Slide 1: Unleashing Value from Conflict-Free Tin
UNLEASHING VALUE FROM CONFLICT-FREE TIN ITRI CONFERENCE 2016 BORIS KAMSTRA CEO ALPHAMIN RESOURCE CORP.
Slide 2: Disclaimer
The statements made in this presentation which are not historical facts contain certain forward-looking statements concerning potential developments affecting the business, prospects, financial condition and other aspects of the Company to which this presentation pertains. The actual results of the
Slide 3: Today's Agenda
A new tin Our journey to Our ambitious A bright Geology Feasibility Study future producer Bisie aims awaits TODAY’S AGENDA
Slide 4: Our Journey to Bisie
OUR JOURNEY TO BISIE Identified as a potential high grade tin deposit Invested in exploration program Initial aim was to produce 20ktpa Sn Industry advisors suggested tempering our output Reduced plan to 10ktpa Sn Drill out resource to support mine as a decent investment proposition Significant capi
Slide 5: Bisie Project
BISIE PROJECT Regional location Bisie project area 1km Mpama North Goma Underground drill pads mine Process plant Mombasa Exploration camp Mpama South Construction drill pads camp Access road Dar es Salaam Manoire village
Slide 6: Transition from Explorer to Tin Miner
TRANSITION FROM EXPLORER TO TIN MINER Corporate overview Board and management team Major Tremont Master Holdings 43% Chairman Charles Needham is the Chairman of the Board and has been involved in the DRC mining Shareholders industry for 10 years. Charles is also the Chairman of Ruashi Mining and Kin
Slide 7: Bisie Project Geology: Mpama North
BISIE PROJECT GEOLOGY Mpama North Long section showing chute geometry, high grade intercepts and mineralisation open at depth § Mineralisation focused within a high grade chute which plunges at 40 degrees to the north § At Mpama North tin mineralisation has been delineated through drilling down to 5
Slide 8: Bisie Project Geology: Mpama South
BISIE PROJECT GEOLOGY Mpama South Diamond drill holes with better intercepts at Mpama South • Limited drilling has been carried out at Mpama South • Tin mineralisation defined over >500m • First phase drilling results at Mpama South were similar to those at Mpama North • Significant grades include:
Slide 9: Alphamin's Mineral Resource Base
ALPHAMIN’S MINERAL RESOURCE BASE Mpama North Mineral Resource Tonnes Sn Sn tonnes Classification % (millions) (thousands) Indicated 3.94 3.94 155.3 Inferred 0.84 4.64 38.9 Exploration – Mineral Resource Growth Potential Within Mining Permit PE13155 PR10346 • Mpama South – positive drill • Soil geoch
Slide 10: Bisie Project Upside
BISIE PROJECT UPSIDE BLUE SKY Mpama Deeps Mpama South Regional targets § Well developed tin and copper in soil anomalies along 15km of the Bisie Ridge § Tin mineralization strongly associated with copper, arsenic, lead, zinc and silver § Significant Sn/Cu/Pb/Zn/As soil anomalies defined over § High
Slide 11: Bisie Project Feasibility Study: Mining and Process Methods
BISIE PROJECT FEASIBILITY STUDY MINING AND PROCESS METHODS Mining by sublevel caving methods Process flow sheet follows standard gravity separation methods Succefully piloted using full-scale equipment.
Slide 12: Bisie Project Feasibility Study Results
BISIE PROJECT FEASIBILITY STUDY RESULTS Key Economic Performance Indicators @$14,800/tSn Economic Sensitivities 180 ¡ Probable Mineral Reserves 3.04Mt @ 3.76%Sn As part of the Indicated Mineral resources 160 Project NPV at 15% discount ($ million) ¡ Tin output per annum 9,000t 140 120 ¡ Life of mine
Slide 13: A Bright Future Awaits
A BRIGHT FUTURE AWAITS Phase 2 • Develop Mpama North 2017 to 2018 • Operate mine and plant at • Develop Mpama Deeps • All future output of 9,000t Sn per 2028 to 2031 annum from 2019 to 2027 • Develop Mpama South expansions are 2025 to 2026 expected to be self funded Phase 1 Phase 3
Slide 14: Social License to Operate
SOCIAL LICENSE TO OPERATE —wj AALPHAMIN
Slide 15: What Are the Next Steps on Our Journey?
WHAT ARE THE NEXT STEPS ON OUR JOURNEY? Roll out of community Constructing light development vehicle access road projects Capital raise to • Labour intensive process begin construction • Process of surveying 1400 families in • Forms the foundation commence in all Extended Bisie range for final road
Slide 16: Building the Road to Prosperity
BUILDING THE ROAD TO PROSPERITY
Slide 17: Alphamin: A New Tin Producer with a Fresh Approach
ALPHAMIN A NEW TIN PRODUCER WITH A FRESH APPROACH Alphamin is a pioneering tin Alphamin is committed to exploration and mining business with the vision to be contributing to the stability and Alphamin will be a new viable and economic activity in North Kivu, respected in the international tin scalab
Slide 18: Ready to Deliver Ambitious Aims
READY TO DELIVER AMBITIOUS AIMS Be at steady state Majority of staff production in DRC nationals 2018 Increasing Producing ~9kt local ton Sn in businesses +60% con supporting mine
Slide 19: Expertise to Overcome Challenges and Unlock Potential
EXPERTISE TO OVERCOME CHALLENGES AND UNLOCK POTENTIAL
Slide 20: The Resolve to Succeed
THE RESOLVE TO SUCCEED Drillers’ Workshop Drillers’ Accomodation Shower and Ablution» . Offices and Mess, \ Fuel Storage Facilities Main Accomodations ¥ / Core Area x Heli-Pad New Vodacom Tower servicing the area A LPHAMIN
Slide 21: Thank You Very Much
ANY QUESTIONS? THANK YOU VERY MUCH