  2. Slide 2: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  3. Slide 3: Regulatory & Shareholding Structure

    INTRODUCTION TO TENAGA Regulatory & Shareholding Structure REGULATORY & SHAREHOLDING STRUCTURE PRIME MINISTER / CABINET Sabah Electricity Sdn Bhd (SESB) (83% owned by TNB) Dependable Capacity: Shareholders Policy Maker 1,223MW Tenaga Nasional Bhd (TNB) Holds Ministry of Energy and Ministry of Financ

  4. Slide 4: Regulated & Non-Regulated Business

    INTRODUCTION TO TENAGA Regulated & Non-Regulated Business Generation Grid/Transmission Distribution Network & Retail Non-Regulated Business Regulated Business TNB Generation Mix: Installed Capacity: Distribution Network Length: Core Business 25,414MW Transmission Network Length: 683,008KM Oil & Dist

  5. Slide 5: TNB Sectoral Sales Analysis

    INTRODUCTION TO TENAGA TNB Sectoral Sales Analysis* Total Unit Sold 53,535.7 GWH 0.9% 1.7% 2.1% Total 25.0% 28.8% Assets RM174.3bn 81.8% Total 37.9% 32.1% TNB: 9.3mn Customers SESB: 0.6 mn Total 35.3% 37.0% Employees 35,878 17.1% 0.3% NO O F C USTO ME R SA LES (RM) SA LES (G W H) Industrial Commerci

  6. Slide 6: Electricity Demand in line with GDP Growth

    INTRODUCTION TO TENAGA Electricity Demand in line with GDP Growth GDP & TNB (Peninsula) Demand Growth TNB (Peninsula) Yearly Peak Demand MW * 18,808 18,566 18,338 17,788 17,790 *Recorded at: 10 Mar’20 16,901 16,822 at 1630hrs 16,562 15,826 15,476 FY'11 FY'12 FY'13 FY'14 FY'15 FY'16 FY'17 FY'18 FY'19

  7. Slide 7: Growing Renewable Energy Business

    INTRODUCTION TO TENAGA Growing Renewable Energy Business– TNB is currently present in more than 5 countries • 55% equity ownership in Vortex Solar Investments S.à.r.l, United 24 operational solar PV farm portfolio of 365MW (May 2017) United Kingdom • Tenaga Wind Ventures UK Ltd, 53 operational onsho

  8. Slide 8: TNB Shareholding Structure and Top KLCI Stocks

    INTRODUCTION TO TENAGA TNB Shareholding Structure Top 10 KLCI Stocks by Market Capitalization RM bil Khazanah Nasional Berhad 84.4 (13.1%) Maybank 18.4 97.1 17.0 66.3 Permodalan Nasional Berhad TNB (12.1%) (PNB) 75.4 17.5 15.5 64.1 Employees Provident Fund Public Bank (15.1%) Board (EPF) 75.5 5.6 6.

  9. Slide 9: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  10. Slide 10: Incentive Based Regulation (IBR)

    INCENTIVE BASED REGULATION (IBR) A Mechanisms For Tariff Setting With Incentives To Improve Efficiency & Greater Transparency Non – Regulated Regulatory Environment: (competitive bidding environment) 1. Clear and Transparent Regulatory Framework Clear and transparent regulatory framework governed by

  11. Slide 11: IBR Regulatory Period

    INCENTIVE BASED REGULATION (IBR) Regulatory Period 2 Average Tariff by Entities (sen/kwh) Fuel Parameters Base tariff for RP2 COAL USD75/MT (RM14.47/mmbtu @ RM4.212/USD) (sen/kWh) RP1 : USD87.5.MT @ RM3.100/USD LNG RM35/mmbtu RP1 : RM41.68/mmbtu REGULATED RM24.20/mmbtu (Jan’18 - Jun’18) Single Buyer

  12. Slide 12: IBR Regulatory Period Timeline

    INCENTIVE BASED REGULATION (IBR) Interim Year 2021 Regulatory Period Timeline INTERIM YEAR RP2 (2018 – 2020) 2021 RP3 (2022 – 2024) 2018 2019 2020 2021 2022 2023 2024 ➢ Energy Commission (EC) has agreed for RP3 to be in 2022-2024, and RP2 to be extended (FY2021 – Interim year). ➢ TNB is in discussio

  13. Slide 13: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  14. Slide 14: 4 Strategic Pillars

    REIMAGINING TNB TNB's strategic aspiration – a key enabler is the corporate structure 4 STRATEGIC PILLARS 4 STRATEGIC PILLARS Future Generation Grid of the Future Future Winning the Customer Sources Proof Regulations • Upgrading existing network • Growing TNB’s renewable infrastructure into a smart,

  15. Slide 15: TNB RE Target of 1,700MW by 2025

    TO BE A LEADING PROVIDER OF SUSTAINABLE ENERGY SOLUTIONS IN MALAYSIA AND INTERNATIONALLY Our pledge in powering the lives of our customers and communities through renewable energy, supporting Malaysia’s commitment in reducing the GHG emission intensity and environmental impact Government Green Devel

  16. Slide 16: TNB's RE Strategy and Capacity

    TO BE A LEADING PROVIDER OF SUSTAINABLE ENERGY SOLUTIONS IN MALAYSIA AND INTERNATIONALLY Our journey towards transitioning into a cleaner and sustainable energy provider TNB’s RE Capacity TNB’s RE Strategy WIND International: International • UK (TNB Wind Ventures): 26 MW 144 MW • Turkey (GAMA): 118

  17. Slide 17: Transitioning Away from Coal Related Revenue

    TRANSITIONING AWAY FROM COAL RELATED REVENUE The Group is committed to ensure that the revenue from the coal generation plants does not exceed 25% Breakdown of TNB's Group Revenue 0.2% 0.3% 0.3% 0.3% 0.3% 0.3% 0.3% 0.3% 2.6% 2.4% 2.7% 2.7% 2.6% 2.0% 1.8% 1.7% 12.6% 13.0% 10.8% 10.5% 11.0% 10.4% 11.4

  18. Slide 18: TNB's Environmental Initiatives

    TNB’S ENVIRONMENTAL INITIATIVES TNB Board of Directors is cognisant of the importance of ensuring sustainability is integrated in the strategic direction of the organisation, decision making processes and operational performance Developed Green House Gas Emission The latest coal generation plants us

  19. Slide 19: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  20. Slide 20: Dividend Policy

    DIVIDEND POLICY Distribution of dividend is based on 30% to 60% dividend payout ratio, based on the reported Consolidated Net Profit Attributable to Shareholders After Minority Interest, excluding Extraordinary, Non-Recurring items Current dividend policy effective FY2017 25% 27% 25% 50% 50% 56% 59%

  21. Slide 21: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  22. Slide 22: FY2020 Outlook: Electricity Demand

    FY2020 OUTLOOK • Due to the MCO and Covid-19 pandemic, demand for Apr’20 fell by 15.7%. • Since the implementation of Conditional Movement Control Order (CMCO), demand has started to pick up as more businesses were allowed to operate. Electricity • Moving forward, demand and sales are expected to fu

  23. Slide 23: FY2020 Outlook: International Business

    FY2020 OUTLOOK • For 2020, we will be executing a strategy aimed at either protecting or creating value from existing assets. • Part of this strategy involves executing a growth strategy focusing on growing TNB’s international Renewable Energy (RE) business leveraging on existing assets, capabilitie

  24. Slide 24: Agenda

    01 INTRODUCTION TO TENAGA 02 REGULATORY AGENDA 03 BUSINESS STRATEGY & DIRECTION 04 DIVIDEND POLICY 05 FY2020 OUTLOOK 06 APPENDIX

  25. Slide 25: Electricity Demand by Sector

    APPENDIX Electricity Demand by Sector - Lower electricity demand mainly from sluggish industrial and commercial sectors 2Q main contributors for the drop Commercial Industrial Industrial: Y-o-Y (15.3%) Y-o-Y (14.6%) • Iron and steel • Cement products • Electric & electronic (0.1%) (28.3%) (7.5%) (22

  26. Slide 26: IBR – ICPT Mechanism Ensures TNB Remain Neutral

    APPENDIX Incentive Based Regulation (IBR) – Imbalance Cost Pass-Through (ICPT) Mechanisms Ensures TNB Remain Neutral Base Tariff under IBR framework comprises of: a) Opex, Depreciation of Regulated Assets & Tax Expenses of Business Entities - transmission, grid system operation, Single Buyer operati

  27. Slide 27: IBR – ICPT Comprises Two Components

    APPENDIX Incentive Based Regulation (IBR) – Imbalance Cost Pass-Through (ICPT) Comprises Two Components Imbalance Cost Pass-through (ICPT) Fuel Cost Pass Through (FCPT) Generation Specific Cost Adjustment (GSCPT) Changes in Gas/LNG and Coal Costs Changes in: PPAs Power Purchase Agreements • Other fu

  28. Slide 28: IBR – New Features in Tariff Review for RP2

    APPENDIX Incentive Based Regulation (IBR) – New Features in Electricity Tariff Review for RP2 (2018-2020) * Source: Energy Commission (EC) 28 28

  29. Slide 29: IBR – IBR Entities

    APPENDIX Incentive Based Regulation (IBR) – IBR Entities 1 1 In RP1, these 2 entity are grouped as Price –Cap entity Source: Energy Commission (EC) 29 29

  30. Slide 30: IBR – Generation and Customer Mix

    APPENDIX Incentive Based Regulation (IBR) – Generation and Customer Mix Generation Mix RP1 vs RP2 Changes in Customer Mix (%) in RP1 (2015-2017) RP1 Base RP1 Actual 43.6% 40.8% Coal Coal 44% 49% 35.1% RP2 1% 1% 0.1% 34.1% 4% Coal Gas 20.6% 22.3% 33% Hydro 61% RE Base IBR RP1 Average Actual IBR RP1 L

  31. Slide 31: International Acquisition

    APPENDIX International Acquisition - Four International Acquisitions to Support Aspiration 30% 30% Equity interest of GAMA Enerji A.S. Equity interest of GMR Energy Limited. Assets include a 853MW natural gas- Assets include 1,915MW coal, gas and fired plant, 117.5MW wind plants and solar plants. 13

  32. Slide 32: Existing TNB Renewable Energy Assets

    APPENDIX Existing - TNB’s Renewable Energy (RE) Assets Others Domestic (Peninsular Malaysia) International Mini Hydro (22MW) ⚫ Kelantan ⚫ GSPARX Rooftop Solar (56MW) United Kingdom (Total secured) Large Hydro ⚫ SJ Pergau (600MW) Solar ⚫ TNB Vortex Solar (365.0MW) Kedah Terengganu Wind Large Scale So

  33. Slide 33: TNB's Environmental Initiatives - Green Development

    APPENDIX TNB’s Environmental Initiatives - Green Development ❑ UNITEN’s Smart UniverCity ❑ Expansion of Electric Vehicle Charging Network ✓ To create a sustainable ecosystem which provide competitive advantage for TNB in moving into smart city environment. ✓ To expand the existing charging station i

  34. Slide 34: TNB's Social Initiatives

    APPENDIX TNB’s Social Initiatives Economic & Social Education Career Development 212 households benefitted from Projek Baiti Jannati and 700 students awarded More than RM183 Program Mesra Rakyat by YTN scholarship with a million contributed in refurbishing or building new total amount of RM66.1 trai

  35. Slide 35: TNB's Governance Initiatives

    APPENDIX TNB’s Governance Initiatives TNB is committed to operating in an ethical, transparent and responsible manner given the critical role we play in national development and the number of stakeholders who are impacted by our business TNB Board Committees Governance Pillars Board Audit Committee

  36. Slide 36: Composition of Board of Directors

    APPENDIX TNB’s Governance Initiatives - Composition of BOD CHAIRMAN EXECUTIVE DIRECTOR / CEO DATO’ SERI DIRAJA MAHDZIR KHALID DATUK SERI AMIR HAMZAH BIN AZIZAN Independent Non-Executive Directors (Total = 7) Non-Independent Non-Executive Directors (Total =2) NORAINI BINTI CHE DAN ONG AI LIN GOPALA K

  37. Slide 37: Capital Management

    APPENDIX Capital Management - New drawdown & FOREX translation increased the gearing, but within the optimal level Statistics 30th Jun'20 31st Dec'19 RM Equivalent of Loan Value (bil) 1 Total Debt (RM' Bil) 47.3 45.4 Net Debt (RM' Bil)* 35.9 31.2 76.1% 1 Gearing (%) 45.8 43.4 Net Gearing (%) 34.8 29

  38. Slide 38: Financial Highlights

    APPENDIX Financial Highlights REVENUE (RM bil) EBITDA (RM bil) 50.4 50.9 47.4 18.4 44.5 14.8 15.5 13.4 22.5 9.3 FY'16 FY'17 FY'18 FY'19 1HFY'20 FY'16 FY'17 FY'18 FY'19 1HFY'20 PAT (RM bil) 7.32 6.91 4.45 3.75 1.41 FY'16 FY'17 FY'18 FY'19 1HFY'20 Note: FY2019 is after MFRS16 implementation 38 38

  39. Slide 39: Technical Highlights

    APPENDIX Technical Highlights EAF (%) Transmission System Minute (mins) 04 05 89.9 1.5 88.1 88.5 88.2 83.4 0.4 0.3 0.2 0.0 FY'16 FY'17 FY'18 FY'19 1HFY'20 FY'16 FY'17 FY'18 FY'19 1HFY'20 Distribution SAIDI (mins) 49.7 50.2 48.2 48.1 44.2 FY'16 FY'17 FY'18 FY'19 1HFY'20 39 39

  40. Slide 40: Disclaimer

    DISCLAIMER All information contained herein is meant strictly for the use of this presentation only and should not be used or relied on by any party for any other purpose and without the prior written approval of TNB. The information contained herein is the property of TNB and it is privileged and c

  41. Slide 41: Thank You

    THANK YOU For further enquiries, kindly contact us at: Investor Relations Office: Investor Relations Team: Ms. Mehazatul Amali Meor Hassan CoE Investor Relations +603 2108 2126 Group Finance Division Tenaga Nasional Berhad mehazatul@tnb.com.my 4th Floor, TNB Headquarters Ms. Sakinah Mohd Ali No.129,

Tenaga Nasional Berhad — Investor Presentation (November 2020) on 6ix