PT ANTAM (Persero) Tbk · IDX:ANTM
PT ANTAM (Persero) Tbk — Investor Day (October 2013)
28 slides from PT ANTAM (Persero) Tbk's investor day presentation, Oct 4, 2013
Slide 1: Indonesia Corporate Day / Indonesia Investment Day
PT ANTAM (Persero) Tbk Indonesia Corporate Day Indonesia Investment Day Corporate Presentation London-New York, 30 September-4 October 2013
Slide 2: Who We Are
Who We Are • 4th Largest Nickel 1H13 Revenue Breakdown: Rp6.125 trillion Producer in the World Coal 1% Ferronickel • Diversified & 18% Gold, Silver & Precious Vertically Metals Services Integrated: Nickel, Nickel Ore 49% Gold, Alumina, Bauxite 32% and Coal • Vast, High Quality Reserves & Resources
Slide 3: Operations Areas and Key Associates
Operations Areas and Key Associates 2 Additional Key Assets in 2012: Sponge Iron Project and additional 7.5% stake at Gosowong, resulting in 25% ownership GOLD Gosowong, North BAUXITE Maluku (PT NHM) Tayan, West Kalimantan SPONGE IRON NICKEL SMELTER Tanjung Buli & Pakal COAL Batulicin, South Island,
Slide 4: Exploration Areas and Joint Ventures
Exploration Areas and Joint Ventures ZINC PT Dairi Prima Minerals BAUXITE Tayan, Landak, Munggu GOLD Pasir, Meliau and PT Gorontalo Minerals NICKEL Mempawah, West GOLD Tanjung Buli, North Kalimantan PT Sorikmas Mining Maluku NICKEL GOLD Gag Island, Papua COAL Jambi Jambi NICKEL Pomalaa, Southeast GO
Slide 5: Our Key Issues
Our Key Issues 1. Mineral and Coal Mining Law (UU Minerba) 2. Lower Commodity Prices 3. Key Projects and Cost Programs
Slide 6: UU Minerba: Ban on Ore Export Implemented in 2014?
UU Minerba: Ban on Ore Export Implemented in 2014 ? Indonesia Mineral Mining Value Chain Based on UU Minerba Raw Processing & Additional Processed Mining materials Minerals Refining Processing Foreign Domestic Foreign Domestic consumption consumption consumption consumption Ban on ore export will in
Slide 7: UU Minerba: Vertical Integration of Nickel
UU Minerba: Vertical Integration of Nickel Value Added Diagram of Nickel Processing Domestic Industry Strength End Use Stainless Stainless Stainless Stainless Household Steel Steel Steel Steel Slab HRC CRC Sheet Ni Fe- Ship Calcine Nickel Construct- Stainless Stainless ion Steel Billet Steel Ni Rod/
Slide 8: Stainless Steel Growth Driven Predominantly by China
Stainless Steel Growth Driven Predominantly by China 7 Source: Glencore
Slide 9: Excess Nickel Supply Yielded Market Surpluses
Excess Nickel Supply Yielded Market Surpluses 8 Source: Glencore
Slide 10: Our Action Plans
Our Action Plans 1. Review and Negotiate Existing Contracts with Key Suppliers 2. Expedite the Construction of Key Projects 3. Optimum Financing and Shareholding Structure to Strengthen the Balance Sheet
Slide 11: Review and Negotiate Existing Contracts with Key Suppliers
Efficiency Measures 1. Review and Negotiate Existing Contracts with Key Suppliers 2. Lower operating cost of power plants following commissioning of additional 2x17MW Wartsila engines at the end of May 2013 3. Expected lower ferronickel cash cost following the operations of 2x30 MW CFPP in 2015 4. R
Slide 12: Business Development Road Map
Business Development Road Map Mining Processing and End Results Refinery • Pomalaa Nickel • Pomalaa • Ferronickel • Tanjung Buli & Ore • East Halmahera FeNi • NPI Pakal Island • NPI • Tapunopaka Gold • Pongkor Logam Mulia Processing • Gold bullions Ore and Refinery Business • Manufacturing Goods • C
Slide 13: Tayan Chemical Grade Alumina Project (1)
Status of Key Projects – Tayan Chemical Grade Alumina Project (1) Tayan Summary Project Cost: Production Capacity: Offtake sales in domestic US$490 million 300Ktpa market and to Japan Commissioning in October 2013—3 months ahead of schedule 97% Overall EPC Progress 12
Slide 14: Tayan Chemical Grade Alumina Project (2)
Status of Key Projects – Tayan Chemical Grade Alumina Project (2) Alumina Site 13
Slide 15: Tayan Chemical Grade Alumina Project (3)
Status of Key Projects – Tayan Chemical Grade Alumina Project (3) Alumina Site 14
Slide 16: Tayan Chemical Grade Alumina Project (4)
Status of Key Projects – Tayan Chemical Grade Alumina Project (4) Jetty 15
Slide 17: Pomalaa Ferronickel Plant Expansion Project (P3FP) (1)
Status of Key Projects – Pomalaa Ferronickel Plant Expansion Project (P3FP) (1) P3FP Summary Project cost: US$573 million Increase in the capacity and efficiency level of the Pomalaa Ferronickel Plant Construction of coal fired power plant to lower cash cost 16
Slide 18: Pomalaa Ferronickel Plant Expansion Project (P3FP) (2)
Status of Key Projects – Pomalaa Ferronickel Plant Expansion Project (P3FP) (2) Package Capex Commissioning (US$ M) Estimate Package 1: Jetty & Facilities 36.5 3Q13 Package 2: Belt Conveyor Package 3: Refining-3 Plant 14.3 37.8 3Q13 1Q14 22.1% Package 4: Ladle Furnace Package 5: Line-4 Ore Prep. 12.
Slide 19: Pomalaa Ferronickel Plant Expansion Project (P3FP) (3)
Status of Key Projects – Pomalaa Ferronickel Plant Expansion Project (P3FP) (3) Ladle Furnace Belt Conveyor New Export Warehouse 18
Slide 20: East Halmahera Ferronickel Project (1)
Status of Key Projects – East Halmahera Ferronickel Project (1) FHT Currently focusing on pre- Summary construction works: land preparation; office and Project cost: US$1.6 billion workshop relocation; and port construction Commissioning in 2015 Focus on procurement process Production capacity: 27,0
Slide 21: East Halmahera Ferronickel Project (2)
Status of Key Projects – East Halmahera Ferronickel Project (2) Area Conditioned Ore & Dryer Area Calcining, ESF, & Refining Conditioned Ore & Dryer Calcining, ESF & Refining Elv.R , ±20m Elv.R ±20m Elv.R , ±10 m Elv.R, ±15m Elv.R , ±15m Calcining, ESF & Refining Elv.R , ±20m Elv. R, ±10m Land Clear
Slide 22: Mempawah SGA Project and Nickel Pig Iron (NPI) Project
Status of Key Projects– Mempawah Smelter Grade Alumina (SGA) Project and Nickel Pig Iron (NPI) Project Mempawah SGA Project NPI Project Project Bauxite processing to smelter Project Nickel ore processing to nickel Description grade alumina Description pig iron (NPI) 1.2 million metric ton of SGA Cap
Slide 23: Weda Bay Project and Sorikmas Mining Project
Status of Key Projects – Weda Bay Project and Sorikmas Mining Project Weda Bay Nickel Project Sorikmas Mining Project Nickel ore processing to nickel and Project Gold mine Description cobalt Description 65,000 TNi and 4,000 ton of cobalt Capacity 90,000 oz p.a. Capacity p.a. Operation Production in
Slide 24: Our Key Initiatives
Our Key Initiatives A prudent financial strategy to achieve a solid balance sheet Sufficient liquidity to strengthen the company’s cash position Intensify efficiency programs Maximise cash flows through increased sales of nickel ore export as well as gold sales. Remain prudent in terms of our capita
Slide 25: Thank You
antam Thank You
Slide 26: Disclaimer
This presentation and/or other documents have been written and presented by Antam. The materials and information in the presentations and other documents are for informational purposes only, and are not an offer or solicitation for the purchase or sale of any securities or financial instruments or t
Slide 27: 1H13 Operational Performance
1H13 Operational Performance 1H13/ % of 2013 Commodity 1H12 1H13 2013 Target 1H12 target PRODUCTION Ferronickel (TNi) 8,009 10,166 18,000 27 56 Nickel Ore (wmt) 4,041,119 6,073,964 11,569,000 50 52 Gold (kg) 1,261 1,268 2,801 0.6 45 Silver (kg) 9,929 8,959 19,869 (10) 45 Bauxite (wmt) 62,301 83,568
Slide 28: 1H13 Financial Highlights
1H13 Financial Highlights 1H12 1H13 Description ∆% (Rp billion) (Rp billion) Net Sales 4,492 6,126 36 Cost of Goods Sold 3,620 5,174 43 Gross Profit 872 951 9 Operating Expenses 470 567 21 Operating Income 402 384 (4) Income for the Year Attributable to Owners of 476 374 (21) the Parent Cash & Cash