Endeavour Mining Plc · TSX:EDV

Endeavour Mining — Technical Presentation (November 2024)

78 slides from Endeavour Mining's technical presentation, November 2024

  1. Slide 1: Lafigué Site Visit

    LAFIGUÉ SITE VISIT November 2024

  2. Slide 2: Disclaimer & Forward Looking Statements

    DISCLAIMER & FORWARD LOOKING STATEMENTS Some of the indicators used by Endeavour in this presentation represent non-IFRS financial expected, and the results of those studies being consistent with Endeavour’s current expectations; measures, including sustaining capital per ounce, non-sustaining capit

  3. Slide 3: Site Visit Itinerary

    SITE VISIT ITINERARY 09:30 Arrival at Lafigué 10:10 Introduction presentation 11:20 Lafigué Main Pit and West pit 12:20 TSF dam drive-by 12:30 Lunch 13:00 Processing plant 14:30 Exploration core display 16:30 Departures to Abidjan 3

  4. Slide 4: Contents

    CONTENTS LAFIGUÉ OVERVIEW 5 OUR PRESENCE IN CÔTE D’IVOIRE 19 PROJECT CONSTRUCTION 25 MINING 32 PROCESSING 38 INFRASTRUCTURE 47 EXPLORATION 53 ESG IMPACT 62 APPENDIX 73 4

  5. Slide 5: Lafigué Overview

    LAFIGUÉ OVERVIEW 1 5

  6. Slide 6: Site Overview

    LAFIGUÉ OVERVIEW SITE OVERVIEW Lafigué Village HME Garage Water Storage Dam Waste Management Facility TSF New Camp Main Pit Central Waste Dump West Pit 6

  7. Slide 7: Management Team

    LAFIGUÉ OVERVIEW MANAGEMENT TEAM Extensive experience operating in West Africa General Manager Finance Manager Exploration Director SVP Projects Paul Day Mirela Gheorghe Hermann N’Guessan Matt Berden Social Performance Mine Manager Exploration Director VP Projects Manager Adam Kouyaté N’faly Kanté P

  8. Slide 8: Asset Snapshot

    LAFIGUÉ OVERVIEW ASSET SNAPSHOT Endeavour’s 5th West African 90-110koz $900-$975/oz 2.7Moz 3.0Moz 2024 Guidance 2024 Guidance As at 31 Dec 2023 As at 31 Dec 2023 project build PRODUCTION AISC P&P RESERVES1 M&I RESOURCES1 The Lafigué mine is the fifth project Endeavour has built in West Africa in the

  9. Slide 9: Asset History

    LAFIGUÉ OVERVIEW ASSET HISTORY Discovery to production in less than 8 years EXPLORATION EXPLORATION 2015 2016 2017 2018 <$25/oz Exploration license Fetekro property ranked Mar 2017: Lafigué deposit Oct 2018: Maiden Indicated discovery costs acquired by Endeavour as greenfield exploration discovery f

  10. Slide 10: Lafigué Construction

    LAFIGUÉ OVERVIEW LAFIGUÉ CONSTRUCTION Delivered on budget and on time in less than 24 months INSIGHTS LAFIGUÉ PROJECT HIGHLIGHTS › The Lafigué PFS was completed in Mineral Reserve 49.8Mt at 1.69g/t for 2.7Moz February 2021 after which the exploration permit was converted Mineral Resource 46.2Mt at 2

  11. Slide 11: Lafigué Construction

    LAFIGUÉ OVERVIEW LAFIGUÉ CONSTRUCTION Greenfield project construction in less than 24 months Airstrip under construction Primary crusher and mill area before assembly July 2022 December 2022 Process plant assembly Primary crusher and mill area post assembly December 2023 June 2024 11

  12. Slide 12: Lafigué Ramp-Up

    LAFIGUÉ OVERVIEW LAFIGUÉ RAMP-UP Four-month ramp-up from first plant feed to nameplate capacity Mining ramp-up Expected Performance INSIGHTS Waste tonnes Ore tonnes Grade 16.0Mt › Construction of the CIL plant commenced in Q4- 3.5 2022 with first gold achieved on 28 June 2024, 21 15Mt 13.9Mt 14.1Mt

  13. Slide 13: West African Construction Track Record

    LAFIGUÉ OVERVIEW WEST AFRICAN CONSTRUCTION TRACK RECORD Endeavour’s third CIL plant construction in Côte d’Ivoire in the last ten years TRACK RECORD Delivered on-schedule in <24 months HOUNDÉ BIOX EXPANSION Delivered on or below 2014 2017 2019 2024 2024 budget Delivered at an industry- leading capit

  14. Slide 14: Mining Operations

    LAFIGUÉ OVERVIEW MINING OPERATIONS Contractor mining supports lower startup costs and fleet flexibility INSIGHTS › Open-pit shovel and truck operation, 95% drill & blast: mining operations contracted to Mota-Engil with an installed capacity of 55Mtpa; explosive supply contracted to MAXAM; grade cont

  15. Slide 15: Processing Operations

    LAFIGUÉ OVERVIEW PROCESSING OPERATIONS Processing plant expected to exceed design nameplate capacity INSIGHTS › 4.0Mtpa conventional CIL processing plant › Crushing by jaw crushers, two cone crushers and High Pressure Primary crusher Grinding Rolls (“HPGR”) followed by milling through a ball mill ›

  16. Slide 16: Tailings Storage Facility

    LAFIGUÉ OVERVIEW TAILINGS STORAGE FACILITY HDPE lined downstream tailings storage facility Stage 1 TSF raise › Total current capacity of 4.5Mt, of which 1.8Mt is expected to be utilised by 31 December 2024 › Stage 2 downstream lift ongoing which will expand capacity to 12.1Mt, expected TSF completio

  17. Slide 17: Exploration Overview

    LAFIGUÉ OVERVIEW EXPLORATION OVERVIEW Long-term potential to supplement existing endowment Exploration Strategy DISCOVERY TARGET 1.5-2.0 Moz $ 45/oz 1 Near-term Central Area (2021-2025) Indicated resources Discovery cost DISCOVERY TARGET Medium- 2 (2021-2025) term Indicated Target 1 resources Target

  18. Slide 18: Our ESG Highlights

    LAFIGUÉ OVERVIEW OUR ESG HIGHLIGHTS Being a trusted partner and delivering on ESG performance ENVIRONMENT HIGHLIGHTS SOCIAL HIGHLIGHTS GOVERNANCE HIGHLIGHTS › 40ha reforestation initiative with the YeS › Vocational and on-site mining skills training › 46-member Local Mining Development Foundation, i

  19. Slide 19: Our Presence in Côte d'Ivoire

    OUR PRESENCE IN CÔTE D’IVOIRE 2 19 19

  20. Slide 20: Côte d'Ivoire in Context

    OUR PRESENCE IN CÔTE D'IVOIRE CÔTE D'IVOIRE IN CONTEXT One of the fastest growing economies “We are increasing our commitment to Côte d’Ivoire as we look to advance our top tier Assafou project on the Tanda- Iguela property, which will cement our position as the largest gold producer, strengthening

  21. Slide 21: Natural Resources in Côte d'Ivoire

    SABODALA-MASSAWA MINE OUR PRESENCE IN CÔTE D'IVOIRE NATURAL RESOURCES IN CÔTE D'IVOIRE The largest exporter of cocoa beans accounting for 45% of global supply INSIGHTS Sissingue › Côte d’Ivoire's economy has traditionally focused on agriculture, but recent discoveries of natural resources Tongon are

  22. Slide 22: Gold Mining in Côte d'Ivoire

    OUR PRESENCE IN CÔTE D'IVOIRE GOLD MINING IN CÔTE D'IVOIRE Endeavour is the largest gold producer in Côte d’Ivoire INSIGHTS SISSINGUE Birimian greenstone belt › Endeavour holds a dominant position in country, operating Endeavour Asset the cornerstone Ity Mine, the new Lafigué mine and the TONGON End

  23. Slide 23: Alignment of Mining Conventions

    OUR PRESENCE IN CÔTE D'IVOIRE ALIGNMENT OF MINING CONVENTIONS Well-aligned mining conventions across West Africa CÔTE D’IVOIRE BURKINA FASO SENEGAL Low High Rate Low High Rate Government 0 1,000 3.00% 0 1,000 3.00% Royalty rate at 1,000 1,300 3.50% 1,000 1,300 4.00% US$/oz gold 1,300 1,600 4.00% 1,3

  24. Slide 24: Economic Contribution to Côte d'Ivoire

    OUR PRESENCE IN CÔTE D'IVOIRE ECONOMIC CONTRIBUTION TO CÔTE D’IVOIRE Delivering increasing benefits to Côte d’lvoire through organic growth YoY increase in economic INSIGHTS Total economic contribution contribution largely driven by spending on Lafigué project › Endeavour’s total economic contributi

  25. Slide 25: Project Construction

    PROJECT CONSTRUCTION 3 25 25

  26. Slide 26: Lafigué Site Layout

    LAFIGUÉ PROJECT CONSTRUCTION LAFIGUÉ SITE LAYOUT From discovery to production in less than eight years N Camp HME Main Pit West Pit CIL Plant Admin buildings Reagent Store Substation MSA TSF 26

  27. Slide 27: Project Construction Strategy

    LAFIGUÉ PROJECT CONSTRUCTION PROJECT CONSTRUCTION STRATEGY Delivered ahead of schedule and below budget › In-house projects construction team has a proven Key project risks Mitigation track record with 5 projects built in West Africa Cost escalation Commit early on critical items to lock in pricing

  28. Slide 28: Project Planning and Execution

    LAFIGUÉ PROJECT CONSTRUCTION PROJECT PLANNING AND EXECUTION Proven in-house projects team and long-standing partnerships Project partners Growth capex breakdown PFS – DFS bridge EPCM Contractor Civils Capital costs, US$M Capital costs, US$M Contractor Treatment Plant 75.9 HPGR Tank Reagents and Serv

  29. Slide 29: Definitive Feasibility Study Highlights

    LAFIGUÉ PROJECT CONSTRUCTION DEFINITIVE FEASIBILITY STUDY HIGHLIGHTS DFS defined an Endeavour type project Lafigué Project DFS highlights PLANT TYPE, SIZE & CAPEX 203Koz Plant type Gravity / CIL Mill capacity 4.0 Upfront capital cost, $m 448 RESERVES & RESOURCES (as at 31 December 2022) P&P Reserves

  30. Slide 30: Project Supply Chain

    LAFIGUÉ PROJECT CONSTRUCTION PROJECT SUPPLY CHAIN Leveraging platform in West Africa INSIGHTS Sissingue › Abidjan port to Lafigué is nearly 500km by road, which takes 2 days typically (wet season road conditions can cause delays) Assafou Lafigué › The Port of Abidjan handles 80% of commercial exchan

  31. Slide 31: Track Record of Delivering Above Nameplate

    LAFIGUÉ PROJECT CONSTRUCTION TRACK RECORD OF DELIVERING ABOVE NAMEPLATE Plant optimisations underway at Lafigué Realised plant throughput vs DFS Planned tonnes Actual tonnes Pre-leach tank commissioned CIL plant expansion 6.7Mt to 5Mtpa 6.2Mt 6.4Mt 5.0Mt 5.4Mt 5.0Mt 5.0Mt 5.0Mt + 24 % Ity 3.7Mt 3.0M

  32. Slide 32: Mining

    MINING 4 32 32

  33. Slide 33: Pit Sequencing and Grade Control Drilling

    PROJECT–BUILD MINING LAFIGUÉ – SABODALA-MASSAWA PIT SEQUENCING AND GRADE CONTROL DRILLING Increasing focus on grade control drilling Lafigué long-term mining sequence 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 P&P Reserves Main Pit: Pushback 1 5.9Mt @ 1.60g/t for 301koz Legend Main

  34. Slide 34: Pit Sequencing

    PROJECT–BUILD MINING LAFIGUÉ – SABODALA-MASSAWA PIT SEQUENCING 12 years of production visibility INSIGHTS 2024-2029 › Four distinct Main Pit pushbacks Main Pit pushback 2 over 12-year life-of-mine 2024-2025 › Three West Pit cutbacks from 2024 Main Pit pushback 1 to 2032 to support Main Pit and 2029-

  35. Slide 35: Mining Methods

    PROJECT–BUILD MINING LAFIGUÉ – SABODALA-MASSAWA MINING METHODS Mining fleet has capacity to move in excess of 50Mt per year INSIGHTS Haulage 100 tons 140 tons › Mining permit granted September 2021 5x 20x HD785-7 HD1500 › Conventional open pit mining using Komatsu hydraulic excavators and mechanical

  36. Slide 36: Mine Performance YTD-2024

    PROJECT–BUILD MINING LAFIGUÉ – SABODALA-MASSAWA MINE PERFORMANCE YTD-2024 Focus on increasing mining volumes following the wet season Material moved CIL operational Commercial production Total Ore (t) Total Waste (t) Wet commissioning May 2024 Achieved 1 August 2024 +27Mt 3.5Mt 3.4Mt 3.4Mt 3.0Mt 0.3

  37. Slide 37: Planned DFS Mine Performance

    PROJECT–BUILD MINING LAFIGUÉ – SABODALA-MASSAWA PLANNED DFS MINE PERFORMANCE Consistent mining volumes resulting support mill feed Material moved Medium and long-term exploration targets to Total Ore (t) Total Waste (t) supplement production from Y-7 onward ~8.9 54.9Mt 55.0Mt 55.1Mt 55.4Mt 52.5Mt 45

  38. Slide 38: Processing

    PROCESSING 5 38

  39. Slide 39: Processing Facility

    PROCESSING – LAFIGUÉ PROCESSING FACILITY Targeting outperformance vs 4.0Mtpa nameplate throughput INSIGHTS › Ore will be processed via a 4.0Mtpa CIL processing plant and utilizes high pressure grinding rolls in the grinding circuit › The LOM plant feed will consist of 7% oxide ore and 93% fresh ore,

  40. Slide 40: Processing Flowsheet

    PROCESSING – LAFIGUÉ PROCESSING FLOWSHEET High Pressure Secondary Crushed Ore Stockpile Grinding Rolls crushing Stockpile Primary crushing Gravity Ball mill Concentrator Cyanide leach and Tails thickening Tailings storage Pre-leach thickening absorption facility Elution Electrowinning Furnace Gold b

  41. Slide 41: Crushing and Grinding Circuits

    PROCESSING – LAFIGUÉ CRUSHING AND GRINDING CIRCUITS Utilising HPGR technology for cost effective crushing of fresh ore INSIGHTS High Pressure Grinding Rolls › Crushing circuit consists of primary jaw crusher and two secondary cone crushers › High pressure grinding rolls (HPGR) support crushing circu

  42. Slide 42: Site Optimisation Initiatives

    PROCESSING – LAFIGUÉ SITE OPTIMISATION INITATIVES Focus on increasing plant capacity and flexibility MOBILE CRUSHER STOCKPILE CONVEYER BELT UPGRADE › Additional mobile crusher acquired to supplement feed of high- › Motor on stockpile conveyer belt is being upgraded to allow for grade oxide ore into

  43. Slide 43: Gravity Circuit

    PROCESSING – LAFIGUÉ GRAVITY CIRCUIT Maximizing gold recovery Knelson gravity INSIGHTS concentrator › Circuit utilizes gravity concentrating split of cyclone underflow to recover free gold associated with high grade plant feed ahead of the CIL process › The gravity circuit has a design capacity of +

  44. Slide 44: Thickening and Leaching Circuits

    PROCESSING – LAFIGUÉ THICKENING AND LEACHING CIRCUITS Optimisation of reagent costs via tails thickening › Pre-leach thickener provides reclaim water to mill circuit › Tails thickener reclaims excess lime and cyanide to recirculate Thickeners within pre-leach circuit, optimising processing costs › C

  45. Slide 45: Elution and Gold Refining

    PROCESSING – LAFIGUÉ ELUTION AND GOLD REFINING Reduced LFO consumption through use of electric equipment › Split-elution circuit containing an induction furnace and electric carbon regeneration kiln, Gold Room reducing LFO consumption within plant design › Overall plant design includes primarily ele

  46. Slide 46: Planned DFS Processing Performance

    PROCESSING – LAFIGUÉ PLANNED DFS PROCESSING PERFORMANCE Consistent +200koz production Ore processed Total Ore (t) Grade 3.3Mt 4.0Mt 4.1Mt 4.0Mt 4.0Mt 4.0Mt 4.0Mt 4.0Mt 4.0Mt 4.0Mt 2.01g/t 1.64g/t 1.52g/t 2.05g/t 1.75g/t 1.85g/t 1.76g/t 1.80g/t 1.91g/t 1.81g/t 1.75g/t 4.0Mt 1.32g/t 3.9Mt 2.6Mt 0.44g/

  47. Slide 47: Infrastructure

    INFRASTRUCTURE 6 47

  48. Slide 48: Tailings Storage Facility

    INFRASTRUCTURE – LAFIGUÉ TAILINGS STORAGE FACILITY Stage 2 TSF embankment raise ongoing TSF design capacity 41.0 Mt › TSF is a downstream raise construction method with an HDPE liner; TSF design is Stage 2 capacity in compliance with the Global Industry Standard on Tailings Management 12.0Mt (“GISTM

  49. Slide 49: Power Generation

    INFRASTRUCTURE – LAFIGUÉ POWER GENERATION Grid power supplemented by backup power station 225kV POWER LINE POWER STATION › 32km overhead power line from the Dabakala post › Backup diesel power consisting of 7 gensets, each 2000kVA › 11kV substation situated next to the process plant › Out of project

  50. Slide 50: Site Accommodation

    INFRASTRUCTURE – LAFIGUÉ SITE ACCOMODATION Camp accommodates +300 employees Accommodation Bar and canteen › Camp construction completed in May 2024, with capacity to host over 300 employees › Camp earthworks were Lafigué completed in 2022, in advance of DFS finalisation camp 50

  51. Slide 51: Water Harvest and Storage Facilities

    INFRASTRUCTURE – LAFIGUÉ WATER HARVEST AND STORAGE FACILITIES Infrastructure supports projects phase and operations Water harvest dam Water storage dam › Water harvest dam completed in July 2023 › Water storage dam completed in July › Water harvest dam has capacity of 2023, ahead of wet season, to s

  52. Slide 52: Site Access

    INFRASTRUCTURE – LAFIGUÉ SITE ACCESS Airstrip supports efficient movement of people and gold Airstrip – first flight Camp earthworks › On-site airstrip operational from May 2023 › Airstrip and camp earthworks started in to support construction, providing access H2-2022 ahead of construction to Abidj

  53. Slide 53: Exploration

    EXPLORATION 7 53

  54. Slide 54: Exploration Overview

    EXPLORATION – LAFIGUÉ EXPLORATION OVERVIEW Long-term potential to grow endowment Exploration Strategy DISCOVERY TARGET 1.5-2.0 Moz 45/oz $ 1 Near-term Central Area (2021-2025) Indicated resources Discovery cost DISCOVERY TARGET Medium- 2 (2021-2025) term Indicated Target 1 resources Target 4-12 Unde

  55. Slide 55: Discovery Track Record

    EXPLORATION – LAFIGUÉ DISCOVERY TRACK RECORD Substantial increase in M&I resource M&I resource1 additions M&I Resource (Mt) M&I grade (g/t) 2.9Moz 3.0Moz 3.0Moz +150% 2.5Moz M&I increase 2.54g/t from 2019 2.40g/t 2.25g/t 2.04g/t 2.04g/t 2.02g/t 1.2Moz 0.5Moz 3.0Moz Measured & Indicated resource 2018

  56. Slide 56: Lafigué Near Mine Exploration

    EXPLORATION – LAFIGUÉ LAFIGUÉ NEAR MINE EXPLORATION Targeting deep mineralisation and improved resource definition INSIGHTS › Three deep holes, totalling 2,013 metres were drilled to test the near mine underground potential within a 400 metre radius of the Lafigué deposit › Results confirming a down

  57. Slide 57: Fetekro Property Exploration

    EXPLORATION – LAFIGUÉ FETEKRO PROPERTY EXPLORATION High priority targets within the Fetekro property Fetekro Exploration permit INSIGHTS › 2024 drilling focused on the Central area targets, as well as some exploration at the Corridor T4-12 target and Corridor Target 1 › Central Area remains a high-

  58. Slide 58: Lafigué North

    EXPLORATION – LAFIGUÉ LAFIGUÉ NORTH Lafigué main ore body 58

  59. Slide 59: Lafigué North

    EXPLORATION – LAFIGUÉ LAFIGUÉ NORTH Continuous mineralisation down dip of Lafigué main ore body 59

  60. Slide 60: Lafigué North

    EXPLORATION – LAFIGUÉ LAFIGUÉ NORTH Continuous mineralisation down dip of Lafigué main ore body 60

  61. Slide 61: Lafigué Deep

    EXPLORATION – LAFIGUÉ LAFIGUÉ DEEP Mineralisation extends below Lafigué pit shell 61

  62. Slide 62: ESG Impact

    ESG IMPACT 8 62

  63. Slide 63: Our ESG Highlights

    ESG IMPACT – LAFIGUÉ OUR ESG HIGHLIGHTS Being a trusted partner and delivering on ESG performance ENVIRONMENT HIGHLIGHTS SOCIAL HIGHLIGHTS GOVERNANCE HIGHLIGHTS › 40ha reforestation initiative with the YeS › Vocational and on-site mining skills training › 46-member Local Mining Development Foundatio

  64. Slide 64: Promoting Biodiversity at Lafigué

    ESG IMPACT – LAFIGUÉ PROMOTING BIODIVERSITY AT LAFIGUÉ 70,000 tree planting initiative with YeS Foundation and SODEFOR INSIGHTS › Following the success of the Krozialé forest reforestation at our Ity mine, in 2024 our Foundation’s partnership with the YeS Foundation and SODEFOR (the government fores

  65. Slide 65: Energy Sources - Côte d'Ivoire

    ESG IMPACT – LAFIGUÉ ENERGY SOURCES - CÔTE D’IVOIRE Increased focus on renewables INSIGHTS › H1-2024 grid power availability reduced in Côte d’Ivoire due to temporary breakdowns at two natural gas power plants in Côte d’Ivoire; Burkina Faso imports approximately a quarter of its grid capacity from C

  66. Slide 66: Community Engagement

    ESG IMPACT – LAFIGUÉ COMMUNITY ENGAGEMENT Proactive approach to developing social initiatives that benefit local stakeholders INSIGHTS Stakeholder engagement identified literacy and skills training as priority › We commenced our community and stakeholder initiatives. Since 2023, $1.5m has been inves

  67. Slide 67: Livelihood Restoration Plan – Rice Production

    ESG IMPACT – LAFIGUÉ LIVELIHOOD RESTORATION PLAN – RICE PRODUCTION Creating jobs and boosting the local economy through social investment INSIGHTS › Côte d'Ivoire is the 6th largest producer of rice in sub-Saharan Africa, producing 2.3 million tonnes in 2022. The Ivorian Government aims for rice sel

  68. Slide 68: Supporting Female Empowerment

    ESG IMPACT – LAFIGUÉ SUPPORTING FEMALE EMPOWERMENT Championing female employment and women’s rights ‘I CHOOSE MY FUTURE’ SUPPORTING FEMALE ENTREPRENEURS › Workshops led by health experts held to raise awareness about teenage › 72 women from 5 women's associations benefit from market gardening, pregn

  69. Slide 69: Our Workforce

    ESG IMPACT – LAFIGUÉ – LAFIGUÉ OUR WORKFORCE Strong commitment to growing local and diverse talent INSIGHTS WORK FORCE COMPOSITION1 › Training: Fostering a performance-orientated culture + 1,539 = 1,843 through regularly scheduled training courses and recruitment audits › Skills and experience trans

  70. Slide 70: N'Goto Yè Tè Hè Initiative

    ESG IMPACT – LAFIGUÉ – LAFIGUÉ N’GOTO YÈ TÈ HÈ INITIATIVE “Building for the future” in Djimini language INSIGHTS › To mitigate the impact of the demobilisation following the Lafigué construction, we established a dedicated initiative called N’Goto Yè Tè Hè, which means building for the future in the

  71. Slide 71: Boosting Employability in the Hambol Region

    ESG IMPACT – LAFIGUÉ BOOSTING EMPLOYABILITY IN THE HAMBOL REGION Employability and entrepreneurship programme at Lafigué INCREASING ADULT LITERACY VOCATIONAL TRAINING › Since 2022, 693 students including 280 women have learnt literacy and › Since 2023, local youths have been trained in boiler making

  72. Slide 72: Health and Safety

    ESG IMPACT – LAFIGUÉ HEALTH AND SAFETY Strong safety culture established at Lafigué LTIFR and hours worked INSIGHTS › During the construction of Lafigué, we had a LTM Hours worked (millions) 8.1M significant level of contractors working on site, which LTIFR (12 month trailing basis)1 7.6M required c

  73. Slide 73: Appendix

    APPENDIX 9 73

  74. Slide 74: Maintaining Best in Class Margins

    APPENDIX – LAFIGUÉ MAINTAINING BEST IN CLASS MARGINS Two thirds of costs incurred in West African CFA, pegged to the Euro All-in cost drivers Overview Outlook › Grid power currently costs approximately $0.15/kWh1, compared to self-generated › Lafigué is connected to the grid Power power at $0.31/kWh

  75. Slide 75: Quarterly Operating Data

    ESG – LAFIGUÉ APPENDIX – LAFIGUÉ QUARTERLY OPERATING DATA Q1 241 Q2 241 Q3 24 Operating Data Total tonnes mined - OP (kt) 8,832 9,296 8,873 Total ore tonnes - OP (kt) 816 1,024 1,250 Tonnes of waste mined - open pit (kt) 8,016 8,272 7,623 Open pit strip ratio (W:t ore) 9.82 8.08 6.10 Total tonnes mi

  76. Slide 76: Quarterly Financial Data

    ESG – LAFIGUÉ APPENDIX – LAFIGUÉ QUARTERLY FINANCIAL DATA Q1 241 Q2 241 Q3 24 All-in Costs Mining costs - OP - - 27.1 Processing and maintenance - - 10.9 Site G&A - - 4.1 Capitalized waste - - (11.8) Inventory adjustments and other - - (9.7) Non-cash operating costs - -- Operating expenses - - (20.6

  77. Slide 77: Executive Management Team

    EXECUTIVE MANAGEMENT TEAM Ian Cockerill Guy Young Djaria Traore Martin White Guénolé Pichevin CEO CFO EVP Operations & ESG EVP & Chief Technical EVP Strategy & Business • Joined in 2024 as CEO and in 2022 • Joined in 2023 • Joined Endeavour in 2019; Officer Development as a Director • 25+ years expe

  78. Slide 78: Contact Us

    CORPORATE OFFICE 5 Young Street, London W8 5EH, United Kingdom T: +44 203 011 2723 OPERATIONS OFFICE Abidjan Office, Route du Lycée Technique, Abidjan, 08 BP 872 Abidjan 08, Côte d’Ivoire T: +225 27 22 48 99 00 CONTACT US investor@endeavourmining.com Follow us: TSX.EDV endeavourmining.com LSE.EDV 78