  1. Slide 1: Southern Natural Gas Company 2024 Outage Review

    Slide 1: Southern Natural Gas Company 2024 Outage Review

    Southern Natural Gas Company 2024 Outage Review May 22, 2024

  2. Slide 2: Welcome

    Slide 2: Welcome

    Welcome 2

  3. Slide 3: Agenda

    Slide 3: Agenda

    Agenda • Review of current and upcoming notable Outages • May/June/July/August • Unscheduled outages • North System • South System • South Louisiana System • EEC • The next outage meeting will be on June 19th, at 1:30 CST • Contacts 3

  4. Slide 4: Disclaimers

    Slide 4: Disclaimers

    Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas

  5. Slide 5: Color Key for Maps

    Slide 5: Color Key for Maps

    Color Key for Maps • Yellow • Restrictions are possible • With extended duration, restrictions could be necessary from time to time • Lower than normal pressures may be experienced • Meter(s) affected are noted with (PIN #) • Red • Restrictions are probable 5

  6. Slide 6: Southern Natural Gas Pipeline

    Slide 6: Southern Natural Gas Pipeline

    Southern Natural Gas Pipeline Chattanooga Rome SC Muldon North GA Hartwell Elb MS Bell Mills Aiken a System Tarrant Exp McConnells Atlanta res Pell City DeArmanville Wrens s Louisville Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore

  7. Slide 7: Unscheduled Outage Update

    Slide 7: Unscheduled Outage Update

    Southern Natural Gas Pipeline Unscheduled Outage Update Unscheduled Pipeline maintenance Chattanooga SMLL west of Hall Gate 2-13-24 to RTS-TBD Seg.Rome 560 cap. 700 Mdth/d impacted 95 SC Muldon North Mdth/d Hartwell GA Elb MS Bell Mills Aiken a System Tarrant Exp McConnells Atlanta res Pell City DeA

  8. Slide 8: SNG North System Pigging Review

    Slide 8: SNG North System Pigging Review

    SNG North System Pigging Review May/June/July/August Chattanooga Huntsville Pigging on Logansport Pigging on NML Supply line 6-25-24 to 6-27-24 Rome 6-10-24 to 6-13-24 Pro.5454-east of Pro. 5663-west of Tarrant AL Logansport Muldon Storage Pigging on LL Atlanta Tarrant Bell Mills 6-4-24 to 6-6-24 MS

  9. Slide 9: SNG North System Maintenance Review

    Slide 9: SNG North System Maintenance Review

    SNG North System Maintenance Review May/June/July/August PL. remediation Gadsden Branch loop Chattanooga line 5-13-24 to 8-2-24 Pipeline maintenance Pro. 21261 north of Pell Huntsville Rome Calhoun loop line City 8-19-24 to 9-13-24 Rome Pro.15374 AL north of Bell Mills Muldon Storage Atlanta Tarrant

  10. Slide 10: SNG South System Pigging Review

    Slide 10: SNG South System Pigging Review

    SNG South System Pigging Review May/June/July/August MS Pigging on WSLL 7-9-24 to 7-11-24 Pigging on SMLL Pigging on SMLL Hartwell Pro. 18717 south of 7-16-24 to 7-18- 5-28-24 to 5-30- Wrens Aiken Elb 24 Atlanta 24 a Pro. 36087 west of Exp Pro. 18931 west of Wrens Ellerslie Hall Gate GA res Pigging

  11. Slide 11: SNG South System Maint. Review

    Slide 11: SNG South System Maint. Review

    SNG South System Maint. Review May/June/July/August MS Unit maintenance at Hall Hartwell Gate Aiken Elb 4-1-24 to 5-24-24 Atlanta a Exp Wrens GA res s Ocmulgee Bay Springs unit outage 6-24-24 to 6-26-24 AL Hallgate Seg. 420 Cap. Of 1,675 Ellerslie Auburn Mdth/d impacted 375 Thomaston Mdth/d Rincon E

  12. Slide 12: SNG South System Maint. Review cont.

    Slide 12: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. May/June/July/August MS Pipeline maintenance Hartwell SML 5-20-24 to 6-18-24 Aiken Elb Pipeline maintenance Atlanta Seg. 430 capacity of a SML Exp Wrens 2,283 Mdth/d impacted 5-22-24 to 6-18-24 GA res Seg. 420 capacity of up to 148 Mdth/d s 1,675 Mdth/d impacted

  13. Slide 13: SNG South System Maint. Review cont.

    Slide 13: SNG South System Maint. Review cont.

    SNG South System Maint. Review cont. May/June/July/August SM2ndLL Pipeline remediation Pipeline remediation SML MS 6-3-24 to 6-7-24 Seg. 460 capacity of 6-24-24 to 6-28-24 2,140 Mdth/d Pro.17842/34908 Hartwell impacted 65 Mdth/d west of Thomaston Aiken Elb Pro. 21649 east of Atlanta a Elmore Exp Wre

  14. Slide 14: SNG South Louisiana System Pigging Review

    Slide 14: SNG South Louisiana System Pigging Review

    SNG South Louisiana System Pigging Review May/June/July/August Gwinville Pearl River MS LA Franklinton Pigging on SS28 line 7-15-24 to 7-19-24 Pro. 28751-west of White Pigging on MPFLL Castle 7-15-24 to 7-19-24 Pro. 5942-south of Franklinton West Leg White Castle Toca East Leg Shadysi de Compressor

  15. Slide 15: SNG South Louisiana System Maint. Review

    Slide 15: SNG South Louisiana System Maint. Review

    SNG South Louisiana System Maint. Review May/June/July/August Pipeline maintenance FGL 7-8-24 to 8-8-24 Seg. 370 cap. 1,123 Sesh maintenance at Mdth/d impacted 20 Delhi Mdth/d 5-21-24 to 5-22-24 Cap. South of Gwinville = 456 Mdth/d Gwinville 5-23-24 = Cap. 482 Pipeline maintenance Mdth/d FGLL 5-29-2

  16. Slide 16: EEC Line

    Slide 16: EEC Line

    EEC Line May/June/July/August Rome SC Muldon North GA Hartwell Elb MS Bell Mills aE Aiken Tarrant System McConnells xp Atlanta Reform res DeArmanville Providence Pell City Hall Gate Wrens Louisville s Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selma Elmore

  17. Slide 17: SNG North System Pigging Review

    Slide 17: SNG North System Pigging Review

    SNG North System Pigging Review Remainder of year Chattanooga Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Pigging on NMLL Bear Creek Storage 10-8-24 to 10-9-24 AL Pro. 15346-east of Tarrant Loganspor

  18. Slide 18: SNG North System Maint. Review

    Slide 18: SNG North System Maint. Review

    SNG North System Maint. Review Remainder of year Muldon unit maintenance 9-9-24 to 11-8-24 Muldon Shut-in test Huntsville 10-1-24 to 10-7-24 Restrictions first into ISS Rome then CSS-not to exceed AL 36% of CSS DIQ /DWQ Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArman

  19. Slide 19: SNG South System Pigging Review

    Slide 19: SNG South System Pigging Review

    SNG South System Pigging Review Remainder of year MS Pigging on Ocmulgee Hartwell Atlanta line-Ocmulgee Aiken Elb to Bass Junction Atlanta a 9-17-24 to 9- Exp Wrens 18-24 GA res s Ocmulgee AL Ellerslie Hallgate Auburn Thomaston Elba Riceboro Gallion Selma Elmore Holy Trinity York Enterprise Bay Spri

  20. Slide 20: SNG South System Maint. Review

    Slide 20: SNG South System Maint. Review

    SNG South System Maint. Review Remainder of year Elmore unit maintenance 10-17-24 Thomaston Griffin 2nd Seg. 460 capacity of loop line Pipeline MS 2,293 Mdth/d maintenance impacted 450 Mdth/d 9-16-24 to 9-20-24 Gallion unit Hartwell maintenance Elmore unit North of Thomaston 10-15-24 Gallion unit Pr

  21. Slide 21: SNG South Louisiana System Pigging Review

    Slide 21: SNG South Louisiana System Pigging Review

    SNG South Louisiana System Pigging Review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadysi de Compressor Station Southern will be conducting other Storage Field general maintenance during this period 21

  22. Slide 22: SNG South Louisiana System Maint. Review

    Slide 22: SNG South Louisiana System Maint. Review

    SNG South Louisiana System Maint. Review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadysi de Compressor Station Southern will be conducting other Storage Field general maintenance during this period 22

  23. Slide 23: EEC Line

    Slide 23: EEC Line

    EEC Line Remainder of year Chattanooga Rome SC Muldon North GA Hartwell Elb MS Bell Mills a Aiken Tarrant System Exp McConnells Atlanta Reform res DeArmanville Providence Pell City Hall Gate Wrens Louisville s Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selm

  24. Slide 24: Gas Control Contacts

    Slide 24: Gas Control Contacts

    Gas Control Contacts Skyler Spyker – Manager • (713) – 420 – 2386 (office) • (806)-470-7743 (cell) • skyler_spyker@kindermorgan.com Kal Dankovich – Outage Coordinator • (205) – 533 – 4795 (cell) • kalman_dankovich@kindermorgan.com Jimmy Reese – Lead Controller • (205) – 577 – 3204 (cell) • jimmy_ree

  25. Slide 25: Questions?

    Slide 25: Questions?

    Questions? 25