Sunrise Energy Metals Limited · ASX:SRL
Sunrise Energy Metals — Clean TeQ Holdings — Corporate Update (May 2018)
38 slides from Sunrise Energy Metals's corporate update, May 30, 2018
Slide 1: Community Consultative Committee meeting 30 May 2018
Community Consultative Committee meeting 30 May 2018 CLEAN TEQ PAGE 1
Slide 2: Overview
OVERVIEW 1. Project Update 2. Community Involvement 3. Modification Application Updates 4. Environmental Management 5. Other Items C L E AN T E Q S U N R I S E P AG E 2
Slide 3: Clean TeQ Update
CLEAN TEQ UPDATE
Slide 4: Indicative Project Schedule
INDICATIVE PROJECT SCHEDULE 2018 2019 2020 2021 DETAILED DEFINITIVE PROJECT CONSTRUCTION COMMENCE ENGINEERING FEASIBILITY FINANCING Commence formal COMMISSIONING FEED for process STUDY Secure project debt plant construction & RAMP UP plant and associated Due June 2018 finance via MLA group infrastru
Slide 5: Project Financing
PROJECT FINANCING STRONG BANKING SUPPORT FOR PROJECT DEBT FACILITY ▪ Mandated Lead Arranger (MLA) group appointed November 2017 ▪ National Australia Bank ▪ Societe General ▪ Natixis ▪ International Commercial Bank of China (ICBC) ▪ US$500 million in indicative commitments received, prior to syndicat
Slide 6: Offtake & Investment Strategy
OFFTAKE & INVESTMENT STRATEGY CONSIDERABLE DEMAND FROM END USERS AND INTERMEDIARIES ▪ First offtake agreement with Beijing Easpring signed in 2017 ▪ Extensive due-diligence is ongoing by a Binding five-year offtake agreement for 20% of range of parties considering product offtake cobalt and nickel s
Slide 7: Innovative Clean-iX Processing
INNOVATIVE CLEAN-iX® PROCESSING
Slide 8: Innovative Clean-iX Processing
INNOVATIVE CLEAN-iX® PROCESSING SULPHATE PRODUCTS DIRECT FROM PRIMARY ORE PROCESSING ▪ Clean–iX® process removes Ore Leach Slurry High Concentration Nickel / Cobalt Nickel & Cobalt Solution Sulphates intermediate processing steps HPAL Ion Purification / ▪ cRIP has 60+ years of Exchange SX operation
Slide 9: Sunrise Process Flowsheet
SUNRISE PROCESS FLOWSHEET FOUR-STAGE PROCESS FROM ORE DIRECT TO SULPHATES MINING 1 & BENEFICIATION Ore is mined, crushed and mixed with water to make a slurry HIGH PRESSURE 2 ACID LEACHING Slurry treated at high pressure, high temperature & low pH in autoclaves to leach metals C L E AN T E Q S U N R
Slide 10: Sunrise Process Flowsheet
SUNRISE PROCESS FLOWSHEET FOUR-STAGE PROCESS FROM ORE DIRECT TO SULPHATES METAL 3 EXTRACTION (Clean iX®) Ion-exchange used to extract nickel, cobalt and scandium from leached solution 4 REFINING Eluate processed via solvent extraction before separation & crystallisation C L E AN T E Q S U N R I S E
Slide 11: Community Update
COMMUNITY UDPATE
Slide 12: Building Our Social Licence
BUILDING OUR SOCIAL LICENCE ▪ Regional community briefings and meetings: 1:1 and groups ▪ Advertising local employment and procurement: meetings scheduled for July 2018 ▪ Building our NSW team: Environmental Specialist, HR recruiter recently joined ▪ Many ways to stay in touch: newsletters, eNews, w
Slide 13: Local Shire Council Site Tour
LOCAL SHIRE COUNCIL SITE TOUR C L E AN T E Q S U N R I S E P AG E 1 3
Slide 14: It's Been a Busy Few Months
IT’S BEEN A BUSY FEW MONTHS C L E AN T E Q S U N R I S E P AG E 1 4
Slide 15: Employment EOI Statistics
EMPLOYMENT EOI STATISTICS Trundle / Tullamore / Fifield = 21 Parkes = 27 Condobolin = 33 NSW TOTAL = 125 All EOI 167 Forbes = 9 Other NSW = 35 C L E AN T E Q S U N R I S E P AG E 1 5
Slide 16: Procurement EOI Statistics
PROCUREMENT EOI STATISTICS Trundle / Tullamore / Fifield = 3 Parkes = 11 Condobolin = 10 NSW TOTAL = 44 All EOI 63 Forbes = 2 Other NSW = 18 C L E AN T E Q S U N R I S E P AG E 1 6
Slide 17: Modification Update
MODIFICATION UDPATE
Slide 18: Modification Applications Update
MODIFICATION APPLICATIONS UPDATE Optimisation Modification (MOD 4) • Modification 4 seeks approval for the opportunities identified in the Optimisation Study. • EA submitted in November 2017. • Responses to Submissions submitted in February 2018. • Response to DP&E additional information request sub
Slide 19: Modification Applications Update
MODIFICATION APPLICATIONS UPDATE Accommodation Camp Modification (MOD 6) • Modification 6 seeks approval for the relocation of the accommodation camp. • EA submitted in January 2018. • Response to Submissions submitted in February 2018. • Approved May 2018 C L E AN T E Q S U N R I S E P AG E 1 9
Slide 20: Environmental Management
ENVIRONMENTAL MANAGEMENT
Slide 21: Environmental Management: Air Quality Assessment
ENVIRONMENTAL MANAGEMENT Air Quality Assessment • Assessment prepared in accordance with EPA’s Approved Methods for the Modelling and Assessment of Air Pollutants in NSW. • Model used to predict potential air quality impacts – considers modified Project operations (included predicted stack emissions
Slide 22: Environmental Management: Air Quality Monitoring
ENVIRONMENTAL MANAGEMENT Air Quality Monitoring • AQMP will be prepared prior to construction in consultation with the EPA and to the satisfaction of the DP&E. • The AQMP will include an air quality monitoring program for evaluating and reporting on: • baseline monitoring undertaken prior to the Pro
Slide 23: Environmental Management: Air Quality Monitoring
ENVIRONMENTAL MANAGEMENT Air Quality Monitoring • Air quality monitoring will be conducted at: • locations representative of the privately-owned receivers most likely to be affected by Project air quality emissions; and • the sulphuric acid plant stack. • Parameters – dust deposition, particulate ma
Slide 24: Environmental Management: Borefield
ENVIRONMENTAL MANAGEMENT Borefield • The Project borefield will be the primary Project water supply. • Development Consent DA 374-11-00 allows for the extraction and transfer of up to 6,390 ML/year. • Clean TeQ is currently approved to extract approximately 3,154 ML/year from the borefield located i
Slide 25: Environmental Management
ENVIRONMENTAL MANAGEMENT C L E AN T E Q S U N R I S E P AG E 2 5
Slide 26: Environmental Management: Borefield Management
ENVIRONMENTAL MANAGEMENT Borefield Management • Borefield operated in accordance with the requirements of: • Project Development Consent; and • Water Access Licences. • These approvals include (but not limited to): • extraction limits; • requirement to develop a borefield operational strategy (inclu
Slide 27: Environmental Management: Groundwater Management Plan
ENVIRONMENTAL MANAGEMENT Groundwater Management Plan • GWMP must be prepared in consultation with DI-Water and the EPA, and must be approved by the Secretary of the DP&E prior to construction. • GWMP must include: • Baseline groundwater data (levels, yield and quality) in privately-owned groundwater
Slide 28: Environmental Management: Groundwater Works Program – Borefield
ENVIRONMENTAL MANAGEMENT Groundwater Works Program – Borefield • To inform the GWMP (e.g. trigger levels, response measures) for the operational phase, Clean TeQ will undertake a Groundwater Works Program during 2018, including: • 2018 Bore Census to identify groundwater users in the vicinity of the
Slide 29: Environmental Management: Groundwater Works Program – Borefield
ENVIRONMENTAL MANAGEMENT Groundwater Works Program – Borefield • Clean TeQ has engaged ENRS to undertake the 2018 Bore Census. • 2018 Bore Census purpose is to: • Identify existing groundwater users in the vicinity of the borefield. • Update and/or add to the existing baseline information on the bor
Slide 30: Environmental Management: Groundwater Works Program – Borefield
ENVIRONMENTAL MANAGEMENT Groundwater Works Program – Borefield • A groundwater model will be developed by a suitably qualified groundwater expert in accordance with contemporary standards – e.g. the Australian National Groundwater Modelling Guidelines. • The groundwater model will be used to inform
Slide 31: Environmental Management: Groundwater Works Program – Mine
ENVIRONMENTAL MANAGEMENT Groundwater Works Program – Mine • Clean TeQ will undertake the following: • A bore census in the vicinity of the mine site will be undertaken after the borefield bore census. • Develop a contemporary groundwater model for the mine site prior to the commencement of mining op
Slide 32: Environmental Management: Compensatory Water Supply
ENVIRONMENTAL MANAGEMENT Compensatory Water Supply • Development Consent requires: The Applicant must provide a compensatory water supply to anyone whose basic landholder water rights (as defined in the Water Management Act 2000) are adversely and directly impacted as a result of the development. Th
Slide 33: Other Items
OTHER ITEMS
Slide 34: Other Items: Project Employment Opportunities
OTHER ITEMS Project Employment Opportunities • The Project workforce would include: • Construction Phase – up to 1,000 personnel • Operations Phase – approximately 300 personnel. • Approximately one-third of the operational workforce would be located at the Parkes Operation Centre. • Clean TeQ will
Slide 35: Other Items: Project Employment Opportunities
OTHER ITEMS Project Employment Opportunities • Clean TeQ will offer apprenticeships and traineeships. • Clean TeQ has commenced engagement with local Aboriginal community members to develop employment opportunities for members of the local Aboriginal community. C L E AN T E Q S U N R I S E P AG E 3
Slide 36: Other Items: Contributions to Government
OTHER ITEMS Contributions to Government • Clean TeQ will pay taxes, rates, contributions, fees to government in accordance with relevant legislation: • Commonwealth Government – Corporate Tax; • NSW Government – Royalties, Payroll Tax, etc; and • Local Government – Rates, VPA Contributions. Mobile P
Slide 37: Questions & Answers
QUESTIONS & ANSWERS
Slide 38: Disclaimer
DISCLAIMER IMPORTANT INFORMATION This presentation has been prepared by the management of Clean TeQ Holdings Limited (the ‘Company’) in connection with meetings with investors and potential investors and not as specific advice to any particular party or person. The information is based on publicly a