Indiabulls Limited · NSE:IBULLSLTD

Indiabulls — Investor Presentation (June 2013)

41 slides from Indiabulls's investor presentation, June 2013

  1. Slide 1: Indiabulls Group

    Slide 1: Indiabulls Group

    Indiabulls Group | aaa 1 Indiabulls

  2. Slide 2: Indiabulls Group

    Slide 2: Indiabulls Group

    Indiabulls Group  Total Group Networth – Rs. 19,335 Cr  Total Group PAT for FY 12-13 – Rs. 1,454 Cr.  Total Group Capital Expenditure – Rs. 6,200 Cr. (US $ 1.2 bn.) capex in FY 10- 11. Planned capex of Rs. 29,000 Cr (US $ 5.7 bn.) by FY 2014-15.  Focus on Execution and on ground results translat

  3. Slide 3: Journey of Indiabulls Group

    Slide 3: Journey of Indiabulls Group

    Journey of Indiabulls Group Indiabulls Financial Services reverse merged into Indiabulls Housing Finance Ltd. Indiabulls Power announced demerger from Real Estate Indiabulls Indiabulls Power started Real Estate demerged from Financial Indiabulls Indiabulls Services Financial Real Estate Indiabulls S

  4. Slide 4: Indiabulls Group Companies

    Slide 4: Indiabulls Group Companies

    Indiabulls Group Companies Indiabulls Group Indiabulls Housing Finance Indiabulls Real Estate Indiabulls Power Indiabulls Securities India’s 3rd largest National developer Developing 5400 MW Retail Non- Mortgage Finance with Focus on key of Power Plants discretionary wealth Company regions of Mumbai

  5. Slide 5: Strategy and Focus

    Slide 5: Strategy and Focus

    Strategy and Focus  Consolidation – aim to be among top 3 players in existing businesses within next 3 years  No new products – focus on gaining size and scale in existing core areas  No capital market fund raising – all businesses are well funded to achieve growth and size  Goal- FY 2013/14 – t

  6. Slide 6: Indiabulls Housing Finance Ltd (IHFL)

    Slide 6: Indiabulls Housing Finance Ltd (IHFL)

    Indiabulls Housing Finance Ltd (IHFL) 6

  7. Slide 7: Leading Housing Finance Company

    Slide 7: Leading Housing Finance Company

    Leading Housing Finance Company Asset Composition 7%  The company enjoys a long-term rating of AA+ 21%  Focus on long term, low risk home loan business  Retail mortgages comprise 72% of the total asset book  Home loans, which forms the majority of incremental disbursals, are disbursed at 72% an

  8. Slide 8: Assets Growth

    Slide 8: Assets Growth

    Assets Growth Total Loan Assets (Rs. Cr.) Loans Sold (Rs. Cr.) (in preceding 12 months) 34,425.6 2,378.9 2,397.4 27,521.2 19,824.8 177.3 Mar-11 Mar-12 Mar-13 Mar-11 Mar-12 Mar-13  The growth in the loan book inclusive of loans sold in the previous 12 months is 25%  Loans amounting to Rs. 2,397.4 w

  9. Slide 9: Stable Asset Quality

    Slide 9: Stable Asset Quality

    Stable Asset Quality (as % of Total Loan Book) 1.03% 0.79% 0.79% 0.66% 0.46% 0.46% 0.37% 0.33% 0.33% Mar-11 Mar-12 Mar-13 Gross NPA General & Specific Provisions Net NPA  Focus on underwriting Low risk mortgage assets at low LTV’s with emphasis on cash flows of borrowers has allowed the company to

  10. Slide 10: Home Loans: Expanding Reach

    Slide 10: Home Loans: Expanding Reach

    Home Loans: Expanding Reach Indiabulls’ Distribution Network Tier I 56 Tier II 87 Tier III 57 Total 200  The company hosted AAWAS-2012, a budget home show, where 24 Category ‘A’ developers showcased their prime properties in Mumbai. The show’s success reflects the expanding relationship base of the

  11. Slide 11: Improving Liability Profile

    Slide 11: Improving Liability Profile

    Improving Liability Profile 11% 10% 8% 20% 25% 30% Bank Loans 69% 65% 62% Bonds Commercial Paper Mar-11 Mar-12 Mar-13  Outstanding bonds have grown to Rs. 9,406 Cr in Mar 2013, up from Rs. 6,378 Cr in Mar 2012. In this 12 month period long-term bonds formed 51% of the incremental borrowings  Among

  12. Slide 12: Indiabulls Real Estate (IBREL)

    Slide 12: Indiabulls Real Estate (IBREL)

    Indiabulls Real Estate (IBREL) 12

  13. Slide 13: Quality and on-time Delivery

    Slide 13: Quality and on-time Delivery

    Quality and on-time Delivery  Delivery and Execution Track Record Delivered a record 3.3 million SF developed space valued at $1.75 billion (within 4 years of inception). Fastest and largest delivery in value terms by any Indian real estate developer in the same time period.  Focus on Super Metros

  14. Slide 14: Focus on Super-Metros

    Slide 14: Focus on Super-Metros

    Focus on Super-Metros NCR (Delhi) $ 1 bn Jaipur More than 95% of our projects (by Agra Jodhpur Kanpur value) are in super-metro cities – Mumbai Metro Region, National Ahmedabad Capital Region (Delhi) and Chennai Baroda Indore Mumbai Region Vishakapatnam Hyderabad $ 7.5 bn Chennai $ 510 mn Madurai 14

  15. Slide 15: Business Update

    Slide 15: Business Update

    Business Update Key Financial Highlights: FY12-13 FY 12-13 FY 11-12 Total Revenues (Rs. Cr.) 1,300.52 1,391.59 PBT (Rs. Cr.) 267.32 232.32 PAT (Rs. Cr.) 175.38 168.19 EPS (Rs.) 3.73 3.73 Year-on-Year (Y-o-Y) Comparison – Q4 FY12-13 v/s Q4 FY11-12 Q4 FY 12-13 Q4 FY 11-12 Total Revenues (Rs. Cr.) 412.

  16. Slide 16: Business Update

    Slide 16: Business Update

    Business Update  Total Sales of Rs. 3,002 Crores in FY-13 vs. Rs. 1,982 Crores for the year FY -12.  Company completed Share Buyback of 5 Cr. shares for Rs. 273.2 Cr. in FY-13.  Annualized rental income increased to Rs. 486 Cr. in FY-13 vs. Rs. 354 Cr. in FY-12.  Added 220 acres to the land bank

  17. Slide 17: Total Land Bank

    Slide 17: Total Land Bank

    Total Land Bank Area(In Acres) Residential Commercial Total st Opening Balance (As on 1 Apr 2012) 792.85 43.18 836.03 Addition in Q4 FY ’13 220.77 0 220.77 Less: Moved to AUD 53.26 0 53.26 Closing Balance 960.36 43.18 1,003.54 * 2,588 Acres of Nashik SEZ not included in the above • Acquired 220.77 a

  18. Slide 18: Approved Projects

    Slide 18: Approved Projects

    Approved Projects Area Under Construction* - million sq. ft. Regional Breakup of Area Under Construction 7.91 7.15 2.65 2.04 14% 4.38 10% 9.72 50% 5.03 26% Super Premium Premium Mid income Mumbai MMR NCR Chennai Rest of India  Total Saleable Area Under Construction – 19.44 Mn. Sq. ft. as on 31st Ma

  19. Slide 19: Sales Inventory of approved under construction projects

    Slide 19: Sales Inventory of approved under construction projects

    Sales Inventory of approved under construction projects Value of Unsold Total Saleable Area Sold Area to be Total Value Sold Projects Inventory at Current Area (Mn Sqft) ( Mn Sqft) sold (Mn Sqft) (Rs. Cr.) Rates (Rs. Cr.) Super Premium 4.38 1.57 2.80 3,877 10,080 Premium 7.15 6.09 0.41 3,386 308 Mid

  20. Slide 20: Indiabulls Blu, Worli

    Slide 20: Indiabulls Blu, Worli

    Indiabulls Blu, Worli  Project launched at Rs. 36,000 psft in June 2012.  Already achieved residential sale rate of Rs. 53,000 psft.  Office - 250,000 sq ft x sale rate Rs 25,000 (already contracted) = Rs 625 Cr  Construction cost (including IDC and all fees) = Rs 1200 Cr  Cash flow (after all

  21. Slide 21: Projects Pipeline

    Slide 21: Projects Pipeline

    Projects Pipeline Projects Launched in FY 13 1. BLU, Worli, Mumbai – 7-Star luxury residential complex spread over 10 acres in South Mumbai with breathtaking sea views 2. IB Golf City, Savroli, MMR – Premium residential township with 18-hole golf course spread over 350 acres of greens Launch Pipelin

  22. Slide 22: Indiabulls Power (IBPOW)

    Slide 22: Indiabulls Power (IBPOW)

    eee Indiabulls Power (IBPOW) 22 Indiabulls

  23. Slide 23: Indiabulls Power Focus on Delivery and Execution

    Slide 23: Indiabulls Power Focus on Delivery and Execution

    Indiabulls Power (IBPOW) Focus on Delivery and Execution  Plan - Developing 5,400 MW across India. Financial closure achieved for entire 5,400 MW.  Execution - US $6.1 billion capex over next 4 years for 5,400 MW. Phase I (2,700 MW) – construction in full swing (~5,000 workers on site)  For both

  24. Slide 24: Execution

    Slide 24: Execution

    Execution  Execution - construction is in full swing with ~5,000 people working on the sites.  Suppliers - Work given to reputed suppliers and contractors Vendor / Service Provider Scope / Work 1 BHEL Boiler Turbine Generator (BTG) 2 Shapoorji Pallonji BTG – Civil 3 Shapoorji Pallonji BTG - Struct

  25. Slide 25: Amravati Power Plant – 2700 MW

    Slide 25: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW Construction work in full swing.. 25

  26. Slide 26: Amravati Power Plant – 2700 MW

    Slide 26: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 26

  27. Slide 27: Amravati Power Plant – 2700 MW

    Slide 27: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 27

  28. Slide 28: Amravati Power Plant – 2700 MW

    Slide 28: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 28

  29. Slide 29: Amravati Power Plant – 2700 MW

    Slide 29: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 29

  30. Slide 30: Amravati Power Plant – 2700 MW

    Slide 30: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 30

  31. Slide 31: Amravati Power Plant – 2700 MW

    Slide 31: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 31

  32. Slide 32: Amravati Power Plant – 2700 MW

    Slide 32: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 32

  33. Slide 33: Amravati Power Plant – 2700 MW

    Slide 33: Amravati Power Plant – 2700 MW

    Amravati Power Plant – 2700 MW 33

  34. Slide 34: Nashik Power Plant – 2700 MW

    Slide 34: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW Construction work in full swing.. 34

  35. Slide 35: Nashik Power Plant – 2700 MW

    Slide 35: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 35

  36. Slide 36: Nashik Power Plant – 2700 MW

    Slide 36: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 36

  37. Slide 37: Nashik Power Plant – 2700 MW

    Slide 37: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 37

  38. Slide 38: Nashik Power Plant – 2700 MW

    Slide 38: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 38

  39. Slide 39: Nashik Power Plant – 2700 MW

    Slide 39: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 39

  40. Slide 40: Nashik Power Plant – 2700 MW

    Slide 40: Nashik Power Plant – 2700 MW

    Nashik Power Plant – 2700 MW 40

  41. Slide 41: Thank You

    Slide 41: Thank You

    ny Thank You aa Indiabulls