Environmental Clean Technologies Limited · ASX:ECT
Environmental Clean Technologies — Shareholder Meeting (November 2014)
11 slides from Environmental Clean Technologies's shareholder meeting presentation, November 2014
Slide 1: AGM 2014 - Managing Director's Presentation
AGM 2014! Managing Directors Presentation!
Slide 2: Disclaimer
Disclaimer! Environmental Clean Technologies Limited has taken all reasonable care in compiling and producing the informa:on contained in this presenta:on. The Company will not be responsible for any loss or damage arising from the use of the informa:on contained in this presenta:on. The informa:on
Slide 3: Overview
Overview! ! News today – Matmor Purchase Nego:a:ons ! Year in Review: – Key Ac:vi:es – Opera:onal achievements – Status of development • Coldry • Matmor ! Next Steps: – Coldry – Matmor
Slide 4: Today's news – Matmor Purchase Negotiations
Today’s news – Matmor Purchase Negotiations! ! Formalise ownership of IP and P&E under ECT – De-‐risk further investment in development – Increase interest from development partners – Increase value within Coldry; Increase value within Matmor ! Key commercial principles agreed; arrangements now sub
Slide 5: Key Activities
Key Activities! ! Comple:on of the demonstra:on plant design ! Iden:fica:on and appointment Continuous Improvement of a world-‐class engineer / fabricator / constructor in Thermax Methodical & Accountable ! Significant capex reduc:on of Execution more than 60% vs Aus Frugal Innovation ! Development t
Slide 6: Operational Achievements
Operational Achievements! ! Total expenses reduced by 38% ! Core cash expenses decreased 19% ! Employee costs were $332k lower in 2014 resul:ng from organisa:onal efficiencies ! Sales and marke:ng expense was $205k lower ! Engineering expense was $2.412m lower ! Research and development rebate was $34
Slide 7: Status of Development – Coldry in India
Status of Development – Coldry in India! • Status: Complete Indigenisation and firm • Prepared with support from our Indian engineering partner Thermax, cost estimate this activity informed a significant element within the FS Report and was key to establishing commercial feasibility. • Status: Compl
Slide 8: Status of Development - Matmor
Status of Development - Matmor! NLC and NMDC have both made public statements in rela:on to their endeavours with ECT: ! On 26 August NLC released their Annual Report, sta:ng: “Discussions are in progress with M/s. Environmental Clean Technology, Australia for developing a technology to produce lign
Slide 9: Next Steps – Coldry
Next Steps – Coldry! • Status: Proceeding Agreement to proceed with • In progress, with significant activity on options analysis, including NLC siting, raw coal supply, waste heat integration and Matmor opportunities • Status: In progress – 95% complete • The formation of ECT India involves the esta
Slide 10: Next Steps – Matmor
Next Steps – Matmor! ! Con:nue tes:ng program with interested par:es – Ores, Fines, Slimes and others Determine the range of – Lignite “recipes” we will design the Pilot plant around – Batch + Semi-‐Con:nuous tes:ng ! Development of collabora:on op:ons ! Pilot plant development – Engineering & Scal
Slide 11: Thank you
Thank you ! Ashley Moore Managing Director ! info@ectltd.com.au ! +613 9909 6784 ! www.ectltd.com.au
Environmental Clean Technologies — Shareholder Meeting (November 2014) on 6ix