KGHM Polska Miedz S.a. · GPW:KGH

KGHM Polska Miedz — H1 2021 Earnings Presentation

47 slides from KGHM Polska Miedz's earnings presentation, Aug 18, 2021

  1. Slide 1: Results of the KGHM Group for the first half of 2021

    Slide 1: Results of the KGHM Group for the first half of 2021

    Results of the KGHM Group for the first half of 2021 Lubin, 17-18 August 2021

  2. Slide 2: Cautionary Statement

    Slide 2: Cautionary Statement

    Cautionary Statement This presentation was prepared by KGHM Polska Miedź S.A. (KGHM). The presentation is strictly of an informational nature and should not be construed as containing investment advice. The users of this presentation are solely responsible for their own analysis and assessment of th

  3. Slide 3: Agenda

    Slide 3: Agenda

    Agenda 1. Responsible production – 2. Macroeconomic situation 3. Production results of KGHM’s metallurgical plants and execution of main targets the KGHM Group by segment with the Copper Mark certificate 4. Financial results 5. Advancement of 6. Supporting slides – of the KGHM Group development init

  4. Slide 4: We produce copper responsibly

    Slide 4: We produce copper responsibly

    We produce copper responsibly Achievements in 2021:  The Głogów and Legnica smelter/refineries were certified by The Copper Mark – an international program providing a credible The granting of The Copper assurance framework to promote Mark, participation in the responsible production practices CDP

  5. Slide 5: It's worth getting vaccinated

    Slide 5: It's worth getting vaccinated

    It’s worth getting vaccinated We are effectively fighting the spread of the COVID-19 virus and fulfilling the expectations of KGHM’s employees and of society ASSISTANCE ENCOURAGEMENT VACCINATIONS In all of KGHM’s Divisions Every vaccinated employee of Vaccinations directly at the information/registr

  6. Slide 6: Employee safety as a strategic priority for the KGHM Group

    Slide 6: Employee safety as a strategic priority for the KGHM Group

    Employee safety as a strategic priority for the KGHM Group H1 2021 Safety and development Accident ratios1)  ISO 45001:2018 Granting of an Occupational Health and Safety -29% Change2) in LTIFR in KGHM Polska Miedź S.A. Management System Certificate  Leader’s Gold Card of Workplace 18.6 -44% Change

  7. Slide 7: Macroeconomic situation and execution of main targets

    Slide 7: Macroeconomic situation and execution of main targets

    Macroeconomic situation and execution of main targets

  8. Slide 8: Summation of H1 2021 in the KGHM Group

    Slide 8: Summation of H1 2021 in the KGHM Group

    Summation of H1 2021 in the KGHM Group Main macroeconomic factors and aspects of the Group compared to H1 2020 Macroeconomic environment1) Production and C1 cost Financial results +65% +8.6% +32% Copper price Copper production Increase in revenues to PLN 14 506 mn +59% -5% +100% Silver price Silver

  9. Slide 9: Macroeconomic environment: commodities and currencies prices

    Slide 9: Macroeconomic environment: commodities and currencies prices

    Macroeconomic environment Commodities and currencies prices Copper prices reached a historic daily fixing maximum on 10 Cena Price(USD/t) (USD/t) Avg. Śr. ann. (USD/t) roczna (USD/t) [PLN/t] May of 10 724.5 USD/t. The average copper price amouted to [USD/t] Cena Price(PLN/t) (PLN/t) Avg. Śr. ann. (P

  10. Slide 10: Precious metals prices in H1 2021

    Slide 10: Precious metals prices in H1 2021

    Precious metals prices in H1 2021 The first half of 2021 was a calm time for these metals compared to the price volatility of 2020 Silver in H1 2021 remained stably above 25 USD/koz t After the volatility of 2020 the gold/silver ratio fell below the long term average Srebro Silver(USD/troz) (USD/koz

  11. Slide 11: Copper prices more than double that of the minimum in spring 2020

    Slide 11: Copper prices more than double that of the minimum in spring 2020

    Copper prices more than double that of the minimum in spring 2020 Commodities price index already 25% higher than prior to the pandemic Over the course of 12 months the copper price rose The industrial metals price index has risen by more than by 126% and reached a historic maximum on 10 May 50% sin

  12. Slide 12: Higher economic activity in H1 2021 especially in the eurozone

    Slide 12: Higher economic activity in H1 2021 especially in the eurozone

    Higher economic activity in H1 2021 especially in the eurozone Industrial PMI in the USA and Europe rose above 60. Average Industrial PMI in the eurozone was 63.4. In China meanwhile forward indicators fell slightly in June. Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-1

  13. Slide 13: Economic growth forecast of the IMF from July 2021

    Slide 13: Economic growth forecast of the IMF from July 2021

    Economic growth forecast of the IMF from July 2021 Eurozone Poland Canada 2020: -2.7% 2020: -5.3% 2020: -6.5% 2021F: 4.6%  +0.2 p.p. 2021F: 4.6%  +1.1 p.p. 2021F: 6.3%  +1.3 p.p. 2022F: 5.2%  +0.7 p.p. 2022F: 4.5%  -0.2 p.p. 2022F: 4.3%  +0.5 p.p. World 2020: -3.2% 2021F: 6.0%  0.0 p.p. 2022F

  14. Slide 14: Payable copper production by the KGHM Group

    Slide 14: Payable copper production by the KGHM Group

    Key production indicators H1 2021 381 Payable copper production +8.6% H/H by the KGHM Group [kt] higher by 8.6% (h/h) Payable copper production Payable copper production +31% H/H  KGHM Polska Miedź: KGHM Polska Miedź [kt] Sierra Gorda1) [kt] higher production from +4.4% H/H 39 51 293 28 purchased c

  15. Slide 15: Key financial indicators

    Slide 15: Key financial indicators

    Key financial indicators H1 2021 Doubled adjusted EBITDA Group adjusted EBITDA2) Group revenues [mn PLN] +32% H/H [mn PLN] for the KGHM Group +100% H/H compared to H1 2020 5 313 14 506 10 948 Higher adjusted EBITDA compared to H1 2020 7 761 5 649 (+PLN 2 662 mn; +100%), of which by segment:  KGHM P

  16. Slide 16: The production of miners in H1 2021

    Slide 16: The production of miners in H1 2021

    The production of miners in H1 2021 Copper production by miners, Q2 2021 vs Q2 2020 30% 20% 10% -3% -3% -7% -13% -13% 0% -10% 22% 19% 10% 7% 5% 2% 1% -20% Teck Freeport Grupa KGHM Codelco KGHM Polska Anglo Glencore Antofagasta BHP Southern Rio Tinto Vale McMoran Miedź S.A. American Copper Copper pro

  17. Slide 17: The financial situation of the KGHM Group remains stable and safe

    Slide 17: The financial situation of the KGHM Group remains stable and safe

    The financial situation of the KGHM Group remains stable and safe 2021 Budget Total unit production cost of electrolytic copper from own concentrate KGHM Polska Miedź S.A.1) 20.2 [k PLN/t] 19.2 Investments Capital expenditures 1 036 2 853 of KGHM Polska Miedź S.A.2) [mn PLN] Other expenditures, incl

  18. Slide 18: Group production and sales in H1 2021

    Slide 18: Group production and sales in H1 2021

    Group production and sales in H1 2021 Execution of annual targets 2021 Budget Production Copper in concentrate [kt] 195.1 390.0 KGHM Polska Miedź S.A. Silver in concentrate [t] 640 1 200 Electrolytic copper, total [kt] 293.2 573.0 Electrolytic copper from own concentrate [kt] 192.2 385.0 Metallic si

  19. Slide 19: Production results of the KGHM Group by segment

    Slide 19: Production results of the KGHM Group by segment

    Production results of the KGHM Group by segment

  20. Slide 20: Metals production

    Slide 20: Metals production

    Metals production KGHM Group Payable copper production Silver production [t]  Higher production: [kt] -5% H/H − by KGHM Polska Miedź due to higher 708 676 +8.6% H/H production from purchased copper-bearing materials H1 2020 H1 2021 − by KGHM INTERNATIONAL due mainly to higher production by the Robi

  21. Slide 21: Production results: KGHM Polska Miedź

    Slide 21: Production results: KGHM Polska Miedź

    Production results KGHM Polska Miedź S.A. Ore extraction +1.4% H/H Production of copper –1.9% H/H Electrolytic copper +4.4% H/H Metallic silver -5.1% H/H [mn t dry weight] in concentrate [kt] production [kt] production [t] 281 293 14.8 15.0 199 195 101 75 49.5 49.3 From 695 659 purchased Ag grade me

  22. Slide 22: Production results: Sierra Gorda

    Slide 22: Production results: Sierra Gorda

    Production results Sierra Gorda1) Payable copper production +30% H/H Silver production +25% H/H [kt] [t] 15.6 12.5 6.8 7.7 51.2  Higher silver production in H1 2021 versus H1 2020 39.2 Q2 2020 Q2 2021 H1 2020 H1 2021 due to higher silver 28.3 content in mined ore TPM production -12% H/H 20.2 [koz t

  23. Slide 23: Production results: KGHM INTERNATIONAL

    Slide 23: Production results: KGHM INTERNATIONAL

    Production results KGHM INTERNATIONAL Payable copper production +18% H/H Silver production +51% H/H [kt] [t] 1.18 0.57 0.78 0.31  Higher silver production by 36.3 the Sudbury Basin due to 30.7 higher silver content in ore Q2 2020 Q2 2021 H1 2020 H1 2021  Higher gold production by 20.1 the Robinson

  24. Slide 24: Financial results of the Group

    Slide 24: Financial results of the Group

    Financial results of the Group

  25. Slide 25: Group sales revenue

    Slide 25: Group sales revenue

    Group sales revenue H1 2021 Revenues from contracts with customers +32% H/H Revenues from contracts with [mn PLN] customers [mn PLN] +5 437 14 506 +104 +32% H/H 10 948 -561 14 506 -1 034 955 10 948 1 407 -388 782 1 269 12 144 Revenues for Change in sales Change in prices Change in Adjustment of Othe

  26. Slide 26: C1 unit cost

    Slide 26: C1 unit cost

    C1 unit cost1) KGHM Group C1 – KGHM Polska Miedź S.A. C1 – Group [USD/lb] [USD/lb] incl. the +33% H/H 2.12 minerals extraction  The increase in C1 cost in KGHM Polska Miedź by 33% versus H1 2020 was mainly tax 1.59 +18% H/H 0.38 1.02 due to an increase in the minerals 1.21 1.10 extraction tax charg

  27. Slide 27: Operating results

    Slide 27: Operating results

    Operating results KGHM Group Change in adjusted EBITDA1) Adjusted EBITDA [mn PLN] [mn PLN] +100% H/H 5 313 +1 050 +15 5 313 145 +1 226 +371 1 478 2 651 533 2 651 130 428 H1 2020 KGHM Polska KGHM Sierra Other H1 2021 162 Miedź S.A. INTERNATIONAL Gorda 3 157 1 931 Higher adjusted EBITDA versus H1 2020

  28. Slide 28: Financial results

    Slide 28: Financial results

    Financial results KGHM Group 3 723 Profit for the period +433% H/H consolidated net profit for H1 2021 [mn PLN] Higher Group profit by PLN 3 024 million (5.3-times) mainly due to an improved net result on sales with a higher CIT [million PLN] Higher net result on sales by PLN 1 666 mln +3 558 +1 866

  29. Slide 29: Cash flow

    Slide 29: Cash flow

    Cash flow KGHM Group [mn PLN] +4 629 - 390 - 212 -1 710 2 522 -1 663 1 268 -1 526 - 64 - 300 - 18 Cash as at Profit/loss before Exclusion of Income tax Change in Acquisition of Proceeds Interest paid Dividend Other Cash as at 01-01-2021 income tax income and costs paid working capital property, plan

  30. Slide 30: Net debt of the KGHM Group

    Slide 30: Net debt of the KGHM Group

    Net debt of the KGHM Group As at the end of Q2 2021 Main factors affecting net debt in the first half Net debt / adjusted EBITDA -56% of 2021 compared to 30 June 2020 1.6 1.4 0.9 Increases in debt 0.8 0.7  Cash expenditures on property, plant and equipment 30-06-2020 30-09-2020 31-12-2020 31-03-202

  31. Slide 31: Advancement of development initiatives

    Slide 31: Advancement of development initiatives

    Advancement of development initiatives

  32. Slide 32: A rationale and responsible investment program

    Slide 32: A rationale and responsible investment program

    A rationale and responsible investment program Capital expenditures by KGHM Polska Miedź S.A. in H1 2021 CAPEX execution in H1 2021 by area by category Mining Replacement Metallurgy Maintaining mine production Other activities Development Leasing IFRS 16 Development - uncompleted 1036 29% 726 *excl.

  33. Slide 33: Role of Deep Głogów (GGP) in maintaining output in Poland

    Slide 33: Role of Deep Głogów (GGP) in maintaining output in Poland

    Role of Deep Głogów (GGP) in maintaining output in Poland Deposit access program in KGHM’s concessioned areas Share of production from GGP in total production Active concessions and in Poland future potential Ore extraction dry weight from GGP [kt] +5% Q2/Q1 +43% H/H 982 1 030 2 012 1 410 13.2% 13.7

  34. Slide 34: CAPEX execution in key projects

    Slide 34: CAPEX execution in key projects

    CAPEX execution in key projects Replacement of Other Outfitting of the machine park in mines; incl. the Other mines Construction of Deposit Access Program (18%) SW-4 shaft Deposit Deposit Access exploration & Tailings Division: Program Maintaining Damówka assessment modernisation of Other pumphouse

  35. Slide 35: Energy Development Program, including RES

    Slide 35: Energy Development Program, including RES

    Energy Development Program, including RES Actions in 2021 Development of renewable Energy sources Optimisation and development of conventional sources  Further permits are in the process of being obtained and design work is underway on  In 2020 two gas-fired turbines at the gas- the Obora Sandpit

  36. Slide 36: By 2030 the increase in share of RES will lead to a substantial reduction in CO2 emissions

    Slide 36: By 2030 the increase in share of RES will lead to a substantial reduction in CO2 emissions

    By 2030 the increase in share of RES will lead to a substantial reduction in CO2 emissions Share of power source in supplies to KGHM Polska Miedź S.A. 2019: 2020: 2019 Own generation sources covered 22.42% of KGHM’s 3 TWh total power needs in 2020 Natural Market Own source Gas (almost 1.5% more than

  37. Slide 37: The first photovoltaic power plants

    Slide 37: The first photovoltaic power plants

    The first photovoltaic power plants projects PVPP Piaskownia Obora Installed power 8 MW Projected avoided emissions Estimated production 8.5 GWh over 25 years:  CO2 more than 80 kt  SOx more than 70 tonnes  NOx more than 70 tonnes  CO more than 30 tonnes  PM more than 4 tonnes PVPP HMG I-III co

  38. Slide 38: Key elements of the Strategy advanced in H1 2021

    Slide 38: Key elements of the Strategy advanced in H1 2021

    Key elements of the Strategy advanced in H1 2021  Stable copper production from domestic assets (mined  Enhanced Energy efficiency production 220.9 kt; metallurgical production 293.2 kt) Production Efficient  Continuation of digital transformation under the  Stable copper production from interna

  39. Slide 39: Supporting slides

    Slide 39: Supporting slides

    Supporting slides KGHM Polska Miedź S.A. 40

  40. Slide 40: Sales revenue

    Slide 40: Sales revenue

    Sales revenue KGHM Polska Miedź S.A. Revenues from contracts with customers Higher revenues from contracts with customers [mn PLN] by PLN 3 248 million (+37%) in H1 2021 compared to +37% H/H H1 2020 mainly due to higher metals prices (copper +65%, 12 144 silver +59%) 740 8 897 1 996 Other 830 Sales

  41. Slide 41: Expenses by nature

    Slide 41: Expenses by nature

    Expenses by nature KGHM Polska Miedź S.A. Expenses by nature Expenses by nature higher by PLN 3 529 million, [mn PLN] H/H 10 678 +49% H/H Minerals extraction tax Minerals 1 635 recognised in expenses 5 724 extraction by nature tax recognised 4 954 in expenses by 7 149 nature 3 656 Purchased 4 296 67

  42. Slide 42: EBITDA and profit for the period

    Slide 42: EBITDA and profit for the period

    EBITDA and profit for the period KGHM Polska Miedź S.A. Adjusted EBITDA Profit for the period [mn PLN] [mn PLN] Higher EBITDA, +63% H/H +466% H/H higher net profit 3 157 4 226  EBITDA higher by 63% 1 931 versus H1 2020  Higher net profit by PLN 3 479 mn 747 (+466%) than in H1 2020 mainly due to mo

  43. Slide 43: Profit for the period

    Slide 43: Profit for the period

    Profit for the period KGHM Polska Miedź S.A. Profit for the period [mn PLN] +466% H/H +588 +103 4 226 +3 247 +947 -458 +1 141 -2 089 747 Profit for the Increase in revenues Increase in cost of sales, Impairment losses Fair value gains/(losses) Impairment losses Other Increase in income tax Profit fo

  44. Slide 44: Market risk management: copper hedged position

    Slide 44: Market risk management: copper hedged position

    Market risk management Hedged position on the copper market (as at 30 June 2021) Copper Hedged position – open as at 31 Dec 2020 In the first half of 2021 the Parent Entity Hedged position implemented in H1 2021 [kt] recorded a result on derivatives* and hedges in the amount of -PLN 936 million: 69

  45. Slide 45: Market risk management: currency, silver and interest rate

    Slide 45: Market risk management: currency, silver and interest rate

    Market risk management Hedged positions on the currency, silver and interest rate markets (as at 30 June 2021) USD/PLN Hedged position – open as at 31 December 2020 In the first half of 2021 transactions were [mn USD] Hedged position implemented in H1 2021 implemented on the forward currency market:

  46. Slide 46: Revenues and EBITDA in Q2 2021

    Slide 46: Revenues and EBITDA in Q2 2021

    Revenues and EBITDA in Q2 2021 KGHM Group Higher EBITDA of the KGHM Revenues from contracts with Adjusted EBITDA customers [mn PLN] Group by PLN 1 183 mn (Q/Q) [mn PLN] mainly due to more favourable +37% Q2/Q2 +78% Q2/Q2 metals prices, broken down by 2 705 segment as follows: 7 761 93 529 657 835 5

  47. Slide 47: Investor Relations Department

    Slide 47: Investor Relations Department

    Investor Relations Department https://kghm.com/en/investors ir@kghm.com | esg@kghm.com T +48 76 74 78 280 | F +48 76 74 78 205