  1. Slide 1: Long Beach Container Terminal

    f ra + = =—t At . Svan wens iF =s Pe | i Container Terminal

  2. Slide 2: Agenda

    AGENDA Terminal Overview Equipment Fleet Terminal Phases Environmental Sustainability

  3. Slide 3: avg

    avg v2

  4. Slide 4: Terminal Particulars

    TERMINAL PARTICULARS 304 acres Annual throughput capacity 3.3 MTEU Three large berths – 4250’ of wharf 76’/23m channel draft – 60’/18.3m alongside Storage capacity 73,000 TEU Intermodal – 48,000 track feet, handling up to 35% on dock rail Two gate complexes (28 in lanes/17 out lanes) 2250 grounded r

  5. Slide 5: Slide 5

  6. Slide 6: Equipment Fleet

    EQUIPMENT FLEET 14 STS Cranes - Tandem lift, dual hoist primary - Fully automated secondary trolley - 26 container (66.5m) outreach - 50.2m above waterside rail (165’/175’ Cab height) 70 ASC - 9 & 10 Wide, 1 over 6 72 AGV - All electric 5 IY RMG Cranes - Dual cantilever Spanning 8 tracks 50 Terminal

  7. Slide 7: Phase I

    PHASE I April 2016 - First Commercial Vessel

  8. Slide 8: Phase II

    PHASE II September 2017 – Phase II Completion

  9. Slide 9: Project Complete

    PROJECT COMPLETE Q4 2019 TERMINAL AREA SUMMARY: MIDOLE HARBOR 2 a, CONTAINER TERMINAL 300 62 ACRES. 4 ¥ " NORTH OF OCEAN BLVD. «24.42 ACRES PIER D AREA 4.24 ACRES (Ol SET-ASIDE AREAS 456 ACRES. a LAY BERTH 41S ACRES. TOTALPIERE TERMINAL © 305.19 ACRES:

  10. Slide 10: Published HTA Turn Time Reports

    Published HTA Turn Time Reports % of Moves % of Average Median Average Visit Time Median Visit Time % of Moves Between Moves Visit Time Visit Time Terminal (minutes) (minutes) Under 1 Hr 1 and 2 Hrs Over 2 Hrs Terminal (minutes) (minutes) Middle Harbor 48 38 79.2% 17.0% 3.8% Middle Harbor 48 38 CUT

  11. Slide 11: Long Beach Container Terminal

    Wk Long Beac Container PANS Terminal

  12. Slide 12: Emission Reduction (CHE + OTR)

    Emission Reduction (CHE + OTR) Emission Reduction from Pier F to MHT 120% Reduction of particle pollutants 100% 96% 96% 96% is more than 80%. 90% 88% 88% 87% 86% 84% 84% 85% 84% 84% Percent of Pier F Emision 80% 58% 60% 52% 51% 47% 43% 40% 34% 33% 20% 0% PM10 PM2.5 DPM NOx SOx CO HC CO2 N2O CH4 Annu