  1. Slide 1: Investor Presentation November 2016

    Investor Presentation November 2016 KNR House, 3rd & 4th Floor, Plot No.114, Phase-1, Kavuri Hills, Jubilee Hills, Hyderabad - 500 033 A Well Established Name in Roads & Highway Constructions Phone No. 040-40268759/61/62, Fax No. 040-40268760 E-mail: info@knrcl.com

  2. Slide 2: Disclaimer

    Disclaimer This presentation and the accompanying slides (the “Presentation”), which have been prepared by KNR Constructions Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any secu

  3. Slide 3: Key Highlights & Result Update

    Key Highlights & Result Update 3

  4. Slide 4: Standalone Financial Highlights

    Standalone Financial Highlights Revenue (Rs. Million) EBITDA (Rs. Million) PBT (Rs. Million) 74% +56% +52% 6,767 997 811 639 534 3,882 H1 FY16 H1 FY17 H1 FY16 H1 FY17 H1 FY16 H1 FY17 Revenue (Rs. Million) EBITDA (Rs. Million) PBT (Rs. Million) 72% +43% +41% 3,735 560 490 392 347 2,169 Q2 FY16 Q2 FY1

  5. Slide 5: Key Updates

    Key Updates  Signed a share purchase agreement to sell their equity stake in two Road BOT assets  Company along with Patel Engineering Limited (PEL) signed a share purchase agreement to sell entire equity stake in two Road BOT assets viz. Patel KNR Infrastructure Limited and Patel KNR Heavy Infras

  6. Slide 6: Standalone Financial Results – H1

    Standalone Financial Results – H1 Rs. Million H1 FY17 H1 FY16 YoY Total Revenue 6,766.7 3,881.5 74% Operating Expenses 4,886.7 2,623.3 Employees Expenses 258.7 211.8 Other Expenditure 624.7 407.5 EBITDA 996.7 638.9 56% EBITDA margin 14.7% 16.5% Other Income 190.7 167.7 Depreciation 278.0 208.8 Inter

  7. Slide 7: Standalone Financial Results – Q2

    Standalone Financial Results – Q2 Rs. Million Q2 FY17 Q2 FY16 YoY Total Revenue 3,735.0 2,169.4 72% Operating Expenses 2,714.5 1,441.0 Employees Expenses 129.9 114.4 Other Expenditure 330.8 221.7 EBITDA 559.8 392.2 43% EBITDA margin 15.0% 18.1% Other Income 132.2 96.4 Depreciation 146.3 105.6 Intere

  8. Slide 8: Standalone Balance Sheet

    Standalone Balance Sheet Rs. Millions Sep-16 Rs. Millions Sep-16 NON-CURRENT ASSETS 9,269 EQUITY 8,046 Fixed Assets Equity Share capital 281 Property, plant and equipment 2,647 Other equity 7,765 Capital work-in-progress 32 NON - CURRENT LIABILITIES 1,437 Other Intangible assets 0 Financial liabilit

  9. Slide 9: Business Overview

    r@urc KNR CONSTRUCTIONS LIMITED Business Overview

  10. Slide 10: Business Overview and Vision

    Business Overview  One of the leading companies providing Engineering, Procurement and Construction (EPC) services  To develop KNRCL as a  Major Projects in Roads & Highways – one of the fast growing sector Centre of excellence in  Established presence in Irrigation and Urban Water Infrastructur

  11. Slide 11: Transformation

    Transformation 2015 2/4 laning of Madurai – Ramanathapuram Section of NH-49 in the State of Tamil Nadu under NHDP Phase-III on EPC mode worth Rs. 9,371 mm 2013 3rd BOT Toll project worth Rs.9,005 mn in Kerala 2012 Early completion of Biggest Road Project – Bijapur Hungund Section of Rs. 8,250 mn - 1

  12. Slide 12: Management

    Management… Mr. K.Narasimha Reddy – Founder Promoter & Managing Director  Over 48 years of experience in the Highway sector  Started career in 1968 and engaged in the business of undertaking civil and mechanical contracts  Extensive knowledge and experience in multi project planning Scheduling, c

  13. Slide 13: Supported by Professional Team

    Supported by Professional Team Mr. T.L. Verma (Vice President - Projects) Mr. D. Tirupathi Reddy (GM – Projects)  A Bachelor of Engineering (BE) from MITS  Over 24 years of rich experience in various fields Gwalior (MP) with Over 35 years of total of Civil Engineering experience with ~20 years of

  14. Slide 14: Key Business Strengths

    KGhiRC KNR CONSTRUCTIONS LIMITED Key Business Strengths 14

  15. Slide 15: Project Execution

    1. Project execution Significant experience and Strong track record in timely execution of Projects  Top management’s active Scheduled Completion (Days) involvement at all stages of Project Actual Completion execution (Days)  Selection of Major Raw Material  Selection of construction Camp locatio

  16. Slide 16: Pan India Project Execution Capability

    Pan India Project Execution* Capability Arunachal Pradesh Bihar No of Projects 1 Uttar Pradesh Value of Projects Rs. 920 mn No of Projects 4 No of Projects 1 Value of Projects Rs. 1,411 mn Value of Projects Rs. 1,704 mn Assam No of Projects 2 Madhya Pradesh Value of Projects Rs. 1,913 mn No of Proje

  17. Slide 17: Project Execution Highlights

    Project Execution Highlights  Cement Concrete Road  Completed Widening to 4/6 lanes and Strengthening of Existing two lane carriageway of NH – 5 in the State of Orissa for a length of 56.0 Kms with total contract value of work is Rs 2,310 mn  Existing road was widened & strengthened with flexible

  18. Slide 18: In-house Construction Equipment

    2. In-house Construction Equipment World Class Construction Equipments Use of Right tools for right work Sl. No. Name Of The Machinery Qty 1 Tippers 665 2 Excavators 161 3 Compactors 70 4 Concrete Mixers And Pumps 105 5 Loaders 39 6 Pavers 14 7 Crushers 14 8 Graders 32 9 Tractors 28 10 Cranes 34 250

  19. Slide 19: In-house Execution Team

    3. In-house Execution Team In-house team of 800 Qualified and experienced employees led by proven management team 1% 6% 36% 22% Project Engineering Site Supervision Site Engineers Equipment Operators 35% Admin & Office Staff 19

  20. Slide 20: Reputed Clientele

    4. Reputed Clientele National Highways Authority of Andhra Pradesh Road Development India (NHAI) Corporation (APRDC) Ministry of Road Transport & Hyderabad Growth Corridor Limited Highways (MoRTH) (HGCL) Karnataka State Highway Karnataka Road Development Improvement Project (KSHIP) Corporation (KRDC

  21. Slide 21: Reputed Clientele (cont.)

    4. Reputed Clientele (cont.) A.P. Irrigation (Government of Andhra GMR Projects Private Limited Pradesh) Engineers India Limited (Government of India Sadbhav Engineering Limited Undertaking) Public Works Department Oriental Structural Engineers Pvt. (Government of Arunachal Ltd. Pradesh) 21

  22. Slide 22: BOT Portfolio

    r@urc KNR CONSTRUCTIONS LIMITED BOT Portfolio 22

  23. Slide 23: BOT Portfolio – Annuity Projects

    BOT Portfolio – Annuity Projects Patel KNR Heavy Infrastructures Limited Particulars Patel KNR Infrastructures limited (PKIL)^ (PKHIL)^ Stake 40% 40% Project Details Project Type Road-Annuity Road-Annuity State Karnataka Telangana JV Partner PEL PEIL Client NHAI NHAI Length(KM) 60.00 53.00 Concessio

  24. Slide 24: BOT Portfolio – Toll Projects

    BOT Portfolio – Toll Projects Particulars KNR Walayar Tollways Private Limited KNR Muzaffarpur Barauni Tollway Private Limited Stake 100% 51% Project Type Road-Toll Road-Toll Project Detail State Kerala Bihar JV Partner - JKM Infra Project Ltd Client NHAI NHAI No of Lanes Two to Four Two Length(KM)

  25. Slide 25: Walayar–Vadakkancherry Project

    Walayar –Vadakkancherry Project  KNR Walayar Tollways Private Limited is a wholly owned subsidiary of KNR Constructions Limited, incorporated as an SPV for execution of Walayar Road Project  Provisional Completion Certificate for 100% of Project length has been issued for the project on 31st Octob

  26. Slide 26: Muzaffarpur - Barauni Project

    Muzaffarpur - Barauni Project  KNR Muzaffarpur Barauni Tollway Private Limited is a Step down subsidiary of KNR Constructions Limited, incorporated as an SPV for execution of Muzaffarpur -Barauni Road project on BOT (Toll) basis  Provisional Completion Certificate for 75% of Project length has bee

  27. Slide 27: Order Book & Business Strategy

    Order Book & Business Strategy 27

  28. Slide 28: Order-book Break-up

    Order-book Break-up Order book of Rs. 45,791 million as on 30th September 2016 Other State Govt. 100% 43% Others Captive 1% 0% International Order* 6% Central Govt. 50% Captive State Govt. Central Govt. International Order* Others * - Government of People's Republic Of Bangladesh 28

  29. Slide 29: Order-book Highlights

    Order-book Highlights Key Projects Rs. mln Irrigation Roads - 15% Hubli – Hospet Section of NH - 63 6,674 Non Captive 85% Roads - Madurai -Ramanathpuram Section of NH-49 6,526 Captive 0% Thiruvananthapuram Bypass 4,985 Rehabilitation and upgradation of Dindigul-Bangalore 4,149 Road (Pollachi to Coim

  30. Slide 30: Order-book: State-wise

    Order-book: State-wise Arunachal Pradesh No of Projects 1 Balance Value Rs. 557 mn Madhya Pradesh No of Projects 3 Balance Value Rs. 2,439 mn Karnataka AP & Telangana No of Projects 9 No of Projects 10 Balance Value Rs. 7,699 mn Balance Value Rs. 7,507 mn Tamil Nadu Kerala No of Projects 9 No of Pro

  31. Slide 31: Business Strategy

    Business Strategy Focus on Projects involving Higher degree of engineering skills Continuously Focus on securing explores growth EPC contracts from opportunities by reputed Clients and forming strategic Concessionaire Joint Ventures (JVs) Capitalise on Opportunity of Execute all the huge Infrastruct

  32. Slide 32: Financial Highlights

    r@urc KNR CONSTRUCTIONS LIMITED Financial Highlights 32

  33. Slide 33: Standalone Financial Results

    Standalone Financial Results* Rs. Million FY16 FY15 YoY Total Revenue 9,025.5 8,761.3 3% Operating Expenses 6,062.9 5,965.5 Employees Expenses 435.2 380.8 Other Expenditure 973.3 1,153.6 EBITDA 1,554.1 1,261.4 23% EBITDA margin 17.2% 14.4% Other Income 304.9 124.6 Depreciation 431.4 540.6 Interest 1

  34. Slide 34: Standalone Balance Sheet

    Standalone Balance sheet* Rs. in Million Mar-16 Mar-15 Rs. in Million Mar-16 Mar-15 Shareholder’s Fund 7,270 5,692 Non-Current Assets 7,689 5,254 Share capital 281 281 Fixed Assets 2,468 2,269 Reserves & Surplus 6,988 5,411 Non-current Investments 355 228 Minority Interest 0 0 Deferred Tax Assets (N

  35. Slide 35: Consolidated Financial Results

    Consolidated Financial Results* Rs. Million FY16 FY15 YoY Total Revenue 9,951.2 9,311.9 7% Operating Expenses 6,634.5 6,470.8 Employees Expenses 466.9 382.3 Other Expenditure 1,108.0 1,191.0 EBITDA 1,741.9 1,267.8 37% EBITDA margin 17.5% 13.6% Other Income 424.1 128.9 Depreciation 480.7 551.7 Intere

  36. Slide 36: Consolidated Balance Sheet

    Consolidated Balance sheet* Rs. in Million Mar-16 Mar-15 Rs. in Million Mar-16 Mar-15 Shareholder’s Fund 6,970 7,885 Non-Current Assets 14,563 15,165 Share capital 281 281 Fixed Assets 12,631 13,432 Reserves & Surplus 6,688 7,604 Non-current Investments 168 236 Minority Interest 807 906 Deferred Tax

  37. Slide 37: Standalone Financial Highlights

    Standalone Financial Highlights* Financial Year 2010 2011 2012 2013 2014 2015 2016 Rs. 7,125 Rs. 7,930 Rs. 7,505 Rs. 6,921 Rs. 8,348 Rs. 8,761 Rs. 9,025 Turnover $118.6 $132.0 $125.0 $115.2 $139.0 $140.0 $136.1 Rs. 1,121 Rs. 1,356 Rs. 1,338 Rs. 1,164 Rs. 1,258 Rs. 1,261 Rs. 1,554 EBITDA $18.7 $22.6

  38. Slide 38: Standalone Financial Highlights

    Standalone Financial Highlights Revenue & EBITDA (Margin %) EBITDA 15.7% 17.1% 17.8% 16.8% 15.1% 14.4% 17.2% Margin (%) 8,761 9,026 7,930 8,348 7,125 7,505 6,921 Revenue 1,356 1,338 1,164 1,258 1,261 1,554 1,121 EBITDA 2010 2011 2012 2013 2014 2015 2016 Net Profit & Net Worth (RoE) RoE (%) 16.7% 16.

  39. Slide 39: Standalone Net Working Capital Days

    Standalone Net Working Capital Days 79 69 53 52 48 98 43 52 45 74 40 66 64 45 51 53 41 34 26 23 28 7 10 13 16 16 15 18 15 20 15 17 12 8 12 6 Mar-10 Mar-11 Mar-12 Mar-13 Mar-14 Mar-15 Mar-16 Jun-16 Sep-16 Inventory Debtors Creditors Net Working Capital 39

  40. Slide 40: Shareholding Pattern as on 30th September 2016

    Shareholding Pattern as on 30th September 2016 Shareholders Holding more than 1% of the Equity % to Equity (Other than Promoters) HDFC Mutual Fund 8.35% 10.5% Tata Mutual Fund 3.76% 26.4% 58.1% ICICI Mutual Fund 3.04% Copthall Marutius Investment Limited 3.11% 5.0% Franklin Mutual Fund 1.80% PROMOTE

  41. Slide 41: Other Businesses

    Other Businesses  Strong growth opportunity in development of Agricultural Infrastructure Irrigation & Water Management Projects  Execution of Irrigation & Water Supply Projects with Joint Venture Partners And Urban Water  Executed 3 Projects in Telangana & 1 Project in Infrastructure Bihar Manag

  42. Slide 42: Project Gallery

    r@urc KNR CONSTRUCTIONS LIMITED Project Gallery 42

  43. Slide 43: Completed Projects

    Completed Projects BOT (Annuity) Road Project on NH-7 in the BOT (Annuity) Road Project on NH-7 in the State of Telangana State of Telangana 43

  44. Slide 44: Completed Projects

    Completed Projects BOT (Annuity) Road Project on NH-7 in the Four Lane Highway on NH-50, Bijapur to State of Karnataka Hungund Project in the State of Karnataka 44

  45. Slide 45: Completed Projects

    Completed Projects Road Project in the state of Karnataka - Road Project in the state of Karnataka - Bijapur - Hungund Bijapur - Hungund 45

  46. Slide 46: Completed Projects

    Completed Projects Walayar –Vadakkancherry BOT (Toll Road ) Walayar –Vadakkancherry BOT (Toll Road ) Project, Kerala Project, Kerala 46

  47. Slide 47: Completed Projects

    Completed Projects Bridge across River Godavari in Telangana State 47

  48. Slide 48: Completed Projects

    Completed Projects Bridge across River Godavari in Telangana Bridge across River Godavari in Telangana State State 48

  49. Slide 49: Under-Construction Projects

    Under-Construction Projects Muzaffarpur -Barauni Road project on BOT Muzaffarpur -Barauni Road project on BOT (Toll), Bihar (Toll), Bihar 49

  50. Slide 50: Under-Construction Projects

    Under-Construction Projects Flyover at Coimbatore in the State of Tamil Irrigation Project in Telangana State Nadu 50

  51. Slide 51: For further information, please contact

    For further information, please contact: Company : Investor Relations Advisors : KNR Constructions Ltd. Strategic Growth Advisors Pvt. Ltd. CIN: L74210DL1995PLC238364 CIN: U74140MH2010PTC204285 Mr. K. Venkata Ram Rao Mr. Jigar Kavaiya / Mr. Kevin Shah (GM - Finance & Accounts) +91-9920602034 / +91 9