 1,866 - Gulabpura - Chittorgarh 207 2,000 - Kishangarh - Gulabpura 767 1,957 - Hapur Moradabad 2,908 5,161 3,285 Puducherry Poondiankuppam 142 525

  25. Slide 25: Growth Strategy

    Growth Strategy Bharatmala Pariyojana: Strong growth envisaged till FY 2022  ~Rs 5tn of total investment for developing 34,800km of roads lined up over the next 4-5 years  Of this Rs1.2tn would come from PPP, Rs 2tn from market borrowings and balance Rs ~2tn from Budgetary allocation/ToT/CRF/Toll

  26. Slide 26: Company Overview

    Company Overview IRB Group  IRB Infrastructure Developers Limited (“IRB”) incorporated in 1998, has strong in-house integrated execution capabilities  One of the leading Infrastructure Development company in India in road and highway sector  Group has successfully executed numerous BOT projects i

  27. Slide 27: Key Competitive Advantage

    Key Competitive Advantage One of the largest BOT Project Portfolio in the Roads IRB InvIT : 17 BOT projects out and Highways perpetual of which 11 are Sector being tolled, opportunity to and balance are recycle capital and under various monetize assets phases of Key development Competitive Professio

  28. Slide 28: Roadmap So Far

    Roadmap So Far  First ever Airport Project in  Awarded 2 Nos. of Six Achieved Financial Closure for HAM Projects IRB’s portfolio Laning Projects of – 4 Laning of Puducheery to Poondiyankuppam – Greenfield Airport Project Section of NH-45A in Sindhudurg, NHAI on DBFOT – 4 Laning of Poondiyankuppam

  29. Slide 29: The "IRB" Group

    The “IRB” Group IRB’s BOT Road Projects Sr. Length Company Road Name No. in Km 1 Aryan Toll Road Pvt. Ltd. Pune – Sholapur BOT 26.00 2 ATR Infrastructure Pvt. Ltd. Pune – Nashik BOT NH 50 29.81 100% 3 Mhaiskar Infrastructure Pvt. Ltd. Mumbai – Pune BOT MPEW & NH4 206.00 14 BOT Projects 4 Thane Ghodb

  30. Slide 30: Organization Structure

    Organization Structure Board of Directors Mr. Virendra D. Mhaiskar Chairman and Managing Director Mrs. Deepali V. Mhaiskar Mr. Mukesh Gupta Mr. Sudhir Hoshing Executive Director Joint Managing Director Joint Managing Director Mr. Chandrashekhar S. Kaptan Mr. Sunil H. Talati Mr. Sandeep Shah Mr. Suni

  31. Slide 31: Organization Structure

    Organization Structure Statutory Auditors Mr. Rajkamal R. Bajaj Internal Auditors Suresh Surana & Associates LLP BSR & Company LLP Advisor to the Board Chartered Accountants Chartered Accountants Joint Statutory Auditors Bankers / Lenders of IRB Group Gokhale & Sathe Andhra Bank Canara Bank Chartere

  32. Slide 32: Shareholding Pattern

    Shareholding Pattern Shareholding Pattern as On September 30, 2018 Name Percentage (%) Promoter 57.37 Promoter Group 0.17 FII / EPI 21.14 DII 13.28 Others 8.04 Total 100.00 Shareholders holding more than 1% shares as on September 30, 2018 Name Percentage (%) Government of Singapore 4.40 Aditya Birla

  33. Slide 33: Corporate Recognition

    Corporate Recognition IRB has been awarded CNBC TV 18 Essar Steel Infrastructure Excellence Award in the Highways & Flyovers category for Mumbai - Pune section of National Highways (NH-4). This award was in recognition of the high quality work implemented on the development and maintenance of the Mu

  34. Slide 34: Corporate Recognition

    Corporate Recognition This award was won by IRB for being the ideal This award was won companies to work for by the company for infrastructure sector in India having employee acknowledging its business friendly policies, operations, quality of its respect for dignity of management, concern for emplo

  35. Slide 35: Our CSR Initiative

    Our CSR Initiative We have replicated same model and have started a We also generously school in the Pathankot district of Punjab, near the contributed to the Amritsar- Pathankot BOT project. Chief Minister’s drought relief fund in Maharashtra. The School building was inaugurated on 27 March 2017.Th