Contango Silver & Gold Inc. · AMEX:CTGO

Contango Silver & Gold — Contango ORE — Precious Metals Summit Zurich November 2022

33 slides from Contango Silver & Gold's conference presentation, Nov 16, 2022

  1. Slide 1: Precious Metals Summit Zurich November 2022 Corporate Update

    Precious Metals Summit Zurich November 2022 Corporate Update and Plans for 2022-2024

  2. Slide 2: Forward Looking Statement

    FORWARD LOOKING STATEMENT The Feasibility Study (“FS”) referenced herein that relates to Peak Gold, LLC (“Peak Gold”), was prepared by Kinross Gold Corporation (“Kinross”), which controls the Manager of Peak Gold and holds 70% of its outstanding membership interests, in accordance with Canadian Nati

  3. Slide 3: Cautionary Note Regarding Estimates of Measured, Indicated and Inferred Resources

    The Preliminary Economic Assessment (“PEA”) referenced herein was prepared in accordance with Canadian National Instrument 43-101 (NI 43-101). CORE is not subject to regulation by Canadian regulatory authorities and no Canadian regulatory authority has reviewed the PEA or passed upon its accuracy or

  4. Slide 4: Corporate Overview

    CORPORATE OVERVIEW Now trading on the NYSE American: CTGO 6.77 Million Shares Outstanding 6.87 Million Shares Fully Diluted 100,000 Options; No Warrants $20 million Convertible Debt (8% Coupon) Convertible @ $30.50 ~ $US17.8 Million Cash as of September, 2022 Contango 30% owner of Peak JV; Kinross O

  5. Slide 5: Developing Alaska's Next Gold Mines

    Developing Alaska’s Next Gold Mines Manh Choh – Development Stage Project under construction in partnership with Kinross (70%) and the Alaska Native Tetlin Tribe (Royalty) 100% Owned Lucky Shot Mine – Exploring historic high-grade gold mine Three Early-Stage Exploration Projects: Shamrock Eagle-Hona

  6. Slide 6: Manh Choh Gold Deposit

    Manh Choh Gold Deposit 1.3 Million ounce gold Measured plus Indicated Resources1 Average grade = 4g/t Gold1 Located in Alaska on the Alaska Hwy On Private Land Owned by the Tetlin Alaska Native Tribe Business Partnership with Kinross – Paid $93 Million for 70% interest Using the Fort Knox Milling Fa

  7. Slide 7: Near-Term Production Potential & Exploration Upside

    NEAR-TERM PRODUCTION POTENTIAL & EXPLORATION UPSIDE 7 MANH CHOH GOLD PROJECT NYSE-A:CTGO September 2020 entered into JV agreement between Contango (30%) and Kinross (70% and Operator) to form new Peak Gold LLC, with Royal Gold and Tetlin Tribe retaining royalty interests; Plan is to mine Manh Choh G

  8. Slide 8: Manh Choh Gold Project: Anticipated Economics

    MANH CHOH GOLD PROJECT: Anticipated Economics Using existing infrastructure at Fort Knox, Peak Gold LLC is planning on a 2024 start date Kinross estimates 914,000 GEO production over a 4.5-years equating to roughly 225,000 GEO per annum (30% to Contango Ore = 67,500 GEO/Yr)1 Using elevated cut-off g

  9. Slide 9: Manh Choh Gold Project Location

    The project is located 29 km (18 mi) from the Alaska Hwy and 400 km (240 mi) to the Fort Knox Milling Complex 9 MANH CHOH GOLD PROJECT LOCATION MANH CHOH DEPOSIT Image used with permission from Kinross Manh Choh

  10. Slide 10: Peak Gold JV Project Highlights

    PEAK GOLD JV 10 Processing ore from the Peak Gold Project at Fort Knox avoids mill construction and is expected to decrease execution risk, lower capital expenditures, drive attractive returns, and reduce the project’s environmental footprint and permitting requirements. Leverages Fort Knox’s succes

  11. Slide 11: Manh Choh Update Construction Underway

    11 Manh Choh Update Construction underway

  12. Slide 12: Manh Choh Update – Road Construction Underway

    12 Manh Choh Update – Road Construction underway

  13. Slide 13: Manh Choh Update – Road Construction Underway

    13 Manh Choh Update – Road Construction Underway

  14. Slide 14: Manh Choh Update – Camp Construction Completed

    14 Manh Choh Update – Camp Construction Completed

  15. Slide 15: Peak Gold LLC Exploration Highlights

    PEAK GOLD LLC 15 Exploration Highlights Completed ~$3.0 million exploration program Q4 2020 primarily directed at metallurgical and geotechnical drilling, and on-going environmental studies to advance feasibility and permitting Completed ~$3 million in 2021 exploration program and conducted resource

  16. Slide 16: Manh Choh Gold Project and Surrounding Targets

    16 MANH CHOH GOLD PROJECT AND SURROUNDING TARGETS Main MC North MC $3 Million Exploration Program Planned for 2022 Exploration for New Resources in Chief Danny Area – 4000 meters (13,000 ft) in 15 to 20 holes Further evaluation of 685,000 acre Manh Choh property Additional regional stream sediment s

  17. Slide 17: Asset Summary

    ASSET SUMMARY 17 Peak Gold Project ~(675,000 Acres) State Claims (~160,000 Acres) Peak Gold JV 70% 30% 100% State Mining Claims Part of PGLLC 100% Contango ORE The Manh Choh project consists of a ~685,000 acres land package including ~13,423 acres of State Mining Claims  Roughly the size of Rhode I

  18. Slide 18: Lower Risk & Reduced Timeline to Production Decision

    18 LOWER RISK & REDUCED TIMELINE TO PRODUCTION DECISION DRILLING SCOPING STUDY PERMITTING & FEASIBILITY PRODUCTION DETAILED DESIGN PROCURMENT CONSTRUCTION $19 million Program in 2021: Resource In-fill, Hydrology, Geotechnical, Metallurgical Engineering; Environment and Community Outreach With ~$2 mi

  19. Slide 19: Reference: Hart 2005 Tintina Gold Province

    19 1 Hart, C.J.R., 2005. Mid-Cretaceous Magmatic Evolution and Intrusion-related Metallogeny of the Tintina Gold Province, Yukon and Alaska. Unpublished PhD thesis, University of Western Australia, 198 p. 1

  20. Slide 20: Lucky Shot Portal Circa 1930

    Lucky Shot Portal Circa 1930 20

  21. Slide 21: Lucky Shot Portal Circa 1930

    Lucky Shot Portal Circa 1930 21

  22. Slide 22: Lucky Shot Property Historic Resources

    Lucky Shot Property Historic Resources1 Historic M&I Reserve on Adjacent Coleman Segment of LS Vein: 206k Tonnes @ 18.3 g/t Gold for 121,500 Ounces of Contained Gold2 1 The historical production information presented is based upon reports file by the US Geological Survey from information provided by

  23. Slide 23: Lucky Shot Vein

    Lucky Shot Vein: +1 mile (1.6 km) strike length and open along strike and down dip 23 Coleman Adit Lucky Shot “500” Adit War Baby Adit Looking NNE Enserch Tunnel

  24. Slide 24: Coleman block and Lucky Shot block

    4 Coleman block Bey Lucky Shot block wae)

  25. Slide 25: Lucky Shot Update - Safety First Approach

    Lucky Shot Update - Safety First Approach Zero LTIs 25

  26. Slide 26: Contango Exploration Plan for Lucky Shot Project

    Contango Exploration Plan for Lucky Shot Project Rehab and extend existing Enserch tunnel to explore the Lucky Shot vein down-dip - prep for exploration drilling in three stages: Stage 1a Drift 500 meters along footwall and parallel to vein for detailed in-fill drilling; Stage 1b Continue Enserch tu

  27. Slide 27: Lucky Shot – Pilot Hole Drill Holes

    27 Lucky Shot – Pilot Hole Drill Holes Total of 23 completed to date All holes intersected the Lucky Shot Vein 10 pilot holes from Western & Eastern Ballrooms plus 6 fan holes from Western Footwall Drift Many contain Visible Gold (VG) ASSAYS PENDING! Completed 7 holes from Tunnel Face Extended tunne

  28. Slide 28: Lucky Shot vein section with visible gold

    War Baby Fault Lucky Shot vein VG VG VG VG Coleman Fault VG VG

  29. Slide 29: 15-20 Meter spacing

    15-20 Meter spacing ee,

  30. Slide 30: Lucky Shot – At the Face with Lucky Shot Vein

    30 Lucky Shot – At the Face with Lucky Shot Vein

  31. Slide 31: Thank You

    = CONTANGO 022 THANKYOU

  32. Slide 32: Corporate Inquiries

    Corporate Inquires:info@contangoore.com+1-778-386-6227www.contangoore.com NYSE American: CTGO Twitter: @orecontangoLinkedIn: Contango OREInstagram: ContangoOREFacebook: Contango ORE

  33. Slide 33: Non-GAAP Forward Looking Estimates Note

    This presentation contains forward looking estimates of all-in sustaining cost (“AISC”), resources and EBITDA, which are a financial measure not determined in accordance with United States generally accepted accounting principles (“GAAP”). We cannot provide a reconciliation of estimated AISC, resour

Contango ORE — Precious Metals Summit Zurich November 2022 on 6ix