  1. Slide 1: AGM – Presentation by CEO & Managing Director

    Tuesday, 6 May 2025 AGM – PRESENTATION BY CEO & MANAGING DIRECTOR Hillgrove Resources Limited (ASX: HGO) (Hillgrove or Company) is pleased to attach a copy of presentation to be delivered by Hillgrove’s CEO & Managing Director, Bob Fulker, at the Company’s Annual General Meeting on Tuesday, 6 May 20

  2. Slide 2: Hillgrove Resources AGM Presentation

    Hillgrove Resources AGM Presentation 6 May 2025 Bob Fulker Managing Director 1

  3. Slide 3: Important Notice and Disclaimer

    Important Notice and Disclaimer Disclaimer To the maximum extent permitted by law, neither Hillgrove nor its related corporations, directors, officers, employees or agents, nor any other person, accepts any liability, including, without limitation, any liability arising from fault or negligence, for

  4. Slide 4: Corporate snapshot

    Corporate snapshot An Australian copper producer Market Statistics Major Shareholders Share price1 $0.034 Freepoint Metals & Concentrates 20.0% Shares on issue 2,537M Ariadne Australia 10.3% Market capitalisation $86M Debt Nil Board & Management Cash2 $15M Derek Carter Chair Enterprise value $79M Bo

  5. Slide 5: Group summary

    Group summary Significant progress in 2024 ▪ January 2024 • Commencement of bulk mining ▪ February 2024 • Processing plant commissioned • First revenues received ▪ July 2024 • Commercial production declared ▪ October 2024 • Maiden Underground Reserve1 • 96% increase in Resource1 • $10 million standb

  6. Slide 6: Sustainability

    Sustainability Strong focus on ESG 1. Scope 2 greenhouse gas emissions (GHG) are indirect emissions (i.e. not ASX:HGO | AGM Presentation | May 2025 created onsite) produced from purchased electricity, steam, heat, or cooling. 5 2. Local is defined as within a 125km radius from Kanmantoo

  7. Slide 7: Year in review

    Year in review Strong operating and financial performance ▪ Improved performance in all key operating metrics quarter on quarter • Development; • Tonnes mined; and • Processing recoveries ▪ Strong focus on cost control, whilst delivering production ▪ Deliveries into legacy lower priced hedges near c

  8. Slide 8: Delivering our strategy

    Delivering our strategy To be a mid-tier Australian, multi asset, copper producer - unlocking value for a sustainable future Delivering the Growing the Priority 1 Priority 2 Business Business 2024 Kanmantoo Organic • Achieved Commercial Production Growth • Improved Mineral Resource • Acceleration of

  9. Slide 9: 2025 contribution to strategy

    2025 contribution to strategy Mining and exploration ▪ Achieve Priority 1 by: • Mining the stopes as outlined by the solids; and • Invest in our future by completing the development drives and linking Kavanagh with Nugent ▪ Achieve Priority 2 by: • Developing ahead of what is required; and • Complet

  10. Slide 10: On lease growth opportunities

    On lease growth opportunities Multiple opportunities to increase our Resource and Reserve ▪ Kanmantoo 2024 Mineral Resources1: 19.3Mt grading 0.77% Cu and 0.14g/t Au containing 150kt Cu and 82koz of Au Compared to 2022 MRE2 this represents a: ▪ 96% increase in contained copper ▪ 138% increase in con

  11. Slide 11: Paringa Mine Circa 1870's

    Paringa Mine Circa 1870’s Remnant building, flue and stack are visible today ASX:HGO | Investor Presentation | April 2025 10

  12. Slide 12: ASX:HGO | AGM Presentation | May 2025

    ASX:HGO | AGM Presentation | May 2025 11

  13. Slide 13: Kanmantoo Mineral Resource

    Kanmantoo Mineral Resource Notes: Cu Au 1. Due to effects of rounding, total numbers may JORC Tonnage Cu Au Ag Bi Mine Area Metal Metal not sum. Classification (kt) (%) (g/t) (g/t) (ppm) 2. Tonnage and metal are rounded to the nearest (kt) (koz) 1,000 tonnes, grades are rounded to 2 3,200 0.94 0.04

  14. Slide 14: Kanmantoo Ore Reserve

    Kanmantoo Ore Reserve Tonnes Cu Metal Au Metal Mine Area JORC Classification Cu (%) Au (ppm) Ag (ppm) Bi(ppm) (kt) (kt) (koz) Proved 1,100 1.01 0.04 2.82 220 12 1 Kavanagh Probable 1,000 0.88 0.15 2.70 140 9 5 Proved + Probable Kavanagh Total 2,100 0.95 0.09 2.76 180 21 6 Proved - - - - - - - Nugent