K+s — K+S Aktiengesellschaft — Investor Day (November 2015)
12 slides from K+s's investor day presentation, Nov 12, 2015
Slide 1: Legacy Project – On track
K+S Aktiengesellschaft Legacy Project – On track Capital Markets Day Merkers - November 12th, 2015 Dr. Ulrich Lamp, President and CEO of K+S Potash Canada
Slide 2: Legacy Project Components
Legacy Project Components Rail connection/ Railcars K+S Group 2
Slide 3: How it Begun … (Q1/2012)
Legacy Project How it Begun … (Q1/2012) K+S Group 3
Slide 4: What We Defined … (Q4/2013)
Legacy Project What We Defined … (Q4/2013) K+S Group 4
Slide 5: Where We Stand … (Q4/2015) I
Legacy Project Where We Stand … (Q4/2015) I K+S Group 5
Slide 6: Where We Stand … (Q4/2015) II
Legacy Project Where We Stand … (Q4/2015) II Rail construction by Canadian Pacific Railways “on track” Railcars ordered from National Steel Car Port Construction on Pacific Coast Terminals in Vancouver “on track” K+S Group 6
Slide 7: Safety is Top Priority
Legacy Project Safety is Top Priority More than 450 Days Worked Without a Lost Time Injury K+S Group 7
Slide 8: Drone Flight (from Wellfield to Port)
Legacy Project Drone Flight (from Wellfield to Port) Legacy video K+S Group 8
Slide 9: Outlook – What is Left to Accomplish …
Legacy Project Outlook – What is Left to Accomplish … Tasks to complete to Production in 2016 What could go wrong / what could go better? Gradual Commissioning Pad 6-7 Major Injury at Site Build and Complete Weather Northern Tank Farm Performance of Construction Companies Debrining, dr
Slide 10: Summary: On Track
Legacy Project Summary: On Track Engineering is completed, procurement is substantially done, construction is progressing according to plan. October 2014 October 2015 We have shown that we are able to perform in Saskatchewan and are looking forward to start commissioning our Legacy from summer 2016
Slide 11: Q&A session
DEEP VALUE Q&A session K+S Group 11
Slide 12: Closing remarks
DEEP VALUE Closing remarks Norbert Steiner K+S Group 12