  1. Slide 1: Documents and Timelines For LDC Based Projects

    Documents and Timelines For LDC Based Projects Brad Colden – Manager – Customer Business Relations – Hydro One May 23, 2013 1

  2. Slide 2: HONI’s Role

    HONI’s Role • Our objective - Trusted Advisor – help your organizations navigate the processes – Provide technical assistance where requested/necessary

  3. Slide 3: Agenda

    Agenda • CIA/DTCA Application Components • Threshold CIA (TCIA) Process Review • Revised Letter of Equivalency (LoE) • Project Sizes and Document Requirements & Timelines - Matrices • Distributed Generation update • TIR Update (HONI - Technical Interconnection Requirements) • Questions

  4. Slide 4: CIA Application Components

    CIA Application Components • TAT /DAT – Capacity Screening Link to webinar for TAT/DAT process • Application/Study Agreement • Form B • Single Line Diagram • Map of Location (Distribution Operating Maps may be requested through the Business Customer Centre – BCC) • Payment

  5. Slide 5: Threshold CIAs

    Threshold CIAs • LDC Owned feeder OR Express/Dedicated feeders • Initial Capacity up to 5 MW* • Solar based Small FIT (CAE projects) • May be revised due to changes/constraints to the system or at the request of the LDCs * 50% of remaining bus capacity up to 5 MW at Hydro One discretion

  6. Slide 6: Threshold CIAs Advantages

    Threshold CIAs Advantages • No Charge • LDCs can move projects between TCIAs if system changes are required with appropriate notification to Hydro One. • May be extended to accommodate connecting projects

  7. Slide 7: Threshold CIAs Major Process Highlights

    Threshold CIAs Major Process Highlights • Reminders – 5 months – expiry reminder – 6 months – expiry notice & call to FIT Contact – 7 months – expired project notice & call to FIT Contact • For Extensions (six month extensions) – Provide LoEs for connected projects – List valid projects identified f

  8. Slide 8: Letters of Equivalency (LoEs)

    Letters of Equivalency (LoEs) – Updated to include additional information necessary to add the generation unit to OGCC data systems. – Draft • Four (4) weeks in advance of ISD – Signed LoE • 10 days after In Service Date • Signed by a P. Eng or Officer of the LDC – Single Line Diagram required when

  9. Slide 9: Letter of Equivalency (LoE)

    Letter of Equivalency (LoE) • Enables no single line for projects ≤ 500 kW on an LDC owned feeder • Express feeder – if all Protections are owned by LDC an SLD is not required.

  10. Slide 10: Letter of Equivalency – Cont’d

    Letter of Equivalency – Cont’d Generator/ Site Name of Facility (Generator) Enhance OPA Contract Number (if applicable) Legal Address view of revised LDC Operating Designation sectioning Proposed Energization Date 3-Phase or Phase (Red, White or Blue) Fuel Type (Wind, Solar, Bio, Hydro) Capacity (MW

  11. Slide 11: Project Size: less than or equal to 250 kW Hydro One owned / shared

    Project Size: less than or equal to 250 kW Hydro One owned / shared feeders w/ downstream embedded LDC Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC Feeder Protection Setting Review HONI Protection Settings Review - Six (6) weeks before ISD SCADA Monito

  12. Slide 12: Project Size: Less than or equal to 500 kW LDC owned / Express Feeder

    Project Size: Less than or equal to 500 kW LDC owned / Express Feeder No Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC • Setting Reviewed during LDC CIA Feeder Protection Setting Review • If changes required - An approved copy of proposed (required on E

  13. Slide 13: Project Size: from 251kW to 500 kW Hydro One owned /shared feeders

    Project Size: from 251kW to 500 kW Hydro One owned /shared feeders w/ downstream embedded LDC Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC Feeder Protection Setting Review • HONI Protection Settings Review ‐ Six (6) weeks before ISD • Monitoring Requir

  14. Slide 14: Project Size: 501kW to 1MW Fully Owned LDC feeder / Express Feeders

    Project Size: 501kW to 1MW Fully Owned LDC feeder / Express Feeders (serving only that LDC) Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC • Setting Reviewed during LDC CIA Feeder Protection Setting Review • If changes required - An approved copy of prop

  15. Slide 15: Project Size: 501kW to 1MW Hydro One owned /shared Feeders

    Project Size: 501kW to 1MW Hydro One owned /shared Feeders w/ downstream embedded LDC Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC HONI Protection Settings Review Required – Six (6) weeks before Feeder Protection Setting Review Cases by Case Basis (If

  16. Slide 16: Project Size: Greater than 1 MW Fully Owned LDC feeder / Express Feeders

    Project Size: Greater than 1 MW Fully Owned LDC feeder / Express Feeders (serving only that LDC) Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC • Setting Reviewed during LDC CIA Feeder Protection Setting Review • If changes required - An approved copy of

  17. Slide 17: Project Size: Greater than 1 MW Hydro One owned/shared Feeders

    Project Size: Greater than 1 MW Hydro One owned/shared Feeders w/ downstream embedded LDC Engineering and Project Management Assignment Scope / Requirements Requirements from the LDC HONI Protection Settings Review • Required Feeder Protection Setting Review • Cases by Case Basis Directioning will b

  18. Slide 18: DG Processes – FIT 2.0 DATs

    DG Processes – FIT 2. 0 DATs • The OPA will release two (2) waves of DATs: Feeder Level DATs and individual (project) DATs. Currently, GCD has done some preliminary screening and expects 132 Feeder DATs on Hydro One feeders. Expecting 79 cases of shared feeders. • The OPA has a very aggressive timel

  19. Slide 19: TIR - Revision 3 Technical Interconnection Requirements

    TIR - Revision 3 Technical Interconnection Requirements • No longer a mandatory requirement for LDCs connecting on LDC owned or express feeders. • Still available as a resource • Posted at: http://www.hydroone.com/Generators/Pages/TechnicalRequirements.aspx • This webinar will be posted at this addr

  20. Slide 20: Thank you

    Thank you e The End. hyd rg 20