Slide 1: Building the ASX's next mid-tier iron ore producer
Building the ASX’s next mid-tier For personal use only iron ore producer ASX:M4M NON-DEAL ROADSHOW PRESENTATION April 2024
Slide 2: Disclaimer and Competent Persons Statement
Disclaimer and Competent Persons Statement DISCLAIMER The purpose of this presentation is to provide general information about Macro Metals Limited (“Macro” or the “Company”). It is not recommended that any person makes any investment decision in For personal use only relation to the Company based s
Slide 3: Investment Highlights
For personal use only Investment Highlights Dedicated Pilbara Focus Infrastructure Fully Funded Solely focused on exploration and Multiple haulage and port Company is fully funded from existing development of iron ore assets in infrastructure solutions cash reserves for exploration and Pilbara Regio
Slide 4: Corporate Snapshot
Corporate Snapshot Simon Rushton – Managing Director MACRO METALS LIMITED Mr Rushton has 20 years extensive operational and corporate expertise across a range of industries including For personal use only mining, logistics, oil & gas and in private legal practice. Mr Rushton’s recent experience incl
Slide 5: Cane Bore – Macro's Flagship Exploration & Development Asset
Cane Bore – Macro’s Flagship Exploration & Development Asset Project Highlights • Extensive CID mesa targets with significant scale potential • Proximal to multiple haulage and port infrastructure solutions For personal use only • Stakeholder engagement process underway • Program of works submitted
Slide 6: Cane Bore – Considerable Scale, Proximal to Infrastructure
Cane Bore – Considerable Scale, Proximal to Infrastructure Callisto Prospect • Visually consistent pisolite channel iron mineralisation throughout For personal use only sequence1 • Mesa rises 25m high and extends for an area of 850 by 1,050m M Europa Prospect • Base of mesa not exposed, substantial
Slide 7: Goldsworthy East – Sitting in the shadow of a giant
Goldsworthy East – Sitting in the shadow of a giant Location • 100km from Port Hedland via Great Northern Highway For personal use only • Project located adjacent to BHP’s Mining lease, directly along strike from Mt Goldsworthy which produced 55mt at 63.5% Fe between 1965 and 1982 Target Potential •
Slide 8: Catho Well – Drill Defined Target With 13km Strike
Catho Well – Drill Defined Target With 13km Strike Location • Project access to Nanutarra Sealed road via 17km of existing For personal use only station tracks Target Potential • 13km of strike and is dissected into three discrete bodies with varying degrees of drill testing on nominal 800 x 200m dr
Slide 9: Pilbara assets – Aggressive timeline
Pilbara assets – Aggressive timeline Project Activity CY 2024 Q2 Q3 Q4 For personal use only • Rock chip sampling • Mapping • Bulk sampling • Drill permitting Work Cane Bore • Maiden RC drilling program • Mineral resource estimation • Environmental surveys Programs • Commencement of development stud
Slide 10: Other Projects
Other Projects For personal use only 10 Investor Presentation | April 2024
Slide 11: Turner – Substantial Conceptual Targets
Turner – Substantial Conceptual Targets Location Located directly adjacent to Rio Tinto’s Turner Syncline Mine, 25km west-north-west of Tom Price For personal use only Target Potential Multiple Channel Iron Deposit (CID) targets defined from satellite imagery interpretation Exploration Plan Site rec
Slide 12: West Pilbara – Potential For Near Term Development
West Pilbara – Potential For Near Term Development Location Located 120km west-north-west of Paraburdoo, proximal to sealed Nanutarra Road. Ashburton Port is For personal use only approximately 260km away via sealed roads. Mineral Resource E08/1997 Indicated Mineral Resource of 11.5Mt at 53.1% Fe, 5
Slide 13: Deepdale – Substantial Conceptual Targets
Deepdale – Substantial Conceptual Targets Location Deepdale Project comprises four exploration licence applications surrounding the Rio Tinto Robe Valley Operations and CZR For personal use only Resources Ltd’s (ASX: CZR) Robe Mesa Project Target Potential Combination of Detrital Iron Deposit (DID)
Slide 14: Wiluna West – Substantial Conceptual Targets
Wiluna West – Substantial Conceptual Targets Gold Valley For personal use only Location Wiluna West Mine Located 40km southwest of Wiluna, 2.3km to the south along strike from Gold Valley’s Wiluna West DSO Hematite operation E53/2031 Significant Drill Results • 13m @ 59.54% Fe, 0.086% P, 6.08% SiO2,
Slide 15: Mogul Copper – EIS Funding & Drilling Permitted
Mogul Copper – EIS Funding & Drilling Permitted Location Located 60km east of Nullagine in the East Pilbara Region of Western Australia For personal use only Target Potential Previous drilling has reported significant results including: • 3.65m @ 3.9 % Cu, 2.89 % Pb, 3.12% Zn, 189 g/t Ag from 12.75m
Slide 16: Thank you
Thank you For personal use only Contact Us Simon Rushton Managing Director E Simon@macrometals.com.au Alex Cowie Investor Relations E alexc@nwrcommunications.com.au