PT Merdeka Copper Gold Tbk · IDX:MDKA

PT Merdeka Copper Gold Tbk — Investor Day (May 2019)

40 slides from PT Merdeka Copper Gold Tbk's investor day presentation, May 16, 2019

  1. Slide 1: Tujuh Bukit Oxide Project

    Tujuh Bukit Oxide Project James Francis, GM - Operations Investor Day 16 May 2019 PT Merdeka Copper Gold Tbk. 1

  2. Slide 2: Agenda

    Agenda 1. TBO Overview 2. HSE 3. Oxide Operations PT Merdeka Copper Gold Tbk. 2

  3. Slide 3: Indonesia, a great address for copper & gold

    Indonesia, a great address for copper & gold 0.5 B lb Cu PT Merdeka Copper Gold Tbk. 3

  4. Slide 4: Tujuh Bukit – A Tier 1 Mineral Resource

    Tujuh Bukit – A Tier 1 Mineral Resource Oxide Project – Proved & Probable Ore Reserves “UHGZ” - Subset of Porphyry Inferred Resource 43 Mt @ 0.82 g/t Au & 23 g/t Ag 250-300 Mt @ 0.7-0.9 % Cu + 0.7-0.9 g/t Au Tujuh Bukit Porphyry – All Inferred Resources 1.9 Bt @ 0.5 % Cu + 0.5 g/t Au + 93 ppm Mo PT

  5. Slide 5: Tujuh Bukit – Mining Operations Permit (IUP)

    Tujuh Bukit – Mining Operations Permit (IUP) Protected Forest Production Forest PT Merdeka Copper Gold Tbk. 5

  6. Slide 6: Tujuh Bukit – General Site Arrangement

    Tujuh Bukit – General Site Arrangement Major Regulatory Permits: IUP – Mining Operations Permit (4,999 Ha) issued by ESDM IPPKH – Forest Area ‘Borrow Use’ Permit (993 Ha) issued by Forestry Department GoI Feasibility Study (FS) approved by ESDM AMDAL – Environment Impact Assessment approved by DLH I

  7. Slide 7: Tujuh Bukit – OH&S

    Tujuh Bukit – OH&S LOST TIME INJURY FREQUENCY RATE Monthly… 3 Month… 12 Month… 4.0 April 2019: 14,254,703 man-hours LTI free 3.0 2017 to 2019 – Zero LTI’s during Commissioning & Ramp-Up of Operations 2.0 1.0 0.0 Jan-17Feb-17Mar-17Apr-17May-17Jun-17 Jul-17Aug-17Sep-17Oct-17Nov-17Dec-17Jan-18Feb-18Mar

  8. Slide 8: Tujuh Bukit – Environment Reclamation

    Tujuh Bukit – Environment Reclamation CWD Reclamation - Before CWD Reclamation - After Monitoring MIA WD Rehabilitation Area OPP Slope Tree Planting Nursery PT Merdeka Copper Gold Tbk. 8

  9. Slide 9: Tujuh Bukit – Environment Hydroseeding Trial

    Tujuh Bukit – Environment Hydroseeding Trial Spray application Boxcut Rehabilitation - Before Boxcut Rehabilitation - After Project Starting from August 2018 to March 2019 (Phase 1) Total 2018 - March 2019 = 4.35 Ha PT Merdeka Copper Gold Tbk. 9

  10. Slide 10: Main CSR - Community Development Programs

    Main CSR - Community Development Programs •Car Health Service •Free Bus School •Organic farming: dragon •Repairmen of road access •Clean Water Program •Scholarship fruit, oranges, coffee bean •Access farm and village •Health Education •Community Reading Corner •SME development roads •Provision of Ad

  11. Slide 11: Tujuh Bukit – Security

    Tujuh Bukit – Security Security Status: • Site is designated as an ‘Obvitnas (Object Vital National) Project’ • Security provided at site by both Police and Military personnel • Security at Candrian Bay LCT landing facility provided by Marines personnel • Perimeter and general site security provided

  12. Slide 12: Tujuh Bukit – HR Manning Number

    Tujuh Bukit – HR Manning Number Project & Studies contractors 11% Project & Description (s) Total % Studies employees Operations employees Operations employees 713 31% 10% 31% Operations contractors 1119 48 % Project & Studies employees 247 11 % Project & Studies contractors 249 11 % Total 2328 100%

  13. Slide 13: Tujuh Bukit – HR Workforce Breakdown

    Tujuh Bukit – HR Workforce Breakdown Workforces Breakdown 1200 4 1000 388 800 10 600 177 277 50 400 476 450 5 0 200 123 136 10 109 65 0 48 Operations Employees Operations Contractors Project & Studies Employees Project & Studies Contractors Ring 1 Ring 2 Nationals Expats Work Forces Breakdown Ring 1

  14. Slide 14: Tujuh Bukit – Operation Work Flow

    Tujuh Bukit – Operation Work Flow PT Merdeka Copper Gold Tbk. 14

  15. Slide 15: Tujuh Bukit – Oxide Operation Snapshot

    Tujuh Bukit – Oxide Operation Snapshot Mining Method Conventional Open Pit Metals Gold and Silver Mineralization Type High Sulphidation Epithermal Process Method Oxide Heap Leach Plant Capacity - Crushing & Stacking Expanding to 22,500 t/day - HLP & ADR Max. 8.2 Mtpa Recovery Gold 79% and Silver 13%

  16. Slide 16: Oxide Operations – Simple & Low Cost

    Oxide Operations – Simple & Low Cost • Conventional open pit mining from 5 low strip ratio pits. • Ore is crushed to 75 mm and agglomerated at 4 Mtpa through an Ore Preparation Plant • Crushed agglomerate is trucked to the Heap Leach Pad where it is irrigated. • Pregnant solution is pumped to the AD

  17. Slide 17: Open Pit Mining – as at 30th April 2019

    Open Pit Mining – as at 30th April 2019 Pit A Mined OPP Pit E Back fill MSP CWD Pit C Location Pit B East Mined Pit B West Mined PT Merdeka Copper Gold Tbk. 17

  18. Slide 18: Open Pit Mining – as at 31st October 2024 end LOM

    Open Pit Mining – as at 31st October 2024 end LOM Pit A Mined OPP Pit E Back fill MSP Pit C Mined CWD Pit B East Back fill Pit B West Back fill New B West WD New B East WD PT Merdeka Copper Gold Tbk. 18

  19. Slide 19: Open Pit Mining – Pit B West (Cutback 3)

    Open Pit Mining – Pit B West (Cutback 3) PT Merdeka Copper Gold Tbk. 19

  20. Slide 20: Open Pit Mining – Pit B East (Cutback 2)

    Open Pit Mining – Pit B East (Cutback 2) PT Merdeka Copper Gold Tbk. 20

  21. Slide 21: Open Pit Mining – Pit A (Cutback 1)

    Open Pit Mining – Pit A (Cutback 1) PT Merdeka Copper Gold Tbk. 21

  22. Slide 22: Open Pit Mining – Central Waste Dump

    Open Pit Mining – Central Waste Dump PT Merdeka Copper Gold Tbk. 22

  23. Slide 23: Open Pit Mining – Sediment Control

    Open Pit Mining – Sediment Control Mine Sediment Pit A Sediment Control Sump Central Sediment Pit C Sediment Sump PT Merdeka Copper Gold Tbk. Sump 23

  24. Slide 24: Open Pit Mining – Drill & Blast

    Open Pit Mining – Drill & Blast Drill & Blast Pattern Bit Diameter Old Current Pit (mm) Ore (m) Waste (m) Stemming (m) Ore (m) Waste (m) Stemming (m) All 95 3.0 X 3.5 2.0 1.90 X 2.20 2.0 – 2.3 Pits 102 2.0 2.05 X 2.35 2.0 – 2.3 PT Merdeka Copper Gold Tbk. 24 127 3.8 X 4.5 2.5 3.20 X 3.60 2.5

  25. Slide 25: Open Pit Mining – Reconciliation 2019 YTD

    Open Pit Mining – Reconciliation 2019 YTD Reconciliation - Grade Control Actual ore tonnes are 5 % below Ore Reserve (2,363 kt vs 2,481 kt) and gold grade is 9 % higher (1.43 g/t vs 1.32 g/t) resulting in additional 4 % contained gold ounces (109 koz vs 105 koz). PT Merdeka Copper Gold Tbk. 25

  26. Slide 26: Open Pit Mining – IDS Radar Trial

    Open Pit Mining – IDS Radar Trial PT Merdeka Copper Gold Tbk. 26

  27. Slide 27: Ore Preparation Plant (crush and agglomerate)

    Ore Preparation Plant (crush and agglomerate) OPP-2 Run-of-Mine Coarse Ore Bin OPP-1 (ROM) Pad Primary Jaw Crusher Screen Building Secondary Cone OPP Sampler / Crusher Cement Addition Agglomerator COS Stockpile Load Out Bay PT Merdeka Copper Gold Tbk. 27

  28. Slide 28: Heap Leach Pad – Bay Layout

    Heap Leach Pad – Bay Layout Bay 6 Bay 5 Bay 4 Bay 3 Bay 2 Bay 1 Bay 7 Bay 8 Bay 9 PT Merdeka Copper Gold Tbk. 28

  29. Slide 29: Heap Leach Pad – Construction Stages

    Heap Leach Pad – Construction Stages HL Stage 4 HL Stage 3 HL Stage 2 HL Stage 1 PT Merdeka Copper Gold Tbk. 29

  30. Slide 30: Heap Leach Pad – Solution Flow

    Heap Leach Pad – Solution Flow LLDPE Booster Pumps Liner & Station Access Ramp Drain Coils BAY 2 BAY 1 BAY 5A BAY 4 BAY 3 Lift 5 BAY 5B Lift 4 F2 Gravel Clay on top of Lift 3 under- liner BAY 6 Lift 2 liner Lift 1 BAY 7 BAY 8 ILS Pond PLS Pond BAY 9 ISWP SWP BLS / ILS (High CN / Low Au) On-Flow PT M

  31. Slide 31: Heap Leach Pad – Stacking

    Heap Leach Pad – Stacking PTD: 10.2 Mt @ 1.75 g/t Au and 11.10 g/t Ag Lift 5 Lift 4 Lift 4 Lift 3 Lift 3 Lift 2 Lift 1 Lift 2 Lift 1 PT Merdeka Copper Gold Tbk. 31

  32. Slide 32: ADR Processing Plant

    ADR Processing Plant Reagent Mixing Desorption Circuit Clarifier & Gold Refinery (Recovery) [ Au off carbon ] Dewatering Area [ Au electrowinning & smelting ] Reagent Storage Mercury Scrubber Site Assay Laboratory - Intertek Process Water Adsorption Circuit (12 x Detoxification Circuit carbon vessel

  33. Slide 33: ADR Processing Plant – Leach Recovery Gold

    ADR Processing Plant – Leach Recovery Gold KCAA Leach Recovery Model tracking closely to Actual and Model Prediction reconciled to end April 2019. PT Merdeka Copper Gold Tbk. 33

  34. Slide 34: ADR Processing Plant – Leach Recovery %

    ADR Processing Plant – Leach Recovery % Indicated recovery tracking closely to model at 70% vs 72% extraction reconciled to end April 2019. PT Merdeka Copper Gold Tbk. 34

  35. Slide 35: Operational Performance

    Operational Performance Unit 2017 Actual 2018 Actual Open Pit Mining Ore Mined M Tonnes 3.3 5.3 Waste Mined M Tonnes 4.1 9.4 Mine Grade Au g/t 2.11 1.53 Contained Metal Au oz 224,784 261,140 Heap Leach Production Ore Crushed and Stacked M Tonnes 3.2 4.9 Grade Stacked Au g/t 2.16 1.58 Recovered Gold

  36. Slide 36: Production, Cost and Capital Guidance

    Production, Cost and Capital Guidance 2019 Guidance Gold Production 180,000 to 200,000 ounces Cash Costs US$ 425 to US$ 500 AISC US$ 650 to US$ 725 Sustaining Capital US$ 22 to US$ 25 million Growth Capital US$ 50 to US$ 53 million Resource definition and discovery US$ 1 million PT Merdeka Copper Go

  37. Slide 37: LOM Q2 Forecast – Total Tonnes Mined and Gold Produced

    LOM Q2 Forecast – Total Tonnes Mined and Gold Produced (stacked area chart) PT Merdeka Copper Gold Tbk. 37

  38. Slide 38: LOM Production Profile

    LOM Production Profile Gold Production 2017-18 Production 250 - Production capacity of 4 Mtpa - Heap Leach total capacity of 36 Mt - Mining of higher grade pits 200 - ADR processing flow rate 460 m3/h 2019-21 - Expansion 150 - Production capacity increases from 4 Mtpa to maximum rate 8.2 Mtpa - Heap

  39. Slide 39: Oxide Expansion Project – Completion in Q2 2019

    Oxide Expansion Project – Completion in Q2 2019 The Company has undertaken construction activities to increase crushing and agglomerating capacity from 4 Mtpa to 8 Mtpa during 2018 and 2019. This did not disrupt existing operations. The table summarises life of mine key statistics: Based on Expanded

  40. Slide 40: Summary – Significant Progress!

    5. Summary – Significant Progress! 1. Construction commenced in 2015 for total capex $131 million, constructed on budget & dry commissioned February 2017. 2. Oxide mining commenced in November 2016 with wet commissioning and first gold March 2017. 3. Ontrack to meet 2019 guidance of 180-200 koz at A