Alphamin Resources Corp. · TSXV:AFM

Alphamin Resources — ITRI Conference 2016

21 slides from Alphamin Resources's conference presentation, April 2016

  1. Slide 1: Unleashing Value from Conflict-Free Tin

    UNLEASHING VALUE FROM CONFLICT-FREE TIN ITRI CONFERENCE 2016 BORIS KAMSTRA CEO ALPHAMIN RESOURCE CORP.

  2. Slide 2: Disclaimer

    The statements made in this presentation which are not historical facts contain certain forward-looking statements concerning potential developments affecting the business, prospects, financial condition and other aspects of the Company to which this presentation pertains. The actual results of the

  3. Slide 3: Today's Agenda

    A new tin Our journey to Our ambitious A bright Geology Feasibility Study future producer Bisie aims awaits TODAY’S AGENDA

  4. Slide 4: Our Journey to Bisie

    OUR JOURNEY TO BISIE Identified as a potential high grade tin deposit Invested in exploration program Initial aim was to produce 20ktpa Sn Industry advisors suggested tempering our output Reduced plan to 10ktpa Sn Drill out resource to support mine as a decent investment proposition Significant capi

  5. Slide 5: Bisie Project

    BISIE PROJECT Regional location Bisie project area 1km Mpama North Goma Underground drill pads mine Process plant Mombasa Exploration camp Mpama South Construction drill pads camp Access road Dar es Salaam Manoire village

  6. Slide 6: Transition from Explorer to Tin Miner

    TRANSITION FROM EXPLORER TO TIN MINER Corporate overview Board and management team Major Tremont Master Holdings 43% Chairman Charles Needham is the Chairman of the Board and has been involved in the DRC mining Shareholders industry for 10 years. Charles is also the Chairman of Ruashi Mining and Kin

  7. Slide 7: Bisie Project Geology: Mpama North

    BISIE PROJECT GEOLOGY Mpama North Long section showing chute geometry, high grade intercepts and mineralisation open at depth § Mineralisation focused within a high grade chute which plunges at 40 degrees to the north § At Mpama North tin mineralisation has been delineated through drilling down to 5

  8. Slide 8: Bisie Project Geology: Mpama South

    BISIE PROJECT GEOLOGY Mpama South Diamond drill holes with better intercepts at Mpama South • Limited drilling has been carried out at Mpama South • Tin mineralisation defined over >500m • First phase drilling results at Mpama South were similar to those at Mpama North • Significant grades include:

  9. Slide 9: Alphamin's Mineral Resource Base

    ALPHAMIN’S MINERAL RESOURCE BASE Mpama North Mineral Resource Tonnes Sn Sn tonnes Classification % (millions) (thousands) Indicated 3.94 3.94 155.3 Inferred 0.84 4.64 38.9 Exploration – Mineral Resource Growth Potential Within Mining Permit PE13155 PR10346 • Mpama South – positive drill • Soil geoch

  10. Slide 10: Bisie Project Upside

    BISIE PROJECT UPSIDE BLUE SKY Mpama Deeps Mpama South Regional targets § Well developed tin and copper in soil anomalies along 15km of the Bisie Ridge § Tin mineralization strongly associated with copper, arsenic, lead, zinc and silver § Significant Sn/Cu/Pb/Zn/As soil anomalies defined over § High

  11. Slide 11: Bisie Project Feasibility Study: Mining and Process Methods

    BISIE PROJECT FEASIBILITY STUDY MINING AND PROCESS METHODS Mining by sublevel caving methods Process flow sheet follows standard gravity separation methods Succefully piloted using full-scale equipment.

  12. Slide 12: Bisie Project Feasibility Study Results

    BISIE PROJECT FEASIBILITY STUDY RESULTS Key Economic Performance Indicators @$14,800/tSn Economic Sensitivities 180 ¡ Probable Mineral Reserves 3.04Mt @ 3.76%Sn As part of the Indicated Mineral resources 160 Project NPV at 15% discount ($ million) ¡ Tin output per annum 9,000t 140 120 ¡ Life of mine

  13. Slide 13: A Bright Future Awaits

    A BRIGHT FUTURE AWAITS Phase 2 • Develop Mpama North 2017 to 2018 • Operate mine and plant at • Develop Mpama Deeps • All future output of 9,000t Sn per 2028 to 2031 annum from 2019 to 2027 • Develop Mpama South expansions are 2025 to 2026 expected to be self funded Phase 1 Phase 3

  14. Slide 14: Social License to Operate

    SOCIAL LICENSE TO OPERATE —wj AALPHAMIN

  15. Slide 15: What Are the Next Steps on Our Journey?

    WHAT ARE THE NEXT STEPS ON OUR JOURNEY? Roll out of community Constructing light development vehicle access road projects Capital raise to • Labour intensive process begin construction • Process of surveying 1400 families in • Forms the foundation commence in all Extended Bisie range for final road

  16. Slide 16: Building the Road to Prosperity

    BUILDING THE ROAD TO PROSPERITY

  17. Slide 17: Alphamin: A New Tin Producer with a Fresh Approach

    ALPHAMIN A NEW TIN PRODUCER WITH A FRESH APPROACH Alphamin is a pioneering tin Alphamin is committed to exploration and mining business with the vision to be contributing to the stability and Alphamin will be a new viable and economic activity in North Kivu, respected in the international tin scalab

  18. Slide 18: Ready to Deliver Ambitious Aims

    READY TO DELIVER AMBITIOUS AIMS Be at steady state Majority of staff production in DRC nationals 2018 Increasing Producing ~9kt local ton Sn in businesses +60% con supporting mine

  19. Slide 19: Expertise to Overcome Challenges and Unlock Potential

    EXPERTISE TO OVERCOME CHALLENGES AND UNLOCK POTENTIAL

  20. Slide 20: The Resolve to Succeed

    THE RESOLVE TO SUCCEED Drillers’ Workshop Drillers’ Accomodation Shower and Ablution» . Offices and Mess, \ Fuel Storage Facilities Main Accomodations ¥ / Core Area x Heli-Pad New Vodacom Tower servicing the area A LPHAMIN

  21. Slide 21: Thank You Very Much

    ANY QUESTIONS? THANK YOU VERY MUCH

Alphamin Resources — ITRI Conference 2016 on 6ix