Barrick Mining Corporation · TSX:ABX

Barrick Mining — Barrick Gold — 2002 Mining Investment Forum - Goldstrike Mine Tour

38 slides from Barrick Mining's conference presentation, Oct 7, 2002

  1. Slide 1: Welcome to Goldstrike

    October 7, 2002 Welcome to Goldstrike 1

  2. Slide 2: History

    Autoclave Betze-Post Roaster Rodeo Meikle History • Purchased property in 1986 • Oxide heap-leach operation • $62 million viewed as excessive • Barrick’s position: – Double the reserves – High-grade ore potential – Autoclave experience at Mercur 2

  3. Slide 3: Contribution to Barrick

    Contribution to Barrick • Employ 1,700 highly trained and skilled mining professionals • 14,000 direct and indirect jobs • $11 million to communities, schools and charities Reserves and Production 2001 Reserves: 20.4 million ounces 2.5 Production 2 1.5 21.6 million ounces 1 0.5 0 '87 '00 '01 '02E 3

  4. Slide 4: Low Costs

    Low Costs 2002E Cash Costs per Ounce $350 $300 $250 $217 $200 $150 $100 $50 $- '87 '01 '02E Current Status • Two high grade mines • World-Class processing facilities • Solid base of employees 4

  5. Slide 5: Historical Performance

    Historical Performance Manpower % Diff. 1995 1998 1999 2000 2001 98-2001 Surface Open Pit 911 846 800 684 629 -26% Autoclave 386 348 341 340 313 -10% Roaster 3 75 118 131 Other 251 249 200 191 200 -20% Subtotal 1,548 1,446 1,416 1,333 1,273 -12% Underground 66 279 340 468 453 62% Total 1,614 1,725 1

  6. Slide 6: Historical Performance

    Historical Performance Unit Operating Costs Mining $/ton mined 1998 1999 2000 2001 2002E Open Pit .91 .84 .89 .83 .77 Underground 44.99 39.46 38.12 43.07 48.33 Process $/ton milled Autoclave 20.36 20.31 20.30 19.18 18.18 Roaster - - 12.46 13.10 11.76 Historical Performance Category of Spend ($millio

  7. Slide 7: Historical Performance

    Historical Performance Capital Spending ($millions) 1998 1999 2000 2001 2002E Surface 68 272 117 32 13 Underground 46 21 90 90 35 Outlook Increase Reserves and Production • Improve recovery rates • Increase throughput • Continue underground exploration • District Development Program – Use Goldstrike

  8. Slide 8: Outlook

    Outlook Lower Costs • Open pit • Underground • Processing Outlook Cash Flow (millions of dollars) 20011 2002E2 Revenue $823 $691 Costs (473) (440) Stripping Amortization 146 111 Deferred Stripping (129) (103) Capital (122) (48) Free cash flow $245 $211 1100% sold at $340oz. 250% production at $365oz

  9. Slide 9: Reserves and Exploration

    Reserves and Exploration Reserves and Exploration 2001 Reserves Contained Tons Grade ounces (000’s) (oz/ton) (000’s) Betze-Post 108,854 0.151 16,433 Meikle 8,992 0.439 3,946 Total 117,846 20,379 9

  10. Slide 10: Reserves and Exploration

    Reserves and Exploration Reserve Growth (millions of ounces) 50 43.6 40 30 20 10 0 '87 '00 '01 Reserves and Exploration District Development Program • High chance of new discovery • Rapid development • Most profitable 10

  11. Slide 11: Reserves and Exploration

    Reserves and Exploration District Development Program • Exploration close to known ore bodies and new opportunities within the district • Acquire adjacent properties – Rossi – Dee – REN ROSSI STORM North DEE REN Carlin BOOTSTRAP/ CAPSTONE Trend MEIKLE TARA RODEO GOLDSTRIKE BETZE-POST DEEPSTAR GENESI

  12. Slide 12: Reserves and Exploration

    Reserves and Exploration 2002 Exploration Program (millions) Goldstrike Underground - $1.1 • 26 Drill Holes, 22,000 Feet • Completed Goldstrike Surface - $2.9 • 15 Drill Holes, 34,000 Feet • Completed Dee/Rossi - $2.8 • 15 Drill Holes, 50,000 Feet • 6 Completed REN - Barrick Share $1.1 • 15 Drill Ho

  13. Slide 13: Reserves and Exploration

    Reserves and Exploration Distributed ArrayTARA MEIKLE Survey RODEO BETZE-POST GENESIS/ BLUESTAR Reserves and Exploration BANSHEE TARA MEIKLE SOB EAST OF HILL POST FAULT RODEO GOLDEN NORTH APRIL SCREAMER WEST SCREAMER BETZE-POST SIPHON SKARN FAULT HILL GENESIS/ BLUESTAR 13

  14. Slide 14: North Carlin Trend

    ROSSI STORM North DEE REN Carlin BOOTSTRAP/ CAPSTONE Trend MEIKLE TARA RODEO GOLDSTRIKE BETZE-POST DEEPSTAR GENESIS/ BLUESTAR 5000 FEET LEEVILLE CARLIN Open-Pit Mining 14

  15. Slide 15: Open-Pit Mining

    Open-Pit Mining 8000’ 8000’ 7500’ 7500’ 1000’ 1000’ Open-Pit Mining (000’s) 1999 2000 2001 2002E Tons mined 155,010 143,205 154,233 146,887 Tons per day 434 401 433 413 Tons of ore 4,809 11,110 17,412 13,208 Grade oz/ton 0.23 0.21 0.15 0.14 Tons waste 150,201 132,095 136,821 133,679 15

  16. Slide 16: Open-Pit Mining

    Open-Pit Mining 14.6 million oz. Open-Pit Mining 14.6 million oz. 16

  17. Slide 17: Open-Pit Mining

    Open-Pit Mining 2 SE – December 2001 Open-Pit Mining 7 W – February 2002 17

  18. Slide 18: Open-Pit Mining

    Open-Pit Mining NE – December 2002 Open-Pit Mining 8 W – December 2004 18

  19. Slide 19: Open-Pit Mining

    Open-Pit Mining 9 W – December 2005 Open-Pit Mining 10 W – April 2007 19

  20. Slide 20: Open-Pit Mining

    Open-Pit Mining 11 W – October 2008 Open-Pit Mining 12 W – May 2010 20

  21. Slide 21: Open-Pit Mining

    Open-Pit Mining 2001 Costs ($215 per oz.) Mining $94 Processing $94 Administration $19 Royalties & Production taxes $8 Open-Pit Mining 2002E Costs ($226 per oz.) Mining $92 Processing $113 Administration $15 Royalties & Production taxes $6 21

  22. Slide 22: Open-Pit Mining

    Open-Pit Mining 2001 Mining Costs Functional basis - $0.83 per ton Hauling 37¢ Roads & Dumps 12¢ Loading 11¢ Engineering 11¢ Drill & Blast 12¢ Open-Pit Mining 2002E Mining Costs Functional basis - $0.77 per ton Hauling 32¢ Roads & Dumps 12¢ Loading 12¢ Engineering 10¢ Drill & Blast 11¢ 22

  23. Slide 23: Open-Pit Mining

    Open-Pit Mining Unit Mining Costs Tons Mined Per Manshift (thousands) 260 $1.20 $1.18 249 $1.15 245 $1.11 $1.10 $1.01 211 220 $1.00 190 $1.02 181 194 $0.94 $0.90 180 165 $0.83 $0.80 $0.70 140 1996 1997 1998 1999 2000 2001 2002E Open-Pit Mining Reducing costs / Improving productivity • Increase emplo

  24. Slide 24: Underground Mining

    Underground Mining roaster roaster Rodeo Meikle Underground Mining roaster roaster Rodeo Meikle 24

  25. Slide 25: Underground Mining

    Underground Mining roaster roaster Rodeo Meikle Underground Mining 1999 2000 2001 2002E Tons hoisted 997,785 1,256,602 1,372,431 1,663,413 Tons per day 2,734 3,433 3,770 4,557 Grade oz/ton 1.071 0.724 0.561 0.430 25

  26. Slide 26: Underground Mining

    Underground Mining Rodeo Development • Initial production – Q4 2001 • 95% open stopes • 5% cut and fill Underground Mining Meikle headframe Meikle 26

  27. Slide 27: Underground Mining

    Underground Mining Underground Mining Roaster Rodeo 27

  28. Slide 28: Underground Mining

    Underground Mining 2001 Costs ($147 per oz.) Administration $11 Mining $90 Royalties & Production Taxes $14 Processing $32 Underground Mining 2002E Costs ($197 per oz.) Administration $26 Mining $123 Royalties & Production Taxes $13 Processing $35 28

  29. Slide 29: Underground Mining

    Underground Mining 2001 Mining Costs Functional basis - $43.07 per ton Engineering / Overhead $2.40 Hoisting $0.68 Drill, Blast and Ground support $9.01 Mining Activities $30.98 Underground Mining 2002E Mining Costs Functional basis - $48.33 per ton Engineering / Overhead $4.81 Hoisting $1.13 Drill,

  30. Slide 30: Underground Mining

    Underground Mining Unit Mining Costs $55 $50 $48.33 $46.60 $44.98 $45 $43.06 $43.07 $41.00 $40 $35.53 $35 1996 1997 1998 1999 2000 2001 2002E Underground Mining Reducing Costs / Improving Productivity • Increase employee involvement • Improve mining methods - Mining recovery rates - Lower dilution -

  31. Slide 31: Underground Mining

    Underground Mining 2002 Variances • Inadequate Planning - 2001 Revision to Reserves - Revision to development plans - Cost Overruns Underground Mining 2002 Variances • 2001 Revised Reserves - More accurate projection of tons & grades - First principles mine planning - Closer scrutiny of remnant stop

  32. Slide 32: Underground Mining

    Underground Mining 2002 Variances • Revision to Development plans - Previously did not recognize ground conditions in Meikle Main zone, Extension and South Meikle Underground Mining 2002 Variances • Revision to Development plans – Upside in Rodeo • Grade as predicted • Faster ramp-up – Re-forecasted

  33. Slide 33: Underground Mining

    Underground Mining 2002 Variances • Cost Overruns – Much higher cemented fill requirements – Higher binder content (9% vs. 5%) – Delays in implementing new shotcrete supply contract Underground Mining Improvement Projects • Productivities – Development ($29.8 MM) • Screenless development - First pha

  34. Slide 34: Underground Mining

    Underground Mining Improvement Projects Backfill Cost Reduction – Binder (~$3.8 MM) • Renegotiated Cement contract September 02 • Possible alternate Fly ash suppliers • Change in mix from 60:40 to 50:50 • Reduction in overall binder content – Aggregate (~$2.6 MM) • Cheaper aggregate in place since M

  35. Slide 35: Processing

    Processing 2001 Reserves by Process Betze-Post* Tonnage OPT** Ounces Autoclave 27,549 0.209 5,760 Roaster 45,433 0.151 6,680 Stockpiles 35,872 0.105 3,777 Sub-Total 108,854 0.151 16,433 Underground Division Autoclave 2,251 0.507 1,141 Roaster 6,740 0.416 2,804 Sub-Total 8,991 0.439 3,945 Total 117,8

  36. Slide 36: Processing

    Processing 2002E Processing Costs Functional basis $ per ton Autoclave Roaster Autoclaving / Roasting 12.10 3.80 Crushing / Grinding 2.79 4.38 C.I.L. / Tailing 3.29 3.58 $18.18 $11.76 Average $15.13 Processing 2002 Estimated Throughput Tons per Day Autoclave Roaster Total Betze-Post 15,993 12,082 28

  37. Slide 37: Processing

    Processing Reducing Costs / Improving Productivity • Employee involvement in CI initiatives and safety programs • Synergies with roaster/autoclaves and continued focus on recovery improvements in both areas • Throughput CI initiatives at both autoclave and roaster facilities • Optimize reagent consu

  38. Slide 38: Forward Looking Statement

    Forward Looking Statement Certain statements included herein, including those regarding production, costs and earnings, constitute "forward looking statements" within the meaning of the United States Private Securities Litigation Reform Act of 1995. Such Forward-looking statements involve known and