WSP Global Inc · TSX:WSP
WSP Global — TotalEnergies EP South Africa B.V. (TEEPSA) — Technical Presentation (December 2022)
25 slides from WSP Global's technical presentation, December 2022

Slide 1: ESIA for the Proposed offshore PR and EA Application for Block 11B/12B by TEEPSA
ESIA for the Proposed offshore PR and EA Application for Block 11B/12B by TEEPSA Introductory Meeting with Local Authorities / Online Public Meeting

Slide 2: Meeting Objectives
Meeting Objectives ❑ Introduce TEEPSA’s proposed offshore Block 11B/12B development project ❑ Introduce the Environmental and Social Impact Assessment (ESIA) process that is being undertaken as part of TEEPSA’s proposed Production Right and EA process ❑ For the District and Local Municipalities to i

Slide 3: Draft Agenda
DRAFT AGENDA 1. Welcome and Introductions 2. Formal acceptance of Draft Agenda 3. Meeting objectives 4. Meeting administration 5. Introduction to the proposed Block 11B/12B development project 6. Overview of the ESIA and public participation process 6.1 Environmental baseline, proposed specialist st

Slide 4: Meeting Protocols
Meeting Protocols ❑ Before asking a question / commenting, please state your name, surname and organisation ❑ Please work through the facilitator (a translator is available) ❑ Respect one another ❑ Give fellow meeting attendees a fair opportunity to participate during discussions ❑ Agree to disagree

Slide 5: Introduction to TotalEnergies EP South Africa B.V. (TEEPSA)
Introduction to TotalEnergies EP South Africa B.V. (TEEPSA) Block 11B/12B Scoping Presentation December 2022

Slide 6: TotalEnergies is continuing to transform
TotalEnergies is continuing to transform 1954 1955 1963 1970 1980 2003 2021 + Climate Ambitions Human Rights Ambitions Societal and Environment Our vision: Biodiversity Ambitions Transparent Reporting https://https://totalenergies.com/company/transfo 7 rming

Slide 7: Block 11B/12B Overview
Block 11B/12B Overview History: • ER issued in 2012 • TEEPSA operator since 2013 • 2 x Explo wells drilled (2018 + 2020) • 3 x Seismic campaigns (2019 + 2020) • 2 x Gas with associated condensate discoveries • ER expiry – Sept 2022 PR Application: • Application submitted Sept 2022 • Reduced area of

Slide 8: Oil & gas life cycle
Oil & gas life cycle Current phase * Indicative timelines Decision Decision FID Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Exploration Appraisal Development? Production? Decommissioning 9-12* 3-5 * 5-10* ~20 * 1-2* years years years years years Commercial / Is there any field? Oil and gas Decommissioni

Slide 9: Proposed activities Overview
Proposed activities Overview Development: • Drilling of up to six (6) development and appraisal wells • Laying of deep-water subsea manifolds and flowlines connecting wells • Connection to the existing PetroSA F-A Platform at Block 9 – subsea production pipeline ~109km. • Estimated production platea

Slide 10: Proposed activities (2)
Proposed activities (2) Wells + SPS SURF Riser F-A Exiting pipes to shore Block 11B/12B Block 9 New Gas + Condensate Production Pipeline Manifold Wells Flow Lines Production Phase Construction Phase Drilling Unit for Support vessels Helicopters for Well Drilling for drilling Crew Subsea construction

Slide 11: Thank you
TS TotalEnergies Thank you

Slide 12: Environmental and Social Impact Assessment
Environmental and Social Impact Assessment

Slide 13: Project Location
15 Project Location ; Weck Pipeline Route Option Pipeline Route Basecase Existing Wells Platforms In Place — Pipetines | Project pipeline corridor Sea floor contours Block 118/126, ‘CI Exploration Right Area 1 Production Right Application Area, Project Development Ares __Explorstory Prionty Area Sen

Slide 14: Proposed Project Activities
Proposed Project Activities Production ❑ Drilling up to six (6) offshore production and four (4) appraisal wells ❑ Connecting the offshore wells by installing subsea manifolds and flowlines ❑ Connection of manifolds and flowlines to the existing PetroSA F-A Platform at Block 9 Offshore Field, via a

Slide 15: ESIA Process
\\\ ESIA Process

Slide 16: Regulatory Framework - National Environmental Management Act
Regulatory Framework- National Environmental Management Act (Act No. 107 of 1998) Application for Environmental Authorisation in terms of the National Environmental Management Act (Act No. 107 of 1998) Listed activities specified in the NEMA Environmental Impact Assessment (EIA) Regulations of 2014 (

Slide 17: Environmental Application Process (1)
Environmental Application Process (1) We are here 19

Slide 18: Environmental Application Process (2)
Environmental Application Process (2) 20

Slide 19: Environmental Baseline
\\\ Environmental Baseline

Slide 20: Specialist Studies
Specialist Studies Professor Rose Boswell (DSI-NRF South African Research Chair in Ocean Cultures and Heritage, Nelson Mandela University Marine Acoustic Air Quality Climate Change Marine Ecology Cultural Heritage Economic Effect Oil Spill and Drill Discharge Modelling Closure Plan Social 22

Slide 21: Potential Impacts to be Assessed in the ESIA
Potential Impacts to be Assessed in the ESIA Socio-economic Biological Environment ❑ Marine traffic disruption Physical ❑ Loss of fishing gear Environment ❑ Crushing marine ❑ Loss of fishing grounds benthos ❑ Vessel collision ❑ Air quality ❑ Drillship flaring ❑ Social disruption ❑ Seawater quality h

Slide 22: Next steps: ESIA
Next steps: ESIA ❑ Prepare Comment and Responses Register (after 03 February 2023) ❑ Prepare the final Scoping Report and Environmental Management Plan ❑ Submit to Competent Authority 25

Slide 23: Next steps: Public Participation
Next steps: Public Participation ❑ Public meetings in January 2023: ❑ Mossel Bay – Monday 16 January 2023 ❑ Mossel Bay – Tuesday 17 January 2023 ❑ George – Wednesday 18 January 2023 ❑ Knysna – Thursday 19 January 2023 ❑ Plettenberg Bay – Friday 20 January 2023 ❑ Cape St Francis – Saturday 21 January

Slide 24: Block 11B/12B ESIA Public Consultation Office
Block 11B/12B ESIA Public Consultation Office WSP Group Africa (Pty) Ltd, PO Box 6001, Halfway House, 1685 Tel: +27 (0) 11 254 4800, or WhatsApp: +27 (0) 76 694 3842 Fax: +27 (0) 11 315 0317 Email: teepsaEIA@WSP.com Download information from the WSP website: https://www.WSP.com/global-locations/afri

Slide 25: Questions / Discussion
\\\ Questions / Discussion
Source: company website
More decks from WSP Global Inc
Q3 2026 Earnings Presentation13 slides · Nov 5, 2026
Q2 2026 Earnings Presentation13 slides · Aug 6, 2026
Investor Presentation (July 2026)28 slides · July 2026
Q1 2026 Earnings Presentation13 slides · May 7, 2026
Q4 2025 Earnings Presentation14 slides · Feb 26, 2026
Fact Sheet (2025)2 slides · Nov 6, 2025