Slide 1: Adex Mining Inc. Meeting global demand for specialty metals
Adex Mining Inc. Meeting global demand for specialty metals

Slide 2: Adex Mining Inc. – TSX-V: ADE
Adex Mining Inc. – TSX-V: ADE • Adex is a Canadian mining company • Focus: to develop specialty metals at the Mount Pleasant Mine in New Brunswick, Canada • Total 12-year revenue: $1.5 billion • World’s largest indium resource • North America’s largest tin resource

Slide 3: Forward-looking statements
Forward-looking statements Certain statements in this Presentation may constitute “forward-looking” statements which involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Corporation, or the industry in which it operat

Slide 4: Registered confirmation of resources
Registered confirmation of resources Fire Tower Zone (FTZ) There is an NI 43-101-compliant indicated resource of 13,489,000 tonnes at 0.33% tungsten (WO3), 0.21% molybdenum (MoS2) and 0.06% bismuth (Bi) at the FTZ as outlined in the NI 43-101-compliant technical review of the Mount Pleasant Property

Slide 5: Overview
Overview • Investment overview • Adex advantages – Strong demand – Low risk – Location and infrastructure • Ore deposit overview • Financials • Milestones

Slide 6: Investment overview
Investment overview Property totals – from Preliminary Economic Assessment Pre-production capital $200 million Revenue – 12 years $1.5 billion Cash flow $802 million IRR (North Zone/ Fire Tower Zone) 28%

Slide 7: Adex advantages
Adex advantages • Strong metal demand • Low-risk operating and financial environment • Excellent location and infrastructure

Slide 8: Strong demand
Strong demand • Flat-panel displays “Raw-material shortages and higher – mobile phones, prices are likely after computers, TVs the global recession • Next generation of spurred companies to delay or cancel photovoltaic cells projects. [We] favor • Recent production of molybdenum, titanium, indium, a

Slide 9: Strong demand – Indium
Strong demand Indium 1200 1000 800 600 400 Monthly Average Price US$ per KG 200 0

Slide 10: Strong demand
Strong demand • Solder, tinplate, and “Longer term outlook other industrial uses for tin looks very encouraging [due to] • Organotin growing demand for compounds in PVC electrical and plastics electronic applications and • Minable tin may run growth in traditional out in 20 years uses.” Libertas Par

Slide 11: Strong demand – Tin
10 15 20 25 30 0 5 01-Apr-04 01-Jul-04 01-Oct-04 01-Jan-05 01-Apr-05 01-Jul-05 01-Oct-05 01-Jan-06 01-Apr-06 01-Jul-06 01-Oct-06 Strong demand 01-Jan-07 01-Apr-07 01-Jul-07 01-Oct-07 Tin 01-Jan-08 01-Apr-08 01-Jul-08 01-Oct-08 01-Jan-09 01-Apr-09 01-Jul-09 01-Oct-09 01-Jan-10 01-Apr-10 KG Monthly Av

Slide 12: Strong demand
Strong demand • Strong future Chinese demand, attributable “Demand for zinc to the automotive will be led by China, growing at sector’s need for an estimated 8% in galvanized steel 2010, to almost 4.5 • Also used as a white million tonnes.” pigment in paint, a fire retardant and wood VM Group resear

Slide 13: Strong demand – Zinc
0 1 2 3 4 5 0.5 1.5 2.5 3.5 4.5 01-Apr-04 01-Jul-04 01-Oct-04 01-Jan-05 01-Apr-05 01-Jul-05 01-Oct-05 01-Jan-06 01-Apr-06 01-Jul-06 01-Oct-06 Strong demand 01-Jan-07 01-Apr-07 01-Jul-07 01-Oct-07 Zinc 01-Jan-08 01-Apr-08 01-Jul-08 01-Oct-08 01-Jan-09 01-Apr-09 01-Jul-09 01-Oct-09 01-Jan-10 01-Apr-10

Slide 14: Strong demand
Strong demand • Has the highest melting “Projected growth in point of any metal tungsten • Used in drill bits, saw consumption over blades, ammunition, the next five years chrome-plating [2009 to 2013] will substitute, jewelry, require… a 32% incandescent light increase in current bulbs production.”

Slide 15: Strong demand – APT (Tungsten)
100 150 200 250 300 50 0 01-Apr-04 01-Jul-04 01-Oct-04 01-Jan-05 01-Apr-05 01-Jul-05 01-Oct-05 01-Jan-06 01-Apr-06 01-Jul-06 01-Oct-06 Strong demand 01-Jan-07 01-Apr-07 01-Jul-07 01-Oct-07 01-Jan-08 01-Apr-08 APT (Tungsten) 01-Jul-08 01-Oct-08 01-Jan-09 01-Apr-09 01-Jul-09 01-Oct-09 01-Jan-10 01-Apr

Slide 16: Strong demand
Strong demand • Specialty steels “A robust auto market • Moly-based lubricants in China is fueling some of the demand for steel. for exploration drilling January saw an • Nuclear reactor increase of passenger condenser tubes (new car sales in China of application) 115.5%, while auto sales in India r

Slide 17: Strong demand – Molybdenum
Strong demand Molybdenum 100 90 80 70 60 50 40 Weekly Average Price 30 US$ per KG 20 10 0

Slide 18: A rich metals inventory
A rich metals inventory NNW Indicated resource Inferred resource North Zone No. 1-5 Sn Lodes 10.9 Mt Sn, In, Zn 7.6 Mt Sn, In, Zn Saddle Zone Fire Tower Zone (past-producer of tungsten: 1983-85) Indicated resource Inferred resource 13.5 Mt W, 0.8 Mt W, a \o _— - \ 3 _—— Granite and feldspar Tungsten

Slide 19: Resource summary
Resource summary weight (%) ! (MoS,) (wo,) NI 43-101 Resources: H Sn In 2n Mo Ww Bi Cu Mount Pleasant Property | Bm indium zine Moyedenum MMM Tungsten [BM sismuth [MM Copper ' ween ene eee pee EES ReneS aeenESEESS ene Seen 2 413,489,000 t ' ‘ (indicated, 2008) | ma | nia | nla | 021 | 033 | 0.06 | o

Slide 20: Low risk
Low risk • Revenues from early mine production will make a significant capital contribution • Will mitigate much of the risk associated with future financing

Slide 21: Location
Location Maine, USA New Brunswick New Brunswick Oromocto a Lake Mount al J Pleasant | a ot. ) George

Slide 22: Infrastructure
Infrastructure • Fully developed mine workings (FTZ) • Crushing and processing complex • Administration building, maintenance shops, warehouse, ore storage etc. • On-site power and water distribution • Established tailings pond • Estimate replacement cost $84 million

Slide 23: Infrastructure
Infrastructure SU \ Crushing and Engineering/ processing ore storage — complex

Slide 24: North Zone – Status
North Zone – Status Completed • Identified 18.5 million tonnes indicated and inferred (43-101 compliant estimate) • Finished preliminary economic assessment January 2010 Underway • Piloting tin and indium–zinc concentrate production – SGS • Piloting zinc metal and indium sponge production – Thibault

Slide 25: North Zone – Status
North Zone – Status Mine plan • Decline access to underground • Open-stope mining with truck haul to surface • Mechanized trackless equipment • Multi-skilled workforce • 3.1 million tonnes over 10 years Mill production plan • Zinc–indium concentrate (flotation) • Hydromet circuit to make zinc metal

Slide 26: NZ – Production stats
NZ – Production stats From 2010 Tin Zinc Indium Preliminary Economic Assessment Concentrate Metal Sponge In the mill Feed grade 0.71% 1.82% 183 g/t Concentrate grade 46% 50% 4,900 g/t Metal recovery 75% 79% 75% Final products Total production 3,200 t/y 4,000 t/y 40 t/y Price - 2010 preliminary asses

Slide 27: North Zone – Financials
North Zone – Financials Mine life – current plan 10 years Production rate 850 t/d ($ Millions) Pre-production capital 71 Annual revenue 48 Annual operating cost 23 Annual cash flow 25 Pre-tax NPV @ 8% 80 Pre-tax IRR 29%

Slide 28: Fire Tower Zone – Status
Fire Tower Zone – Status Completed • Identified 14.3 million tonnes indicated and inferred (43-101 compliant estimate) • Finished preliminary economic assessment 2008 Underway • Bench-testing moly oxide hydromet – SGS (Lakefield) Upcoming • Pilot plant testwork – fall 2010 • Definitive feasibility –

Slide 29: Fire Tower Zone – Status
Fire Tower Zone – Status Mine plan • Vertical crater retreat • Underground primary crushing • Conveyor to surface • 10 million tonnes over 12 years Mill production plan • Tungsten gravity/flotation • Tungsten concentrate into APT • Molybdenum flotation and impurity leach

Slide 30: FTZ – Production stats
FTZ – Production stats From 2008 Tungsten Molybdenum Preliminary Economic Assessment Concentrate In the mill WO3 MoS2 Feed grade 0.33% 0.21% Concentrate grade 30% 80% Metal recovery 82% 76% Final products APT MoS2 Total production 1,900 t/y 1,100 t/y Price - 2008 preliminary assessment ($US/kg) 21.5

Slide 31: Fire Tower Zone – Financials
Fire Tower Zone – Financials Mine life – current plan 12 years Production rate 2,400 t/d ($Millions) Pre-production capital 130 Annual revenue 92 Annual operating cost 49 Annual cash flow 46 Pre-tax NPV @ 8% 164 Pre-tax IRR 27%

Slide 32: Milestones
Milestones 2008 2009 Completed 2008 drilling program, including Updated 43-101 compliant resource more than 13,000m of drilling estimate for NZ Completed preliminary assessment (scoping) on Sn-In-Zn at NZ Updated NI 43-101 compliant resource estimate for the Fire Tower Zone Developed a staged approa

Slide 33: Milestones
Milestones 2010 Pilot plant program – production of indium sponge and zinc metal Pilot plant program – production of tin and indium-zinc concentrates Conclude concentrate and metal off-take sales contracts Confirmation drilling and upgrade of NZ inferred resources to indicated resources NZ definitiv

Slide 34: Mount Pleasant development plan
Mount Pleasant development plan Activity 2010 2011 2012 2013 2014 North Zone Feasibility study Construction Commence production Fire Tower Zone Metallurgical testwork Feasibility study Construction Commence production Pre-production capital – North Zone: $71 million; Fire Tower Zone: $130 million

Slide 35: Leadership team
Leadership team J. Errol Farr President and Mr. Farr is a seasoned executive with over 15 years of CMA CEO, Director experience in finance, accounting and operations with publicly listed junior mining companies. Mr. Farr has been involved with Adex Mining Inc. since its acquisition of Mount Pleasant

Slide 36: Leadership team
Leadership team William (Bill) B. Technical Mr. W.B. Burton founded Adex in 1993 and was CEO Burton Advisor, from 1994 to 1998. He has worked extensively with a BSc (Hon.) Geology Director number of publicly traded mining and industrial companies and is currently President, CEO and a director of Mag

Slide 37: Financial information
Financial information Share structure Issued and outstanding shares 96,526,026 (as of July 12th, Fully diluted share structure 109,473,689 2010) Fully diluted market capitalization $10,947,369 Current share price $ 0.10 52-week range $ 0.195–$ 0.08 Debt None Adex Share Price 0.2 0.15 0.1 0.05 Closin

Slide 38: Summary of investment opportunity
Summary of investment opportunity • Excellent location • Established infrastructure • Stable political environment • Low-risk strategies for staged development and financing • Predictable yields at target grade • Well-timed to take advantage of economic recovery and growth

Slide 39: For more information
For more information Please contact: Errol Farr, President and CEO Adex Mining Inc. 67 Yonge Street, Suite 1402 Toronto, Ontario, M5E 1J8 efarr@adexmining.com 1-416-941-9663 Investor Relations 1-866-508-2339 investorrelations@adexmining.com www.adexmining.com
Source: Internet Archive copy of adexmining.com
More decks from Adex Mining Inc.
Investor Presentation (June 2025)15 slides · Jun 11, 2025
Investor Presentation (September 2014)20 slides · Sep 11, 2014
Investor Presentation (April 2014)20 slides · Apr 21, 2014
Investor Presentation (February 2013)20 slides · Feb 21, 2013
Investor Presentation (December 2011)15 slides · December 2011
Fact Sheet (October 2010)2 slides · Oct 25, 2010