Bannerman Energy Ltd · ASX:BMN

Bannerman Energy — Investor Presentation (March 2025)

35 slides from Bannerman Energy's investor presentation, March 2025

  1. Slide 1: Investor Presentation

    Investor Presentation MARCH 2025 ASX:BMN, OTCQX:BNNLF AND NSX:BMN

  2. Slide 2: Cautionary Statement - Important notices

    CAUTIONARY STATEMENT Important notices Of the Mineral Resources scheduled for extraction and recovery in the Etango-8 Definitive Feasibility Study (DFS) and Etango-XP / XT Scoping Study (Scoping Study), 100% are classified as Measured or Indicated. Bannerman Energy Ltd (Bannerman, the Company) confi

  3. Slide 3: Forward Looking and Competent Person Statements

    FORWARD LOOKING AND COMPETENT PERSON STATEMENTS Important notices Forward Looking Statements Competent Person Statement This presentation includes various forward looking statements which are identified by the use of forward looking words such as Mineral Resources “may”, “could”, “will”, “expect”, “

  4. Slide 4: The leading next-generation uranium supplier of choice

    ABOUT BANNERMAN ENERGY The leading next- generation uranium supplier of choice Our flagship Etango Project is one of the world’s largest, most advanced uranium development assets. Benefiting from its location in Namibia, a highly established uranium production powerhouse. Strongly de-risked through

  5. Slide 5: Corporate snapshot

    ABOUT BANNERMAN ENERGY Corporate snapshot CAPITAL STRUCTURE SHARE PRICE (ASX: BMN) A$5.00 ASX share price (10 Mar 2025) A$2.14 12 month share price range A$1.90 – A$4.87 A$4.00 Shares on issue 178.8 M A$3.00 Market capitalisation A$383 M A$2.00 Options and performance rights 4.4 M A$1.00 Average dai

  6. Slide 6: The leading next-generation uranium supplier of choice

    INVESTMENT HIGHLIGHTS The leading next- generation uranium supplier of choice 1 Licence to operate in Namibia, a stable, highly established uranium jurisdiction 2 Skilled team with deep Namibian uranium operating and developing expertise 3 Fully permitted with all environmental approvals and Mining

  7. Slide 7: Licence to operate in Namibia, a stable, highly established uranium jurisdiction

    INVESTMENT HIGHLIGHTS 1. Licence to operate in Namibia, a stable, highly established uranium jurisdiction Recognised tier-one supplier to global utilities Rossing Husab 45-years of uranium production and export Etango Langer Heinrich Three large-scale uranium mines; Top 3 global producer Excellent i

  8. Slide 8: Experienced Board of Directors with extensive uranium experience

    INVESTMENT HIGHLIGHTS 2. Experienced Board of Directors with extensive uranium operating & development experience ▪ 40+ years mining and process experience as a mining ▪ 20+ years’ transactional and financing experience as a engineer Brandon Munro corporate lawyer and resources executive ▪ 30 years’

  9. Slide 9: Proven management team with deep in-country and uranium operating experience

    INVESTMENT HIGHLIGHTS 2. Proven management team with deep in-country and uranium operating experience ▪ 25+ years’ experience in various legal roles and is a ▪ 30+ years' experience in the uranium, diamond and coal company director Werner Ewald mining industries ▪ Previous senior roles at Wesfarmers

  10. Slide 10: Fully permitted with all environmental approvals and Mining Licence in place

    INVESTMENT HIGHLIGHTS 3. Fully permitted with all environmental approvals and Mining Licence in place Mining licence Environmental licence Etango Mining Licence awarded CONSENT TYPE DATE ACHIEVED December 2023 ECC 01608 (Etango Project) 5 July 2012 ECC 02193 (linear infrastructure) 26 July 2011 Earl

  11. Slide 11: Strong technical and commercial viability demonstrated via Etango-8 DFS

    INVESTMENT HIGHLIGHTS 15 years 113.5 Mt Initial mine life Total ore throughput 4. Strong technical and commercial viability demonstrated via 8 Mtpa 240 ppm Throughput capacity Average U3O8 head grade Etango-8 DFS • Conventional open pit mining and heap leach processing at 8Mtpa throughput 87.8% 3.5

  12. Slide 12: Outstanding Etango-8 upside price leverage

    INVESTMENT HIGHLIGHTS 4. Outstanding Etango-8 upside price leverage Incorporating completion of the Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE) processes 1 Net cashflow (post-tax) Post-tax NPV (8%) 4,500 43% 800 57% 141% 614 76% 3,000 2,537 US$mm US$mm 400 390 1,774 1,5

  13. Slide 13: Further in-ground leverage via subsequent growth options

    INVESTMENT HIGHLIGHTS 4. Further in-ground leverage realisable via ETANGO-XP ETANGO-XT subsequent growth options (EXPANDED SCALE) Average 6.7 Mlbs U3O8 (EXTENDED LIFE) Average 3.5 Mlbs U3O8 output pa (post exp.) output pa • World-class scale Etango deposit can deliver substantially higher value via

  14. Slide 14: Further upside price leverage from Etango-XP / XT

    INVESTMENT HIGHLIGHTS 4. Further upside price leverage from Etango-XP / XT Incorporating completion of the Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE) processes 1 Net cashflow (post-tax) Post-tax NPV (8%) Post-tax IRR 6,000 1,200 66% 45% 51% 211% Etango-XP 105% 4,079 90

  15. Slide 15: Conventional production, technically de-risked through pilot-plant operation

    INVESTMENT HIGHLIGHTS 5. Conventional production, technically de-risked through pilot-plant operation Proven flow sheet Fifteen years of technical de-risking Industrial-scale Heap Leach Demonstration Plant operated at site from 2015 validates flowsheet and key metallurgical parameters Demonstrated y

  16. Slide 16: Long track record of responsibility and sustainability

    INVESTMENT HIGHLIGHTS 6. Long track record of responsibility and sustainability Early SRT Mondesa Conservancy Environmental Youth Opportunities Learner Assistance Tourism Education baseline monitoring Program Hospitality TOSCO since 2008 Trade Association of Namibia scholarships CTAN (NIMT) Rehabili

  17. Slide 17: Delivering significant, lasting positive social and environmental impact

    INVESTMENT HIGHLIGHTS 7. Delivering significant, lasting positive social and environmental impact 3.5 25 64 760 Mlbs U3O8 million million Namibian per annum, enough to power tonnes tonnes of carbon emissions avoided jobs 7-8 large nuclear of coal displaced by our production from nuclear power using

  18. Slide 18: Phased greenlight approach to Etango development

    THE PATHWAY AHEAD Phased greenlight approach to Etango development Initial early works completed on time and on budget (access road and water pipeline) Detailed design works progressing Current contracts in progress at Etango: Bulk earthworks, internal access roads and construction power (running ah

  19. Slide 19: Project Execution

    INVESTMENT HIGHLIGHTS Project Execution 1 Weekly Schedule Tracking of both design and construction 2 Bi-weekly management of 3D Model Progress 3 Continuous measurement of Budget Against Actual 4 Ongoing Claims Register on all contracts 5 Top 12 Risk Items From Risk Register 6 Quality control and saf

  20. Slide 20: Project Execution

    Project Execution Pre-Mortem - Identify what can go Procurement Strategy wrong and put mitigations in place • Re-packaging of contracts to suit smaller before they happen Namibian contractors • Ensuring water supply- technical control • Place 2 phase orders to control escalation during tender compet

  21. Slide 21: Project to Operations

    Project to Operations • Demo plant value to commissioning • Completed gap analysis on operational readiness requirements – 2 year schedule to complete • Staffing network of Werner and Gavin – desire of people in Namibia to want to work for Bannerman • HR Strategy to develop “superintendents” into “m

  22. Slide 22: Construction Water Storage Dam

    ETANGO SITE PROGRESS Construction Water Storage Dam 22

  23. Slide 23: Bulk Earthworks Contractors Camp

    ETANGO SITE PROGRESS Bulk Earthworks Contractors Camp 23

  24. Slide 24: Controlled Entry to Site

    ETANGO SITE PROGRESS Controlled Entry to Site 24

  25. Slide 25: Temporary Water Storage Dam

    ETANGO SITE PROGRESS Temporary Water Storage Dam 25

  26. Slide 26: Box Cut for the Primary Crusher

    ETANGO SITE PROGRESS Box Cut for the Primary Crusher 26

  27. Slide 27: Box Cut for the Primary Crusher

    ETANGO SITE PROGRESS Box Cut for the Primary Crusher 27

  28. Slide 28: Contractors Camp Construction

    ETANGO SITE PROGRESS Contractors Camp Construction 28

  29. Slide 29: Permanent 33kV overhead powerlines

    ETANGO SITE PROGRESS Permanent 33kV overhead powerlines 29

  30. Slide 30: Roadmap to production

    PROXIMATE, LOW RISK, LONG TERM, EXPANDABLE, SOCIALLY RESPONSIBLE Roadmap to production Financing phase ❑ Initial offtake Development phase agreements Contracting ❑ Build / optimise Production phase Expansion phase contract portfolio ❑ Strategic / project Financing financing ❑ FID by mid 2025 ✓ FEED/

  31. Slide 31: Contact Details

    CONTACT DETAILS Gavin Chamberlain Chief Executive Officer Emma Culver Investor Relations and Communications Manager Phone: +61 8 9381 1436 Email: info@bmnenergy.com @BannermanEnergy @Brandon_Munro 31

  32. Slide 32: One of the world's largest, most advanced uranium development assets

    APPENDIX One of the world’s largest, Mineral Resource Estimate (55ppm U3O8 cut-off)1,3 Resource category Tonnes Grade Contained most advanced uranium Measured (Mt) 32.4 (ppm U3O8) 201 U3O8 (Mlb) 14.3 development assets Indicated 345.7 195 148.5 Inferred 140.6 200 62.0 Total 518.6 197 224.9 Globally

  33. Slide 33: Systematically de-risked through the uranium cycle

    APPENDIX Systematically de-risked through the uranium cycle BULL MARKET BEAR MARKET BULL MARKET Bannerman Etango 20 NI 43-101 Etango Etango DFS Nano-filtration Etango-8 lists on the Mtpa Scoping report 20 Mtpa optimisation study Scoping Study Unfolding ASX Study released released DFS delivered study

  34. Slide 34: The uranium market resurgence is unfolding now

    APPENDIX The uranium market resurgence is unfolding now 520 Utility contract demand building Upper Scenario for Uranium Supply and Demand (Mlbs U3O8) 455 Persistent • Rising confidence in medium and long-term global uranium demand growth picture cumulative supply • Emerging Small Modular Reactor (SM

  35. Slide 35: Etango-8 DFS and Etango-XP / XT Scoping Study

    APPENDIX Etango-8 DFS and Etango-XP / XT Scoping Study Incorporating completion of the Front-End Engineering and Design (FEED) and Control Budget Estimate (CBE) processes Key Metrics Unit Etango-8 Etango-XP (second phase to 16 mtpa) Etango-XT (extended life at 8Mtpa) Physicals Total ore mined and pr

Bannerman Energy — Investor Presentation (March 2025) on 6ix