Besra Gold Inc · ASX:BEZ
Besra Gold — Corporate Update (December 2024)
10 slides from Besra Gold's corporate update, Dec 20, 2024
Slide 1: Disclaimer
Disclaimer Forward looking statements and forecasts This presentation has been prepared by Besra Gold Inc and contains forward-looking statements. Forward-looking statements include those containing words such as “anticipate”, “estimates”, For personal use only “forecasts”, “indicative”, “should”, “
Slide 2: Shareholder Meeting: Jugan Pilot Plant Update
For personal use only 20 December 2025 Shareholder Meeting Jugan Pilot Plant Update Project Development Strategy Recent Activities Next Steps
Slide 3: Jugan Pilot Plant
Jugan Pilot Plant COMPLETED TO DATE • Baseline environmental monitoring • Design, procurement and delivery of For personal use only major components • Earthworks design including TSF • Sterilisation drilling programme NEXT STEPS • Approval of ML/05/2012/D lease renewal date TBA • Approval of sedimen
Slide 4: Focus on how to do this
Project Development Strategy FOCUS ON HOW TO DO THIS • Local employment • Minimum land disturbance • Environment Well positioned for • TSF (Tailings storage facility) method favourable ESG For personal use only • Community • TSF and waste dump size • Timing • Environmental monitoring for compliance
Slide 5: For personal use only
For personal use only Project Development Strategy MORE LIKELY TO REDUCE TO 25m SUBLEVELS PENDING GEOTECHNICAL STUDY OUTCOMES
Slide 6: Minimum land disturbance
Project Development Strategy MINIMUM LAND DISTURBANCE • Reduce open pit footprint • Investigate mechanised UG options For personal use only • Reduce TSF footprint • Less land acquisition required • Flood management is much simpler TSF METHOD • Dry stack tailings • Encapsulate in benign waste • Regul
Slide 7: Power and concentrate production
Project Development Strategy POWER • Hydro power which is low carbon footprint is often preferred by investors For personal use only • Electric options favoured over diesel where practical CONCENTRATE PROUCTION NOT FAVOURED FOR MANY REASONS • Lower metallurgical recovery • Low payability reducing wi
Slide 8: Jugan – Recent Activities
Jugan – Recent Activities INFORMATION GATHERING • Commenced metallurgical test work drilling early December 2024 to obtain representative sample for UG mining option For personal use only • Training commenced for accurate UG Geotech logging • Open Pit and Underground Geotech drilling to follow FEASI
Slide 9: Jugan – Next Steps
Jugan – Next Steps APPROVAL OF ML/05/2012/D LEASE RENEWAL REQUIRED TO CONDUCT PILOT PLANT AND ANY FUTURE MINING OPERATIONS For personal use only Q2 25 Q3 25 Q4 25 Q1 26 Q2 26 Q3 26 Q4 26 Q1 27 Deep Metallurgical Sample Drilling Sample Prep Flotation Qemscan BFS Level Metallurgical Testwork Pastefill
Slide 10: Jugan – Next Steps
For personal use only Jugan – Next Steps