Aker BP ASA · OSL:AKRBP
Aker BP ASA — Investor Presentation (November 2023)
56 slides from Aker BP ASA's investor presentation, November 2023

Slide 1: Investor presentation
Investor presentation November 2023 Aker BP

Slide 2: Disclaimer
Disclaimer This Document includes and is based, inter alia, on forward-looking information and statements that are subject to risks and uncertainties that could cause actual results to differ. These statements and this Document are based on current expectations, estimates and projections about globa

Slide 3: Contents
Contents Page 4 Company overview Page 9 Oil & gas will remain a crucial part of the energy mix Page 11 Our strategic priorities Page 12 Operate safely and efficiently Page 16 Decarbonise our business Page 22 Deliver high return projects on quality, time and cost Page 35 Establish the next wave of pr

Slide 4: Aker BP's investment proposition
Aker BP’s investment proposition The E&P company of the future ✓ World-class assets with high efficiency and low cost ✓ Low emissions and clear pathway to net zero ✓ Driving transformation through digital and alliances ✓ Profitable growth from unique resource base ✓ Financial strength & growing divi

Slide 5: World-class oil and gas portfolio
World-class oil and gas portfolio Large scale, low risk assets on the Norwegian Continental Shelf 2P reserves1 2C resources1 Production2 arstad 1.86bn 0.74bn 455-465 boe boe mboepd Sandnessj en Skarv Trondheim Johan Sverdrup Edvard Grieg / Ivar Aasen Valhall area Partner, 31.6% Operator, ~35-65% Ope

Slide 6: The making of a NCS champion
The making of a NCS champion Aker BP oil and gas production, boepd 500 000 ~460k Growth through M&A 400 000 18 organic project developments since 300 000 2016 200 000 100 000 Leading the industry transformation as the 0 E&P company of the future Q3-17 Q1-14 Q2-14 Q3-14 Q4-14 Q1-15 Q2-15 Q3-15 Q4-15

Slide 7: Reserves and resources
Reserves and resources Year-end 2022 2P oil and gas reserves 2C contingent resources Discoveries Skarv 7% Alvheim Area Area 6% 8% Alvheim Area Non-op 8% 26% Johan Sverdrup Grieg/Aasen 35% Area 11% Grieg/Aasen Area 1,859 mmboe 14% 744 mmboe Yggdrasil 20% Yggdrasil Valhall Area 17% 27% Valhall Area 21

Slide 8: Large value creation to shareholders
Large value creation to shareholders Index 1000 900 >650% shareholder 800 return last 10 years 700 600 >22% annual 500 investor return 400 Index of US oil companies 300 200 100 Index of European oil companies 0 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 Source: Bloomberg, Total Shareholder Re

Slide 9: Oil & gas will remain a crucial part of the energy mix
Oil & gas will remain a crucial part of the energy mix Total energy supply (IEA WEO 2022) Stated policies scenario Announced pledges scenario Net zero emissions by 2050 scenario 2010 2020 2030 2040 2010 2020 2030 2040 2010 2020 2030 2040 Oil Natural gas Coal Nuclear Renewables Oil Natural gas Coal N

Slide 10: Our contribution as a pure play E&P company
Our contribution as a pure play E&P company Maximize Minimize Share technology value emissions and knowledge for shareholders and the society from our operations to enable new industries while producing the energy the world needs 10

Slide 11: Our strategic priorities
Our strategic priorities Aker BP leads the industry transformation as the E&P company of the future Deliver high return Establish the next Operate safely Decarbonise projects on quality, wave of profitable and efficiently our business time and cost growth options Return maximum value to our sharehol

Slide 12: Operate safely and efficiently
Operate safely and efficiently 12

Slide 13: Safety is our priority number one
Safety is our priority number one Injury frequency (TRIF) 1.9 1.8 1.6 1.6 1.6 1.6 1.3 1.1 1.1 Q3-21 Q4-21 Q1-22 Q2-22 Q3-22 Q4-22 Q1-23 Q2-23 Q3-23 TRIF: Total recordable injuries per million exp. hours, rolling 12 months average 13

Slide 14: High production and low cost
High production and low cost Production of oil & gas Production cost 1,000 barrels oil equivalent per day (mboepd) USD per boe 481 453 450 432 412 7.3 7.2 7.2 6.0 5.6 Q3-22 Q4-22 Q1-23 Q2-23 Q3-23 Q3-22 Q4-22 Q1-23 Q2-23 Q3-23 Base opex Tariff & transport Projects Power & environment tax Johan Sverd

Slide 15: Strong performance at Johan Sverdrup
Strong performance at Johan Sverdrup A giant field with excellent reservoir properties Daily oil production since start-up of Johan Sverdrup 755,000 bblpd ▪ Successfully executed development phase 2 ▪ Oil production capacity successfully tested to 755 mbblpd ▪ Long field life (+50 yrs) and a future

Slide 16: Decarbonise our business
#AkerBP Decarbonise our business 16

Slide 17: Aker BP's decarbonization strategy to net zero
Aker BP’s decarbonization strategy to net zero Net zero across operations by 2030 Aker BP’s targets Scope 1 + 2 Scope 3 1. Carbon intensity <4 kg CO2e/boe Avoid Reduce Neutralise Upstream scope 3 reduction through procurement 2. Methane intensity < 0.1 % Support new industries 3. Scope 2 emissions ~

Slide 18: Strong progress on decarbonisation
Strong progress on decarbonisation Continued progress on decarbonisation Main drivers for the reduction Aker BP emission intensity, kg CO2e/boe ▪ Increased ownership in low-emission assets 5.3 following the Lundin transaction 3.8 ▪ Edvard Grieg and Ivar Aasen electrified as part of 3.2 Johan Sverdru

Slide 19: Aker BP – a global leader in low CO2 emissions
Aker 160 BP – a global leader in low CO2 emissions 140 Net emission intensity, 2022 120CO /boe equity share Kg 2 100 80 60 40 20 1 0 1 50 100 150 200 250 300 300 largest producing upstream companies 19

Slide 20: Clear pathway to reduce absolute emissions close to zero
Clear pathway to reduce absolute emissions close to zero Aker BP high level CO2 emissions forecast of operated assets Gross operated scope 1&2 emissions Million t CO2 Electrification Electrification of Retirement of Retirement of All producing 1.8 of Valhall Grieg/Aasen Ula² Skarv/Alvheim² assets el

Slide 21: Evaluating CO2 storage opportunities on the NCS
Evaluating CO2 storage opportunities on the NCS Potential new business opportunity and a potential decarbonisation lever for Aker BP longer term ▪ Carbon capture and storage (CCS) expected to play a key Illustrational outline of Poseidon storage concept role in the transition to a low-carbon energy

Slide 22: Deliver high-return projects on quality, time and cost
Deliver high-return projects on quality, time and cost 22

Slide 23: Aker BP project overview
Aker BP project overview 770 mmboe net oil and gas volume at net capex after tax of around USD 3 billion Aker BP Production Asset area Field development Gross/net volume Net capex estimate PDO submission ownership start Frosk 80.0% 10/8 mmboe USD 0.2bn 2021 2023 Alvheim Kobra East & Gekko 80.0% 50/4

Slide 24: Project execution progressing according to plan
Project execution progressing according to plan ▪ Key milestones achieved on schedule ▪ Main contracts awarded and capacity secured ▪ Project execution on track with fabrication underway at multiple locations ▪ No serious HSSEQ incidents ▪ Total capex estimate in line with plans Construction of Yggd

Slide 25: Yggdrasil
Yggdrasil New North Sea area hub by joining forces across licences Aker BP Hugin: 87.7% Gas ~40% of (operator) Munin: 50.0% estimated volumes Fulla: 47.7% Partners Equinor and Power supply PGNiG Upstream Norway from shore Munin Unmanned production platform Volume estimate 650 mmboe (gross) / Hugin A

Slide 26: Valhall PWP-Fenris
Valhall PWP-Fenris Unlocks new volumes and secures life-time extension on Valhall PWP WP/IP PH Aker BP Valhall: 90.0% Establishes Valhall (operator) Fenris: 77.8% as area gas-hub Partners PGNiG Upstream Norway Power supply and Pandion from shore Valhall Volume estimate 230 mmboe (gross) / Minimal em

Slide 27: Skarv Satellites
Skarv Satellites Investments in future flexibility enabling further area development Aker BP Alve North: 68.1% Gas ~70% of (operator) Idun North: 23.8% estimated volumes Ørn: 30.0% Partners Equinor, Wintershall DEA Low operational and PGNiG Upstream cost Norway Volume estimate 119 mmboe (gross) / Lo

Slide 28: Utsira High projects
Utsira High projects Increased capacity utilisation at Ivar Aasen and Edvard Grieg platforms Aker BP Solveig Phase II: 65.0% Adds low-cost (operator) Symra: 50.0% production Hanz: 35.0% Partners Equinor, OMV, Unlocks potential Wintershall Dea and future developments Sval Energi Solveig Volume estima

Slide 29: Alvheim projects
Alvheim projects Unlocks new volumes, reduces unit cost and secures life-time extension on Alvheim Aker BP Frosk: 80.0% Tie-backs to existing (operator) KEG: 80.0% infrastructure Tyrving: 61.3% Accounts for ca. 50% Partners Vår Energy, of net Alvheim ConocoPhillips, Petoro, volumes in 2024/25 PGNiG

Slide 30: Grow production by executing our projects
Grow production by executing our projects Planning to produce around 525 mboepd in 2028 Production outlook PDOs submitted mboepd ~525 ▪ Net resources of 770 mmboe 24% ▪ The projects lift Aker BP’s production by 250-300 mboepd in 2028 PDOs 17% ▪ Low CO2 emission intensity ▪ Full-cycle portfolio break

Slide 31: Aker BP's key principles for successful project execution
Aker BP’s key principles for successful project execution Partnerships Frontloading Standardisation ✓ Competence and learning ✓ Early planning and maturation ✓ Well designs and equipment ✓ Continuity ✓ Supplier involvement ✓ Topside and subsea equipment ✓ Common goals and incentives ✓ Secured yard a

Slide 32: Alliances with leading suppliers – with proven track record
Alliances with leading suppliers – with proven track record The cornerstone of project planning and execution Alliances established with leading suppliers ▪ Covering majority of capital spend ▪ Subsea, Fixed Facilities, Modifications and Drilling ▪ One team - Common goals - Shared incentives Organis

Slide 33: Execution through alliances and incentive-based contracts
Execution through alliances and incentive-based contracts Capacity secured with alliance partners The PDOs …with the majority of work performed …and compensation formats that incentivise in December… by the alliance partners… productivity and cost reductions 100% Skarv satellites Other facilities, L

Slide 34: Signed contracts with all major yards in Norway
Signed contracts with all major yards in Norway Close and early collaboration to ensure capacity, construction quality and efficiency Aker Solutions Stord Aker Solutions Verdal Aker Solutions Egersund Aker Solutions Sandnessjøen ▪ PWP Topside Fabrication/Integration ▪ Fenris Topside and Jacket ▪ Hug

Slide 35: Establish the next wave of profitable growth options
Establish the next wave of profitable growth options 35

Slide 36: Exploration strategy
Exploration strategy Licence map Uniquely positioned on the NCS Aker BP operator ▪ 2nd largest in Norway with ~200 licences Aker BP partner ▪ Operator for ~70% Targeting 250 mmboe by 2027 ▪ Drill 10-15 exploration wells per year ▪ 80/20 near-field/new areas New ways of working ▪ Combining two strong

Slide 37: Significant 2023 oil discovery in the Yggdrasil area
Significant 2023 oil discovery in the Yggdrasil area Øst Frigg will be an integrated part of ongoing project development ▪ Current volume estimate of 53-90 mmboe, twice as large as the original pre-drill estimate ▪ Increases the resource base for the Yggdrasil project by around 10% ▪ Strong field ec

Slide 38: 2023 exploration program
Ferdinand 2023 exploration program Licence Prospect Operator Aker BP Pre-drill Status share mmboe PL867 Gjegnalunden Aker BP 80% 3-9 mmboe PL1141 Styggehøe Aker BP 70% Dry PL554 Angulata Equinor 30% Dry PL919 Ve Aker BP 80% 3-5 mmboe PL873/442 Øst Frigg Beta/Epsilon Aker BP 48%/88% 54-90 mmboe PL114

Slide 39: Significant upside potential around existing assets
Significant upside potential around existing assets Reserves and resources billion boe 4.0 ▪ Skarv: Exploration opportunities (ILX) and ILX potential, development of tight reservoirs net risked ▪ Edvard Grieg/Ivar Aasen: Infills, ILX and 3.0 basement upside enabled by 4D seismic 3P reserves ▪ Johan

Slide 40: Return maximum value to our shareholders and our society
Return maximum value to our shareholders and our society 40

Slide 41: Capital allocation priorities
Capital allocation priorities Aker BP’s financial frame – designed to drive value creation and shareholder return 1 Financial capacity 2 Profitable growth 3 Return value Maintain financial flexibility and Invest in robust projects Resilient dividend growth in line investment grade credit rating with

Slide 42: Optimising our capital structure
Optimising our capital structure Bond transactions in June 2023 Bond maturities USD/EUR billion ▪ USD 1,500 million in new Senior Notes issued ▪ USD 0.5 billion aggregate principal amount of 5.60% Senior 1.75 Notes due in 2028 ▪ USD 1.0 billion aggregate principal amount of 6.00% Senior Notes due in

Slide 43: Maintaining financial flexibility
Maintaining financial flexibility Net interest-bearing debt Leverage ratio1 Liquidity available2 Excl. leases, USD billion USD million 4 6.7 6.8 3.1 6.4 3 6.2 6.1 2.5 1.5 1.5 1.5 3 2.4 2.2 2.0 1.2 1.2 2 2 0.9 1 0.6 0.5 3.3 3.4 3.0 2.8 0.3 2.7 1 0.2 0.2 0.2 0.2 0.2 0.1 0 Q3-22 Q4-22 Q1-23 Q2-23 Q3-23

Slide 44: Grow production with robust high return projects
Grow production with robust high return projects Production outlook, mboepd Robust and profitable project portfolio ~525 $35-40/bbl 500 455-465 400 Project portfolio break-even oil price 300 ~25% 200 Project portfolio IRR at $65/bbl oil price 100 1-2 years - 2016 2018 2020 2022 2024 2026 2028 Projec

Slide 45: Investing in robust and profitable projects
Investing in robust and profitable projects In an investment-friendly tax system Aker BP est. capex before and after tax USD billion 6 ▪ Around 85% of the planned capex is related 5 to projects subject to the temporary tax system with 86.9% tax deduction 4 ▪ The rest is subject to ordinary tax syste

Slide 46: The Norwegian petroleum tax system
The Norwegian petroleum tax system Supportive for investments Ordinary tax system Temporary tax system ▪ The temporary tax system 100.0 100.0 was introduced summer 1.0 1.0 1.0 1.0 86.9 2020 to stimulate 81.7 1.0 1.0 1.0 1.0 1.0 78.0 investments1) 72.8 1.0 ▪ Applicable for projects with PDO submitted

Slide 47: Strong and resilient cash flow as basis for dividend growth
Strong and resilient cash flow as basis for dividend growth Aker BP value creation plan 2023-2028 Dividends USD billion, accumulated USD per share 2.5 2.20 ▪ Low-cost production gives 2.08 20 $90/bbl 2.00 resilient dividend capacity 2.0 ▪ Distributions shall reflect the 15 capacity through the cycle

Slide 48: 2023 guidance
2023 guidance Previous Actual New guidance YTD-23 guidance Production 445-470 461 455-465 mboped Production cost 6.0-7.0 6.2 6.0-6.5 USD/boe Capex 3.0-3.5 2.2 3.0-3.5 USD billion Exploration 0.4-0.5 0.3 0.4-0.5 USD billion Abandonment 0.1-0.2 0.13 ~0.2 USD billion 48

Slide 49: Third quarter 2023
Third quarter 2023 27 October 2023 Aker BP ASA

Slide 50: Highlights
Highlights Third quarter 2023 Good operational performance ▪ Low cost and low emissions ▪ Maintenance activities impacted production volume Project developments on track ▪ Schedule and cost estimates reiterated ▪ KEG in production five months ahead of plan Strong cash flow ▪ Higher realised prices a

Slide 51: Sales of oil and gas
Sales of oil and gas Volume sold Realised prices Total income mboepd USD/boe USD million 4 866 477 281 450 450 428 69 407 60 66 3 816 66 1 666 64 3 513 3 310 3 291 914 336 582 399 150 409 390 99 384 342 362 88 77 3 182 3 140 101 2 887 2 712 2 858 87 78 64 60 Q3-22 Q4-22 Q1-23 Q2-23 Q3-23 Q3-22 Q4-22

Slide 52: Income statement
Income statement USD million Q3 2023 Q2 2023 450 mboepd (477) Total income 3 513 3 291 Oil and gas sales Production costs 252 247 Other operating expenses 12 13 EBITDAX 3 249 3 031 $84 per boe (75) Exploration expenses 74 27 Net realised price EBITDA 3 174 3 004 Depreciation 557 645 Impairments Oper

Slide 53: Cash flow
Cash flow USD million Operating cash flow before tax Q3-23 2 963 Q2-23 2 938 Q1-23 3 251 Q4-22 3 762 $1.2 bn (-0.7) Taxes paid (862) (2 817) (1 569) (2 995) Free cash flow (FCF) Cash flow – operations 2 101 121 1 682 807 Cash flow – investments (944) (776) (705) (708) $1.83 (-1.04) Free cash flow 1

Slide 54: Tax payments
Tax payments Sensitivity for H1-2024 USD million Tax instalments for fiscal year 2023 set in June 2 500 ▪ Q3 and Q4-22 instalments fixed ▪ Based on forecast full-year 2023 performance 2 000 ▪ Opportunity to adjust in Oct-23 and Jan-24 Additional $100/bbl payment 1 500 Adjustment in October 2023 ▪ Fu

Slide 55: Balance sheet
Balance sheet USD million Assets 30.09.23 30.06.23 30.09.22 PP&E 16 123 16 218 restated 15 307 $6.8 bn ($6.1) Goodwill 13 554 13 554 13 193 Total available liquidity Other non-current assets 3 166 3 248 3 057 Cash and equivalent Other current assets 3 375 1 909 2 689 1 603 3 042 2 015 33% (33%) Tota

Slide 56: www.akerbp.com
AkerBP www.akerbp.com
Source: Internet Archive copy of akerbp.com
More decks from Aker BP ASA
Q3 2026 Earnings Presentation21 slides · Oct 29, 2026
Investor Presentation (October 2026)69 slides · October 2026
Investor Presentation (July 2026)81 slides · Jul 15, 2026
Q2 2026 Earnings Presentation25 slides · Jul 15, 2026
Q1 2026 Earnings Presentation24 slides · May 7, 2026
Q4 2025 Earnings Presentation71 slides · Feb 11, 2026