    SHERRITT THE NAME IN NICKEL Q4 Earnings Call February 12, 2018 1

  2. Slide 2: Forward-looking statements

    Forward-looking statements This presentation contains certain forward-looking statements. Forward-looking statements can generally be identified by the use of statements that include such words as “believe”, “expect”, “anticipate”, “intend”, “plan”, “forecast”, “likely”, “may”, “will”, “could”, “sho

  3. Slide 3: Participants

    Participants David Pathe President & CEO Steve Wood Executive Vice President & COO Andrew Snowden Senior Vice President & CFO 3

  4. Slide 4: Q4 2017 highlights

    Q4 2017 highlights 1 Restructuring at Ambatovy JV eliminated $1.4B of debt 2 NDCC at Moa was lowest since Q3 2004 3 Received $19.9M in cash flow from Moa JV 4 Higher commodity prices and favorable market outlook Sherritt is now ideally positioned to benefit from the nickel price recovery 4

  5. Slide 5: Market environment

    Market environment 5

  6. Slide 6: Nickel and cobalt price trends

    Nickel and cobalt price trends Nickel vs. 90-Day Moving Average (DMA) Cobalt vs. 90-Day Moving Average (DMA) $7.00 $40 Avg. reference prices Avg. reference prices 2017: US$4.72 2017: US$26.53 $6.50 Q4 2017: US$5.25 $35 Q4 2017: US$31.60 $6.00 $30 $5.50 $5.00 $25 $4.50 $20 $4.00 $15 $3.50 $3.00 $10 5

  7. Slide 7: Auto industry is undergoing dramatic changes

    Auto industry is undergoing dramatic changes* 2019 2020 2022 2025 - China begins EV - 100% of Jaguar Land - Ford will launch an all- - Norway’s ban of ICE production quotas at Rover’s fleet will be electric SUV + 24 vehicles take effect 10% of all vehicles electric hybrid and 16 full EVs - 30% of Au

  8. Slide 8: EV batteries will increasingly rely on nickel

    EV batteries will increasingly rely on nickel Kg Content for 50k Wh NMC Battery Changes driven by: Nickel 24.1 - Cobalt supply constraints 32.4 34.4 - Commodity pricing Manganese 24.1 environment 10.8 - Surging end-product Cobalt 24.1 4.3 demand 10.8 4.3 NMC 1:1:1 NMC 6:2:2 NMC 8:1:1 Today 2025 Nick

  9. Slide 9: Sherritt is a low cost nickel producer

    Sherritt is a low cost nickel producer 2017 Nickel industry NDCC 10 C1 Cash Costs (US$/lb) 2017 avg. reference 5 price US$4.72/lb Ambatovy = US$3.83 (2017) Moa = US$2.35 (2017) 0 25th percentile 50th percentile US$2.08 US$3.75 (5) 0 1,000 2,000 3,000 4,000 Mlbs NDCC at Moa and Ambatovy declined sign

  10. Slide 10: Operations

    Operations 10

  11. Slide 11: Metals highlights - Moa JV

    Metals highlights - Moa JV Production(1) (tonnes) NDCC (US$/lb) Nickel Cobalt 4,134 465 3,782 $3.80 382 $1.80 Q4 2016 Q4 2017 Q4 2016 Q4 2017 Q4 2016 Q4 2017 • Q4 2017 production impacted by • US$1.80/lb lowest since Q3 2004 abnormally heavy rainfalls • Driven by high cobalt credit and US$0.50/lb •

  12. Slide 12: Metals highlights - Ambatovy JV

    Metals highlights - Ambatovy JV Production(1) (tonnes) NDCC (US$/lb) Nickel Cobalt 404 5,111 $3.27 $3.10 3,111 245 Q4 2016 Q4 2017 Q4 2016 Q4 2017 Q4 2016 Q4 2017 • Production decline driven by poor asset • High cobalt by-product credit offset higher reliability and plant shutdowns operating and mai

  13. Slide 13: Oil and Gas highlights

    Oil and Gas highlights Oil Production (total NWI, boepd) Unit operating costs (Cuba GWI, $/bbl) 8,163 $12.24 $10.95 6,101 Q4 2016 Q4 2017 Q4 2016 Q4 2017 • Decrease due to natural reservoir decline • Increase in unit production costs due to and expiration of Varadero West PSC in lower production cos

  14. Slide 14: Power highlights

    Power highlights Electricity production (331/3%, GWh) Unit operating costs ($/MWh) 224 201 $24.73 $23.43 Q4 2016 Q4 2017 Q4 2016 Q4 2017 • Production decline impacted by reduced • Cost improvement driven by the timing of gas availability and after-effects of maintenance activities Hurricane Irma 14

  15. Slide 15: Financial highlights

    Financial highlights 15

  16. Slide 16: Balance sheet impact of Ambatovy JV restructuring

    Balance sheet impact of Ambatovy JV restructuring $M Sept. 30, 2017 Dec. 31, 2017 ASSETS Cash, cash equivalents and short-term investments 290.3 203.0 Restricted cash 1.0 13.0 Other 388.6 364.3 Current Assets 679.9 580.3 Advances, loans receivable and other financial assets 1,422.1 713.0 Investment

  17. Slide 17: Income statement impact of Ambatovy JV restructuring

    Income statement impact of Ambatovy JV restructuring $M 2017 Q4 2017 FY Net earnings (loss) from continuing operations 552.9 308.9 Adjusting items: Gain on Ambatovy restructuring (629.0) (629.0) Unrealized foreign exchange loss 24.1 7.7 Other 1.8 (4.7) Total adjustments (603.1) (626.0) Adjusted net

  18. Slide 18: Status of overdue receivables

    Status of overdue receivables Q4 Progress US$M Q3 Overdue Expected/Due Received Q4 Overdue Oil & Gas receivables $28.5 $20.4 ($7.5) $41.4 Power receivables $72.0 $19.2 - $91.2 Total Cuban energy $100.5 $39.6 ($7.5) $132.6 Receivables • Overdue receivables have always fluctuated over the years • Timi

  19. Slide 19: Consolidated cash from Dec. 31, 2016 to Dec. 31, 2017

    Consolidated cash from Dec. 31, 2016 to Dec. 31, 2017 $ millions 51.3 31.7 308.6 (57.2) (35.0) (71.5) 5.7 203.0 (30.6) Dec. 31, 2016 Adj. continuing Interest paid on Receipt of Repayment of Ambatovy Capital Other Dec. 31, 2017 operating cash debentures advances borrowings restructuring expenditures

  20. Slide 20: 2018 forecast highlights

    2018 forecast highlights Production(1) Capex(1) Nickel (tonnes) 2018 Guidance US$ 16,000 Moa $41M Spending on Oil and Ambatovy $13M Gas will be tied to rate of collections of 4,980 Oil & Gas $39M overdue receivables Power $1M Moa Ambatovy NDCC (US$/lb)(2) Cobalt (tonnes) 1,780 $3.25 $2.75 486 Moa Am

  21. Slide 21: Moa's NDCC – sensitivity analysis

    Moa’s NDCC – sensitivity analysis Impact of a US$5/lb cobalt price increase and US$25/t sulphur price decrease 3.00 2.75 2.50 Key assumptions NDCC (US$/lb) (0.50) 2.00 (0.16) • Cobalt price: ~US$30/lb 1.50 • Sulphur: total cost: ~US$200/tonne (including freight and handling) 1.00 0.50 0.00 Midpoint

  22. Slide 22: Recent developments and outlook

    Recent developments and outlook 22

  23. Slide 23: Oil and Gas - developments

    Oil and Gas - developments Oil fields Havana Puerto Escondido/Yumuri • Three-year extension of Production Moa Sharing Contract to 2021 Nickel Update on Block 10 • Extended drilling timeline at 2nd well • Assessing options to reach target reservoir • Drilling results expected in Q3 • Target based on

  24. Slide 24: Corporate developments

    Corporate developments Unit offering Dutch auction tender offer • Generated $132M in gross • Offer to purchase up to $75 proceeds million of outstanding • 1st capital raise in 10 years debentures • Proceeds to reduce debt • Bidding ends Feb. 13 @ 5:00pm • Expanded shareholder base • Clearing price t

  25. Slide 25: Q&A Discussion

    Sea sores . = : $i A ey xl

  26. Slide 26: Sherritt International Corporation

    Sherritt International Corporation 181 Bay Street, 26th Floor, Brookfield Place Toronto, Ontario, Canada M4T 2Y7 Investor Relations Joe Racanelli Telephone: 416.935.2457 Toll-Free: 1.800.704.6698 Email: investor@sherritt.com Website: www.sherritt.com 26

Sherritt International — Q4 2017 Earnings Presentation on 6ix