  1. Slide 1: Building a New Asian Copper Mining Business

    BUILDING A NEW ASIAN COPPER MINING BUSINESS ANNUAL GENERAL MEETING – JULY 2022 AIM : ARS JUNE 2019

  2. Slide 2: Forward Looking Statement

    Forward Looking Statement The information contained in this confidential document (the “Presentation”) has been prepared by Asiamet Resources Limited (the “Company” or "Asiamet") solely for informational purposes. Information contained herein does not purport to be complete and is subject to certain

  3. Slide 3: Company Overview

    Company Overview Asiamet Resources Limited (AIM:ARS) is focused on the development and growth of its high quality portfolio of copper projects in Indonesia HIGH QUALITY COMPELLING VALUE PROVEN TEAM PORTFOLIO BIG GROWTH • Rare portfolio of base and • JORC Resources contain • Internationally recognise

  4. Slide 4: 2021-22 Achievements

    2021-22 Achievements 2021 • Approval of the key environmental permit (AMDAL) for the BKM Project • Completed capital raising for gross proceeds of approximately $14.0 million in February 2021 • Key appointments to board (Eva Armila Djauhari as NED) and management (Andrew Neale GM BKM Project) • Comp

  5. Slide 5: DOID – Due Diligence and ITE Process

    DOID – Due Diligence and ITE Process • Initial Due Diligence on project completed by DOID’s independent consultants • International Bank engaged to advise on debt finance requirements • As part of the initial financing step a bank preferred Independent Technical Expert (ITE) was appointed to review

  6. Slide 6: Indicative Timeline

    Indicative Timeline The indicative timeline below outlines the key activities the Company is working towards to bring the BKM copper project into production. Feasibility Financing Financing Construction Study Update Permitting Site Prep Work Commissioning Construction Ramp-up • Complete FS • Commenc

  7. Slide 7: Environment and Community

    Environment and Community Active programmes  Asiamet has been closely involved in community and social development in Central Kalimantan since commencing exploration work in 1981. Company established Yayasan Tambuhak Sinta (YTS) foundation in 1997 and has provided management, staffing, and financia

  8. Slide 8: Beutong Project – Exciting Cu-Au Discovery

    Beutong Project – Exciting Cu-Au Discovery High Quality Deposit with Huge Upside Potential  Large, high quality porphyry Cu-Au-Mo deposit – only 60km from a seaport and near existing infrastructure (road and power)  Measured + Indicated JORC Resources (100%)  1.2BIbs Cu, 0.4Moz Au, 5.7Moz Ag, 20M

  9. Slide 9: Copper – A Key Driver of the Energy Transition

    Copper – A Key Driver of the Energy Transition BKM Commences Production 9

  10. Slide 10: Why Invest in Asiamet Resources?

    Why invest in Asiamet Resources? Why Invest in Asiamet Resources?? Quality Assets and People Value Timing  Focussed team with a proven track  Copper market fundamentals  Market re-rate potential as BKM record - Indonesia, discovery, mine remain strong over the med-long project is financed and com