  1. Slide 1: ESIA for the Proposed offshore PR and EA Application for Block 11B/12B by TEEPSA

    ESIA for the Proposed offshore PR and EA Application for Block 11B/12B by TEEPSA Introductory Meeting with Local Authorities / Online Public Meeting

  2. Slide 2: Meeting Objectives

    Meeting Objectives ❑ Introduce TEEPSA’s proposed offshore Block 11B/12B development project ❑ Introduce the Environmental and Social Impact Assessment (ESIA) process that is being undertaken as part of TEEPSA’s proposed Production Right and EA process ❑ For the District and Local Municipalities to i

  3. Slide 3: Draft Agenda

    DRAFT AGENDA 1. Welcome and Introductions 2. Formal acceptance of Draft Agenda 3. Meeting objectives 4. Meeting administration 5. Introduction to the proposed Block 11B/12B development project 6. Overview of the ESIA and public participation process 6.1 Environmental baseline, proposed specialist st

  4. Slide 4: Meeting Protocols

    Meeting Protocols ❑ Before asking a question / commenting, please state your name, surname and organisation ❑ Please work through the facilitator (a translator is available) ❑ Respect one another ❑ Give fellow meeting attendees a fair opportunity to participate during discussions ❑ Agree to disagree

  5. Slide 5: Introduction to TotalEnergies EP South Africa B.V. (TEEPSA)

    Introduction to TotalEnergies EP South Africa B.V. (TEEPSA) Block 11B/12B Scoping Presentation December 2022

  6. Slide 6: TotalEnergies is continuing to transform

    TotalEnergies is continuing to transform 1954 1955 1963 1970 1980 2003 2021 + Climate Ambitions Human Rights Ambitions Societal and Environment Our vision: Biodiversity Ambitions Transparent Reporting https://https://totalenergies.com/company/transfo 7 rming

  7. Slide 7: Block 11B/12B Overview

    Block 11B/12B Overview History: • ER issued in 2012 • TEEPSA operator since 2013 • 2 x Explo wells drilled (2018 + 2020) • 3 x Seismic campaigns (2019 + 2020) • 2 x Gas with associated condensate discoveries • ER expiry – Sept 2022 PR Application: • Application submitted Sept 2022 • Reduced area of

  8. Slide 8: Oil & gas life cycle

    Oil & gas life cycle Current phase * Indicative timelines Decision Decision FID Phase 1 Phase 2 Phase 3 Phase 4 Phase 5 Exploration Appraisal Development? Production? Decommissioning 9-12* 3-5 * 5-10* ~20 * 1-2* years years years years years Commercial / Is there any field? Oil and gas Decommissioni

  9. Slide 9: Proposed activities Overview

    Proposed activities Overview Development: • Drilling of up to six (6) development and appraisal wells • Laying of deep-water subsea manifolds and flowlines connecting wells • Connection to the existing PetroSA F-A Platform at Block 9 – subsea production pipeline ~109km. • Estimated production platea

  10. Slide 10: Proposed activities (2)

    Proposed activities (2) Wells + SPS SURF Riser F-A Exiting pipes to shore Block 11B/12B Block 9 New Gas + Condensate Production Pipeline Manifold Wells Flow Lines Production Phase Construction Phase Drilling Unit for Support vessels Helicopters for Well Drilling for drilling Crew Subsea construction

  11. Slide 11: Thank you

    TS TotalEnergies Thank you

  12. Slide 12: Environmental and Social Impact Assessment

    Environmental and Social Impact Assessment

  13. Slide 13: Project Location

    15 Project Location ; Weck Pipeline Route Option Pipeline Route Basecase Existing Wells Platforms In Place — Pipetines | Project pipeline corridor Sea floor contours Block 118/126, ‘CI Exploration Right Area 1 Production Right Application Area, Project Development Ares __Explorstory Prionty Area Sen

  14. Slide 14: Proposed Project Activities

    Proposed Project Activities Production ❑ Drilling up to six (6) offshore production and four (4) appraisal wells ❑ Connecting the offshore wells by installing subsea manifolds and flowlines ❑ Connection of manifolds and flowlines to the existing PetroSA F-A Platform at Block 9 Offshore Field, via a

  15. Slide 15: ESIA Process

    \\\ ESIA Process

  16. Slide 16: Regulatory Framework - National Environmental Management Act

    Regulatory Framework- National Environmental Management Act (Act No. 107 of 1998) Application for Environmental Authorisation in terms of the National Environmental Management Act (Act No. 107 of 1998) Listed activities specified in the NEMA Environmental Impact Assessment (EIA) Regulations of 2014 (

  17. Slide 17: Environmental Application Process (1)

    Environmental Application Process (1) We are here 19

  18. Slide 18: Environmental Application Process (2)

    Environmental Application Process (2) 20

  19. Slide 19: Environmental Baseline

    \\\ Environmental Baseline

  20. Slide 20: Specialist Studies

    Specialist Studies Professor Rose Boswell (DSI-NRF South African Research Chair in Ocean Cultures and Heritage, Nelson Mandela University Marine Acoustic Air Quality Climate Change Marine Ecology Cultural Heritage Economic Effect Oil Spill and Drill Discharge Modelling Closure Plan Social 22

  21. Slide 21: Potential Impacts to be Assessed in the ESIA

    Potential Impacts to be Assessed in the ESIA Socio-economic Biological Environment ❑ Marine traffic disruption Physical ❑ Loss of fishing gear Environment ❑ Crushing marine ❑ Loss of fishing grounds benthos ❑ Vessel collision ❑ Air quality ❑ Drillship flaring ❑ Social disruption ❑ Seawater quality h

  22. Slide 22: Next steps: ESIA

    Next steps: ESIA ❑ Prepare Comment and Responses Register (after 03 February 2023) ❑ Prepare the final Scoping Report and Environmental Management Plan ❑ Submit to Competent Authority 25

  23. Slide 23: Next steps: Public Participation

    Next steps: Public Participation ❑ Public meetings in January 2023: ❑ Mossel Bay – Monday 16 January 2023 ❑ Mossel Bay – Tuesday 17 January 2023 ❑ George – Wednesday 18 January 2023 ❑ Knysna – Thursday 19 January 2023 ❑ Plettenberg Bay – Friday 20 January 2023 ❑ Cape St Francis – Saturday 21 January

  24. Slide 24: Block 11B/12B ESIA Public Consultation Office

    Block 11B/12B ESIA Public Consultation Office WSP Group Africa (Pty) Ltd, PO Box 6001, Halfway House, 1685 Tel: +27 (0) 11 254 4800, or WhatsApp: +27 (0) 76 694 3842 Fax: +27 (0) 11 315 0317 Email: teepsaEIA@WSP.com Download information from the WSP website: https://www.WSP.com/global-locations/afri

  25. Slide 25: Questions / Discussion

    \\\ Questions / Discussion