  1. Slide 1: Luzon Power Supply Outlook

    LUZON POWER SUPPLY OUTLOOK Mark Christian P. Marollano, REE OIC-Section Head / Senior SRS, EPIMB-PPDD Department of Energy MERALCO Interruptible Load Program (ILP) Webinar 20 May 2021, Thursday

  2. Slide 2: Contents

    Contents 1 Power Sector Overview 2 Luzon Power Supply and Demand Outlook

  3. Slide 3: Power Sector Overview

    Power Sector Overview BSS aE

  4. Slide 4: DOE Response to COVID-19: Energy Agencies

    DOE Response to Energy Agencies COVID-19 ▪ Supervise the restructuring of the ▪ Manage NPC assets and liabilities and industry transmission company pending privatization ▪ Establish the Wholesale Electricity Spot ▪ Manage NPC Privatization process Market (WESM) Power Sector Assets and ▪ Assume NPC d

  5. Slide 5: Energy Corporations and Distribution Utilities

    DOE Response to COVID-19 Energy Corporations Distribution Utilities • Private Investor-Owned Utilities ▪ System Operator and Transmission Network Provider National Grid Corporation of the Philippines (NGCP) • Electric Cooperatives ▪ Governs the Wholesale Electricity Spot Market (WESM) Philippine Ele

  6. Slide 6: Power Sector Industry in a Glance: Pre-EPIRA

    DOE Response to COVID-19 Power Sector Industry in a Glance Pre-EPIRA • Vertically Integrated • Single wholesale provider Generation • Regulated distribution and Other Private Utilities supply by DUs Electric Distribution Cooperatives Transmission • Bundled costs • Regulated Tariffs Residential Indus

  7. Slide 7: Power Sector Industry in a Glance: EPIRA

    DOE Response to COVID-19 Power Sector Industry in a Glance EPIRA • Competitive Generation and Supply • Regulated Distribution and Transmission • Liberalization of Power Industry • Unbundled costs • Fairness and Transparency • Establishment of WESM Department of Energy Powering the Nation

  8. Slide 8: Luzon Power Supply and Demand Outlook

    Luzon Power Supply and Demand Outlook

  9. Slide 9: 2020 Luzon Actual Power Outlook

    2020 LUZON Actual Power Outlook Yellow Alert 16 January 2020 04 June 2020 2020 Actual Peak Demand 2020 Projected Peak Demand = 11,103 MW (9 Mar) = 12,285 MW (16-22 May) Implementation of 12 November 2020 ECQ caused drop on Multiple Transmission Facility Tripping, Over Generation and the demand Over

  10. Slide 10: 2021 Luzon Power Outlook (Excess Capacity as of April 1)

    2021 LUZON Power Outlook (Excess Capacity as of 14 April 2021) Department of Energy Powering the Nation Source: NGCP

  11. Slide 11: End of Presentation: Luzon Power Supply Outlook

    END OF PRESENTATION LUZON POWER SUPPLY OUTLOOK Mark Christian P. Marollano, REE OIC-Section Head / Senior SRS, EPIMB-PPDD Department of Energy MERALCO Interruptible Load Program (ILP) Webinar 20 May 2021, Thursday