Slide 1: Copper Focus Asian Base
AIM : ARS COPPER FOCUS ASIAN BASE BUILD READY COPPER PROJECT HIGH QUALITY RESOURCE BASE ADVANCED PROPOSED ASSET SALE ARS AGM – 09 December 2025
Slide 2: Forward Looking Statement
FORWARD LOOKING STATEMENT The information contained in this confidential document (the “Presentation”) has been This presentation contains “forward-looking statements” including but not limited prepared by Asiamet Resources Limited (the “Company” or "Asiamet") solely for to, statements with respect
Slide 3: Company Overview
COMPANY OVERVIEW Quality Assets in Copper and Precious Metals HIGH QUALITY COMPELLING VALUE PROVEN TEAM PORTFOLIO BIG GROWTH Rare portfolio of base and JORC (2012) Resources Internationally recognised precious metal projects with contain 2.9Mt Cu, 2.1Moz team with proven track district scale upside
Slide 4: Corporate Profile
CORPORATE PROFILE Energy transition metals SHARE PRICE MARKET CAPITALISATION CASH Indonesia strong growth £56.1m US$1.47m Direct presence in Indonesia 1.73p US$74.8m Million Leadership invested ~10% of share capital Share price 05/12/25 3,244 million shares on issue No Corporate Debt Cash (as at 30
Slide 5: Corporate Profile: 12-Month Share Price Performance
CORPORATE PROFILE ARS 12-MONTH SHARE PRICE PERFORMANCE: 52 Week Hi – 1.70p; 52 Week Lo – 0.60p (at closing) Consolidation prior to issuance of May 2025 OFS. Share price re-rating upwards following recent announcement of sale of KSK Project. 5
Slide 6: Company Projects Overview
COMPANY PROJECTS OVERVIEW Beutong IUP (80%) 20yr + 2*10yr Extensions KSK Contract of Work (100%) Resources (JORC 2012) 30yr + 2*10yr Extensions Copper – 2.4Mt (100%) Resources (JORC 2012) Gold – 2.11M Oz (100%) Copper – 473kt Silver – 20.9M Oz (100%) Zinc – 101kt Lead – 40kt Large Porphyry Cu-Au- Mo
Slide 7: 2025 Achievements: BKM Optimised Feasibility Study
2025 ACHIEVEMENTS BKM STAGE 1 OPTIMISED FEASIBILITY STUDY Optimised Feasibility Study delivered in May Final Lenders ITE Review report issued within 2 weeks post completion of FS NPV8 $124m, Initial Capital Cost of $179m, C1 Operating costs $1.79/lb Cu Study outcomes confirmed a fully defined, funda
Slide 8: 2025 Achievements: BKM Strategic Investor Engagement
2025 ACHIEVEMENTS BKM PROJECT STRATEGIC INVESTOR ENGAGEMENT Project financing workstreams commenced in June, following receipt of the BKM Independent Technical Evaluation (ITE) report Grant Samuel appointed as Financial Advisor (25 July) to lead the strategic partnering and equity-funding process fo
Slide 9: 2025 Achievements: Sale of 100% Indokal Limited
2025 ACHIEVEMENTS CORPORATE TRANSACTION SALE OF 100% INDOKAL LIMITED 6th November: Asiamet entered into a conditional sale and purchase Agreement (“SPA”) for the proposed sale of 100% of its holding in Indokal Limited (Hong Kong) Indokal directly and indirectly holds 100% of PT Kalimantan Surya Kenc
Slide 10: 2026 Outlook
2026 OUTLOOK INDOKAL SALE COMPLETION + BEUTONG STRATEGY Primary focus on satisfying all Conditions Precedent required to close the Indokal sale, followed by return of capital to shareholders Advance evaluation of the optimal pathway for Beutong, including potential engagement with a strategic partne
Slide 11: Contact Information
CONTACT AIM | ARS Darryn McClelland INFORMATION Chief Executive Officer E: darryn.mcclelland@asiametresources.com W: www.asiametresources.com 11