Aurelia Metals Limited · ASX:AMI

Aurelia Metals — Investor Presentation (December 2022)

9 slides from Aurelia Metals's investor presentation, Dec 19, 2022

  1. Slide 1: Hera Life of Mine Update

    HERA LIFE OF MINE UPDATE 19 December 2022 ASX Code: AMI

  2. Slide 2: Forward Looking Statements

    2 FORWARD LOOKING STATEMENTS HERA | LIFE OF MINE UPDATE This presentation has been prepared by Aurelia Metals Limited (“AMI” or the By its very nature, production and exploration for gold and base metals is a high “Company”). It should not be considered as an offer or invitation to subscribe for ris

  3. Slide 3: Organisational Renewal Program

    3 ORGANISATIONAL RENEWAL PROGRAM HERA | LIFE OF MINE UPDATE Considered and decisive steps to restore and unlock shareholder value Safety Hera Life of Mine Operational Delivery and FIVE-POINT PROGRAM Cash Management Federation Optimisation Guidance Update Federation Funding 19 DECEMBER 2022 Leadershi

  4. Slide 4: Trigger

    4 HERA LIFE OF MINE - TRIGGER HERA | LIFE OF MINE UPDATE Every operating asset must generate positive cash flow • Operational and financial performance has failed to meet internal targets in recent quarters • Mining conditions have become increasingly difficult and constrained ore production:  Dete

  5. Slide 5: Action

    5 HERA LIFE OF MINE - ACTION HERA | LIFE OF MINE UPDATE Rigorous optimisation to deliver the best available plan • Higher development rates provided access to additional stoping areas in Main South and Hays Upper • Detailed interrogation of mining areas to determine a possible stoping inventory • St

  6. Slide 6: Response

    6 HERA LIFE OF MINE - RESPONSE HERA | LIFE OF MINE UPDATE Improved cash outcome but over a shorter mine life • Updated plan yields positive cumulative cash flow from December  ~140kt of ore mined and processed from December 2022 to March 2023  No development mining after December – greater relianc

  7. Slide 7: Federation Optimisation

    7 FEDERATION OPTIMISATION HERA | LIFE OF MINE UPDATE Hera outcome allows Aurelia to further optimise Federation • Hera infrastructure remains a valuable suite of assets in the Aurelia portfolio • Ability to leverage the substantial installed infrastructure for the development of the Federation, incl

  8. Slide 8: Updated FY23 Guidance

    8 UPDATED FY23 GUIDANCE HERA | LIFE OF MINE UPDATE Hera mine plan change necessitates an update to guidance Metal New FY23e Changes reflect: Metric Previous FY23e production (with early Hera finish) • planned cessation of mining at Hera in March 2023 Copper kt 2.3 2.5 impacting gold, zinc and lead p

  9. Slide 9: Contact

    CONTACT T: +61 7 3180 5000 E: office@aureliametals.com.au Level 17, 144 Edward Street BRISBANE QLD 4000 GPO Box 7 BRISBANE QLD 4001 aureliametals.com.au

Aurelia Metals — Investor Presentation (December 2022) on 6ix