    Important notices and disclaimers Nature of Document For personal use only This presentation has been prepared as a summary only, and does not contain all information about Agrimin Limited’s (“Agrimin” or “the Company”) assets and liabilities, financial position and performance, profits and losses,

  3. Slide 3: Agrimin highlights

    Agrimin highlights For personal use only ➢ Developing a globally significant Sulphate of Potash (SOP) operation on the world’s largest undeveloped SOP-bearing salt lake ➢ Long-life operation to be underpinned by a low-risk jurisdiction and first quartile cost position ➢ Leveraged to increasing deman

  4. Slide 4: Corporate snapshot

    Corporate snapshot Capital Structure (19 February 2018) Share Price Chart (1 July 2014 to 19 February 2018) For personal use only ASX Code AMN Native Title Shares 156.2m $1.20 Agreement Positive Signed Share Rights & Options 8.5m Scoping Maiden Study $1.00 Share Price A$0.88 Mackay SOP SOP Resource

  5. Slide 5: Key people

    Key people Board of Directors Key Technical Personnel For personal use only Mark Savich | Chief Executive Officer Tom Lyons | General Manager Financial analyst (CFA) with 14 years of experience in the resources Geologist with experience in a range of commodities including industrial minerals, metals

  6. Slide 6: Sulphate of Potash (SOP): Specialty Fertilizer for Modern Agriculture

    For personal use only Sulphate of Potash (SOP) Specialty Fertilizer for Modern Agriculture

  7. Slide 7: Commodity fertilizers are currently over-supplied

    Commodity fertilizers are currently over-supplied For personal use only ➢ Commodity fertilizers provide three macronutrients that every crop needs: ➢ Nitrogen (N) – the most important for healthy plant growth, such as leaf size, colour and yield ➢ Phosphorus (P) – vital for photosynthesis and enhanc

  8. Slide 8: Major fertilizer producers are adding value downstream

    Major fertilizer producers are adding value downstream For personal use only Potash mine Phosphate mine Sulphur Gas field Oil field Coal mine Sulphuric acid Synthetic gas Carbon dioxide Phosphoric acid Ammonia NPK K K P P NP Nitric acid NPK N N MOP & SOP SOP SSP TSP MAP & DAP (Mannheim) Ammonium nit

  9. Slide 9: SOP is chloride-free potash & a high value product

    SOP is chloride-free potash & a high value product For personal use only ➢ 90% of all potash production is MOP (muriate of potash) which contains 46% chloride ➢ SOP (sulphate of potash) is chloride-free and vital for high value crops, such as fruits and vegetables ➢ SOP improves the nutritional valu

  10. Slide 10: SOP demand is growing rapidly

    SOP demand is growing rapidly For personal use only ➢ Demographic shift from rural to urbanised populations is increasing the consumption of fruits and vegetables SOP Demand (Deliveries) ➢ Agricultural pollution, water scarcity and technological advancements are causing a structural change in food p

  11. Slide 11: SOP supply is already unable to keep up with demand

    SOP supply is already unable to keep up with demand For personal use only ➢ Current supply shortage of SOP is caused by Mannheim Installed SOP Capacity of Major Producers producers being unable to dispose of hydrochloric acid (Overlayed on Population Density) Mannheim Process: MOP + Sulphuric Acid =

  12. Slide 12: Lake Mackay is set to be the next major SOP salt lake

    Lake Mackay is set to be the next major SOP salt lake Current SOP Production Rates of Major Producers1 For personal use only ➢ There are five major salt lakes with installed SOP capacity, three of which started in the last 10 years: 1,500,000tpa ➢ CITIC Guoan Group at Xitai Jinair salt lake (2012) 1

  13. Slide 13: Lake Mackay is comparable to current SOP operations

    Lake Mackay is comparable to current SOP operations Mackay, Australia Luobupo, China Great Salt Lake, USA For personal use only Extraction Method Trenching of Near Surface Brines Trenching of Near Surface Brines Pumping of Near Surface Brines Potassium Concentration 3,603 mg/L 10,413 mg/L 4,600 mg/L

  14. Slide 14: SOP prices are incentivising new production

    SOP prices are incentivising new production For personal use only ➢ Prices for standard SOP products are currently US$500/t Potash Prices for Last 20 Years $1,200 ➢ Since 2000, SOP demand growth has been 5.0% per year, $1,100 compared to MOP demand growth of 2.3% $1,000 $900 $800 ➢ Robust outlook fo

  15. Slide 15: Mackay SOP Project, Western Australia

    For personal use only Mackay SOP Project Western Australia

  16. Slide 16: A globally significant project in the making

    A globally significant project in the making Project Location For personal use only ➢ Project is 100% owned by Agrimin and located 500km east of Alice Springs ➢ Targeting a production rate of 370,000tpa of SOP1 commencing in 2021 and operating for 20 years ➢ Native Title Agreement signed for the pro

  17. Slide 17: Key attributes support large-scale & low-cost production

    Key attributes support large-scale & low-cost production For personal use only ➢ Saline groundwater (brine) within Lake Mackay contains high-grade Potassium and Sulphate in solution Shallow Brine Resources Across the Entire Deposit ➢ Mineral Resources of 23.2Mt of SOP1 (drainable brine) have been de

  18. Slide 18: Shallow resources have excellent potential to grow

    Shallow resources have excellent potential to grow Drill Hole Locations For personal use only ➢ 98 drill holes on a 5km grid provide a strong geological understanding of the deposit ➢ Mineral Resources are defined within a single geological unit over an area of 2,201km2 ➢ Shallow Mineral Resources c

  19. Slide 19: Low-risk development plan for a long-life operation

    Low-risk development plan for a long-life operation Project Layout For personal use only ➢ Trench extraction of 78.5Mtpa of groundwater grading 0.7% SOP ➢ Evaporation ponds start at 34km2 and expand to 59km2 over 20 years ➢ Harvesting of 2.5Mtpa of potash salts grading 17.8% SOP ➢ Production of 370k

  20. Slide 20: On-lake geotechnics support large-scale unlined ponds

    On-lake geotechnics support large-scale unlined ponds For personal use only ➢ Full-scale ponds will cover less than 2% of Lake Mackay at the end of the operation’s proposed 20 year life ➢ Remoulded permeability values of 9.7 x 10-9 to 4.6 x 10-11 m/s indicate suitable on-lake setting for unlined pon

  21. Slide 21: High quality SOP samples produced during testwork

    High quality SOP samples produced during testwork For personal use only ➢ Process testwork has produced commercial grade SOP Simplified Process Flow Diagram samples (>52% K2O) that exceed industry benchmark grades ➢ PFS process testwork successfully validates the use of conventional SOP production t

  22. Slide 22: Transport infrastructure in place

    Transport infrastructure in place Map of Transport Corridors For personal use only ➢ Road: Project is connected to Alice Springs via well-maintained sealed and unsealed roads which are used to transport fuel and supplies to mining operations and communities ➢ Rail: Alice Springs is connected to ship

  23. Slide 23: Scoping study indicates a compelling investment case

    Scoping study indicates a compelling investment case For personal use only ➢ Scoping Study (August 2016) confirmed globally significant scale and compelling economics Scoping Study Material Assumptions and Outcomes Parameter Value Operating Life 20 years ➢ Targeted SOP production of 370,000tpa over

  24. Slide 24: Forecasted to have industry low capex & opex

    Forecasted to have industry low capex & opex For personal use only ➢ Industry low capital intensity of US$700/t, making the Project ➢ Bottom quartile cost, providing an opportunity to displace an attractive development proposition high-cost production from the Mannheim Process Capital Intensity for

  25. Slide 25: Project delivery schedule targets SOP production in 2021

    Project delivery schedule targets SOP production in 2021 For personal use only 2018 2019 2020 2021 Activity Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Pre-Feasibility Study Environmental Assessment Definitive Feasibility Study Regulatory Approvals Financing Trench & Pond Earthworks Plant Construction

  26. Slide 26: Exploration upside from lateral and depth extensions

    Exploration upside from lateral and depth extensions Tenement Map For personal use only ➢ Current Mineral Resources are hosted by a single contiguous deposit covering an area of 2,201km2 ➢ The Company controls a contiguous on-lake area of 3,383km2 and the northern and eastern parts of Lake Mackay ha

  27. Slide 27: Creating sustainable economic development

    Creating sustainable economic development For personal use only ➢ Agrimin’s proposed A$346 million fertilizer operation at Lake Mackay is the only advanced industrial development in this very remote part of the Australia ➢ The Mackay SOP Project will create substantial economic and public benefits f

  28. Slide 28: Summary

    Summary For personal use only ➢ Agrimin is developing a globally significant SOP project in one of the best mining jurisdictions in the world ➢ Robust outlook for SOP prices is supported by: ➢ Urbanised populations rotating to healthier diets ➢ Structural change to food production practices for high

  29. Slide 29: For personal use only

    Office Contact: 2C Loch Street Nedlands, Western Australia 6009 For personal use only Australia T: +61 8 9389 5363 E: admin@agrimin.com.au W: www.agrimin.com.au Investor Relations Contact: Mark Savich Chief Executive Officer M: +61 402 746 757 E: msavich@agrimin.com.au Media Contact: Michael Vaughan

  30. Slide 30: Appendix 1. Mineral Resources Statement (JORC Code 2012)

    Appendix 1. Mineral Resources Statement (JORC Code 2012) Mineral Resources – December 2015 (Total Porosity) For personal use only Category Zone Depth (m) Volume (M m3) Average Total Porosity SOP Grade (kg/m3) Contained SOP (Mt) Indicated Upper 0.4 – 2.7 4,036 45.0% 8.41 15.0 Inferred Upper 0.4 – 6.0