Nickel Industries Limited · ASX:NIC

Nickel Industries — Q4 2025 Earnings Presentation

11 slides from Nickel Industries's earnings presentation, Feb 23, 2026

  1. Slide 1: Quarterly Activities Presentation

    Nickel Industries Limited (ASX:NIC) Quarterly Activities Presentation For the period ended 31 December 2025

  2. Slide 2: Safety and Sustainability

    Safety and Sustainability ▪ The Company-wide 12-month lost time injury frequency rate (LTIFR) as at end of December 2025, was 0.00, with no lost time injuries (LTI) recorded during the quarter, against 3.8 million safe man hours registered. For the twelve months to 31 December 2025, there were 17.7

  3. Slide 3: December quarter review

    December quarter review US$37.3m Adjusted EBITDA from Operations. Mining operations impacted by RKAB delay. Strong HPAL contribution ▪ RKEF nickel metal production of 31,561 tonnes – 1% higher than September quarter (31,148 tonnes) ▪ RKEF Adjusted EBITDA of US$35.0m – 13% lower than September quarte

  4. Slide 4: RKEF operations

    RKEF operations (1) ▪ RKEF production increased 1% Production Units Q3 2025 Q4 2025 Variance ▪ Cash costs were 2% higher than the previous quarter NPI production tonnes 263,430 269,528 2% predominantly due to higher nickel ore costs offset by Nickel grade % 11.8 11.7 (1%) lower electricity costs Tot

  5. Slide 5: HPAL operations

    HPAL operations (1) ▪ HNC produced 21,441 tonnes of nickel and 2,301 Production Units Q3 2025 Q4 2025 Variance tonnes of cobalt, outperforming HNC’s nameplate capacity by 43% Attributable HNC Ni tonnes 2,166 2,144 (1%) Production ▪ Combined operating cash costs increased by 10% Co tonnes 192 230 20%

  6. Slide 6: ENC Project update

    ENC Project update Integrated nickel Refinery ▪ Standalone unit testing is complete and wet commissioning equipment has been set up in anticipation of final commissioning of end-to-end nickel cathode production ▪ Installation of crystallisers to produce nickel and cobalt sulphates has been completed

  7. Slide 7: Mining operations

    Mining operations (1) Production Units Q3 2025 Q4 2025 Variance ▪ Hengjaya Mine experienced substantial downtime as the RKAB extension was not granted until 12 Saprolite production wmt 1,290,014 445,902 (65%) December Limonite production wmt 4,627,943 1,220,171 (74%) ▪ This delay resulted in US$18m

  8. Slide 8: Sampala Project

    Sampala Project ▪ The Company anticipates receiving approval for the ETL RKAB by the end of Q1’2026 ▪ The Company is targeting submitting the feasibility study for the ANN IUP by the end of Q1’2026. The feasibility study includes mine planning, slurry preparation plant and mine infrastructure layout

  9. Slide 9: ENC 10% acquisition by strategic partner

    ENC 10% acquisition by strategic partner Transaction Overview Strategic Value of Transaction Represents Nickel Industries’ entry into supplying Western ✓ aerospace and aeronautical sectors, which demand the highest product quality and strictest qualification standards 10% 44% (1) 46% (2) Sphere’s ac

  10. Slide 10: Aerial overview of ENC construction – video link

    Aerial overview of ENC construction – video link 10

  11. Slide 11: Further information

    Further information Justin Werner Chris Shepherd Managing Director Chief Financial Officer jwerner@nickelindustries.com cshepherd@nickelindustries.com 11

Nickel Industries — Q4 2025 Earnings Presentation on 6ix