Galan Lithium Limited · ASX:GLN

Galan Lithium — Investor Presentation (October 2023)

15 slides from Galan Lithium's investor presentation, October 2023

  1. Slide 1: Accelerated Production for Galan's High-Grade Lithium Brine Projects in Argentina

    ACCELERATED PRODUCTION FOR GALAN’S HIGH-GRADE LITHIUM BRINE PROJECTS IN ARGENTINA PHASE 1 – CONSTRUCTION UNDERWAY October 2023 ASX:GLN | FSX:9CH galanlithium.com.au 1

  2. Slide 2: Disclaimers & Important Information

    Disclaimers & Important Information This presentation has been prepared by Galan Lithium Limited. Competent Persons The information contained herein that relates to exploration results and geology is based on information compiled or reviewed by Dr Luke Milan, who has consulted to the Company. Dr Mil

  3. Slide 3: The Highest Grade, Lowest Impurity Lithium project in Argentina

    The Highest Grade, Lowest Impurity Lithium project in Argentina Significant Resource World-class location supports production target of 60ktpa LCE by 2030 Low risk and rapid project Strong local community and delivery government support • Phase l (5.4ktpa) works have commenced Highly experienced tea

  4. Slide 4: Corporate Snapshot

    Corporate Snapshot Strong cash liquidity, tight share register Market Capitalisation Share Price (30 October 2023) Major Shareholders A$226m A$0.64 A$/share Shares on Issue 2.5 2.3 353.2m 2.1 1.9 Cash/Investments 1.7 1.5 A$33m 1.3 1.1 Directors & Top 20 Unquoted Securities 0.9 Management Shareholder

  5. Slide 5: World-Class Location

    World-Class Location Highly strategic positioning 25+ year history of production within salar Significant regional infrastructure and investment with excellent government and community support Highest grade, lowest impurity lithium brine assets in Argentina 7.3Mt total resource @ 852 mg/l Li Staged

  6. Slide 6: Recent Highlights

    Recent Highlights Phase 1 and 2 DFS Delivered and Full Construction Permits Granted, Construction is underway (6) Phase 2 DFS announced 3 October 2023 ; compelling economics for 20.9ktpa LCE production Full Phase 1 (5.4ktpa LCE production) construction permits granted (1), construction is underway P

  7. Slide 7: Construction Permits Granted – Works Commenced

    Construction Permits Granted – Works Commenced Full Phase 1 HMW construction permits granted * Phase 1 preparation works commenced with engineering and long lead on track for delivering lithium chloride production of 5.4ktpa LCE in H1, 2025 Permits include ponds, plant, onsite laboratory, 200- man c

  8. Slide 8: Compelling Economics

    Compelling Economics Phase 2 DFS Economic Outcomes Released (3 October 2023) Flagship HMW Project 100% ownership Proven processing route Cost Analysis - Lithium Carbonate Equivalent Cost Curve Year 2025 Production of 21 ktpa LCE 16,000 14,000 #REF! #REF! All-In Sustaining Cost (US$/t LCE) 12,000 +40

  9. Slide 9: Low Risk – Staged, Flexible Production Plan

    Low Risk – Staged, Flexible Production Plan Fast track route to Li production Targeting first-phase HMW Li concentrate production in H1 2025 Phase 1 – >5ktpa LCE Phase 2 – 20ktpa LCE Phase 3 – 40ktpa LCE Phase 4 – 60ktpa LCE DFS delivered and full DFS delivered 3 October ’23 Evaluating stage (permit

  10. Slide 10: ESG Update Q2 2023

    Galan Lithium ASX:GLN ESG Focus Areas ESG UPDATE Q2 2023 Highlights and achievements Q2: ● Commenced ESG reporting against the World Economic Forum’s framework of 21 metrics ● Relevant personnel, local communities and agencies were engaged and consulted during the Phase 1 EIA and permitting process.

  11. Slide 11: Highly Experienced Team

    Highly Experienced Team With a proven track record Richard Homsany JP Vargas de la Vega Daniel Jimenez Terry Gardiner Claudia Pohl Non-Executive Chairman Founder & Managing Director Non-Executive Director Non-Executive Director Non-Executive Director • Experienced corporate lawyer • Chilean/Australi

  12. Slide 12: Highly Experienced Team

    Highly Experienced Team A strong and talented group of professionals with world class knowledge and extensive local experience Juan Carlos Barerra Boris Caro Alvaro Henriquez Francisco Lopez Pablo Sanz Project & Board Consultant Project Advisor/Director Group Geology Manager Exploration Manager Busi

  13. Slide 13: The Premier Lithium Developer

    The Premier Lithium Developer Strong local community and Strong local team, including ex The best Lithium project in Argentina government support, evidenced SQM team, experienced in (high grade, low impurities) – and the by recent grant of full Phase 1 Lithium project execution and funding, initial

  14. Slide 14: Further project pipeline: Greenbushes South Lithium Project

    Further project pipeline Hardrock lithium exploration upside Greenbushes South Lithium Project - 100% ownership • E70/4790 only 3km south of Greenbushes Lithium mine • Tenements intersect the Donnybrook- Bridgetown Shear Zone • Drilling complete at Galan’s Greenbushes South Lithium Project; assay re

  15. Slide 15: Contact

    Contact ACN 149 349 646 ASX : GLN | FSX : 9CH Juan Pablo (“JP”) Vargas de la Vega Managing Director Email: jp@galanlithium.com.au Tel: +61 8 9214 2150 Terry Gardiner Non-Executive Director Email: TGardiner@galanlithium.com.au Tel: + 61 400 900 377 Jane Morgan Investor and Media Relations Email: jm@j