  1. Slide 1: Sunrise Project Community Consultative Committee

    Sunrise Project Community Consultative Committee 11 October 2022

  2. Slide 2: Contents

    Contents 1 2 Sunrise Regional Update – Exploration & Test Work Community Update 3 Environmental Management Update 4 Environmental Approvals Update 5 CCC Member Questions 2 Powering innovation | October 22

  3. Slide 3: Sunrise Regional Update – Exploration & Test Work

    01 Sunrise Regional Update – Exploration & Test Work 3 Powering innovation | October 22

  4. Slide 4: Exploration in the Region – Sunrise East (EL 4573)

    Exploration in the Region – Sunrise East (EL 4573) › Diamond drilling completed on EL 4573 “Sunrise East” returned cobalt grades comparable to the Sunrise Project resource › Follow up 53 hole reverse circulation drilling program was completed to test the extent of cobalt bearing oxide mineralisation

  5. Slide 5: Exploration in the Region – Hylea (EL8520, EL8641 and EL8801)

    Exploration in the Region – Hylea (EL8520, EL8641 and EL8801) › 58 Hole reverse circulation drilling program completed during Q2 2022 › Assay results received included significant cobalt and scandium intervals, as well as encouraging nickel and platinum results 5 Powering innovation | October 22

  6. Slide 6: Exploration in the Region – Limestone

    Exploration in the Region – Limestone › Mapping and surface sampling continuing across several prospective limestone tenements › Land access agreements in place › Reverse circulation drilling program planned for the Ezy Lime tenement › Identification of a quality limestone supply closer to the Sunri

  7. Slide 7: Test Work & Technology Development

    Test Work & Technology Development › Process test work completed to optimize the residence time in the U-Column desorption process for nickel and cobalt › Battery recycling tests are underway and testing to date has shown that “black mass” from spent batteries can be readily recycled at Sunrise › Te

  8. Slide 8: Community Update

    02 Community Update 8 Powering innovation | October 22

  9. Slide 9: Community – Working Together

    Community – Working Together › Community Events – Supported the Trundle Back in Time event on 26th March – Supported and attended the Tullamore, Trundle, Bedgerabong, Condobolin, Parkes and Forbes Agricultural Shows › Education and Investment – Continuing to support the Condobolin Public School thro

  10. Slide 10: Keeping People Informed

    Keeping People Informed › Community Communication – Parkes and Condobolin shopfronts are open, first and third Tuesday/Thursday of the month › Sunrise Energy Metals website – Complaints register published monthly, with zero complaints YTD – Community Complaints line listed on our website – 1800 952

  11. Slide 11: Environmental Management Update

    03 Environmental Management Update 11 Powering innovation | October 22

  12. Slide 12: Environmental Monitoring

    Environmental Monitoring › Continuing environmental monitoring: – Air Quality – Surface Water – Groundwater – Meteorological › Depositional dust and Particulate Matter (PM10 and PM2.5) › Surface water monitoring events – April, May, June, July, August, September and October 2022 › Groundwater monito

  13. Slide 13: Rainfall Comparison

    Rainfall Comparison 13 Powering innovation | October 22

  14. Slide 14: Environmental Approvals Update

    04 Environmental Approvals Update 14 Powering innovation | October 22

  15. Slide 15: Project Execution Plan Modification

    Project Execution Plan Modification › Modification was approved 18th January 2022 › Updated Environmental Management Plans (EMPs) are on the Sunrise website – Air Quality and Greenhouse Gas Management Plan* – Blast Management Plan – Biodiversity Management Plan and Revegetation Strategy – Environmen

  16. Slide 16: Critical Asset Approvals

    Critical Asset Approvals › 132kV Electrical Transmission Line (ETL) – Connection agreement with Network Service Providers progressing including initial line design with Essential Energy – First 40km of the ETL will replace the existing 66kV Trundle supply line with a dual 132/66 kV line – This will

  17. Slide 17: Critical Asset Approvals

    Critical Asset Approvals › Raw Water Pipeline – Lease agreement with Councils signed – Licence and easement application over Crown Land progressing › Oversize Transport Route – Met with relevant Shire Councils along the route – Submitted Grant application through NSW Critical Minerals Fund to comple

  18. Slide 18: CCC Member Questions

    05 CCC Member Questions 18 Powering innovation | October 22

  19. Slide 19: Thank you

    Thank you 0. sunrise energy metals