Malaysia Marine & Heavy Engineering Holdings Bhd. · MYX:MHB

Malaysia Marine & Heavy Engineering Holdings Bhd — Q1 2024 Earnings Presentation

24 slides from Malaysia Marine & Heavy Engineering Holdings Bhd's earnings presentation, May 24, 2024

  1. Slide 1: Quarterly Investor Relations Updates 1st Quarter 2024 Financial Results

    Slide 1: Quarterly Investor Relations Updates 1st Quarter 2024 Financial Results

    Quarterly Investor Relations Updates 1st Quarter 2024 Financial Results 24 May 2024

  2. Slide 2: Disclaimer

    Slide 2: Disclaimer

    [Open] Disclaimer This Presentation is not intended to form the basis of any investment decision with respect to Malaysia Marine and Heavy Engineering Holdings Berhad (MHB). Neither this presentation nor anything contained herein shall form the basis of, or be relied upon in connection with, any con

  3. Slide 3: Agenda

    Slide 3: Agenda

    AGENDA 1 Industry Challenges & Market Outlook 2 Business Highlights 3 Ongoing Projects 4 Financials 5 Environmental, Social and Governance 6 Strategic Focus

  4. Slide 4: Industry Challenges & Market Outlook

    Slide 4: Industry Challenges & Market Outlook

    INDUSTRY CHALLENGES & MARKET OUTLOOK

  5. Slide 5: Challenging environment persisted and expected to remain

    Slide 5: Challenging environment persisted and expected to remain

    [Open] Challenging environment persisted and expected to remain The geo-political tensions due to the prolonged Russia-Ukraine and recent Middle East conflicts, US-China rivalry as well as global economic uncertainties have resulted in the following industry challenges and market outlook: Prolonged

  6. Slide 6: Conventional and renewable energy business activities are picking up in parallel

    Slide 6: Conventional and renewable energy business activities are picking up in parallel

    [Open] Conventional and renewable energy business activities are picking up in parallel Stable oil prices over the past three months due to tighter global supply and potential extended OPEC+ restrictions are expected to boost capital expenditure on upstream activities in 2024, while the growth in lo

  7. Slide 7: Business Highlights

    Slide 7: Business Highlights

    BUSINESS HIGHLIGHTS

  8. Slide 8: Encouraging start for the year as MHB recorded profit in the first quarter

    Slide 8: Encouraging start for the year as MHB recorded profit in the first quarter

    [Open] Encouraging start for the year as MHB recorded profit in the first quarter Achievements Financials Our plans for 2024 Heavy Engineering Continue contracting Revenue strategies improvement to Segment Successful mitigate challenging CPP Topside sail-away RM984.5 environment of SK408W Jerun Deve

  9. Slide 9: Ongoing Projects

    Slide 9: Ongoing Projects

    ONGOING PROJECTS

  10. Slide 10: EPCIC SK408W Jerun Development Project

    Slide 10: EPCIC SK408W Jerun Development Project

    [Open] Progress was at 93% as of March 2024 EPCIC SK408W Jerun Development Project Client & Field Operator Sapura OMV Upstream Location SK408W, Offshore Bintulu, Sarawak CPP Topside Sail-away in February 2024 Note: Engineering, Procurement, Construction, Installation and Commissioning (EPCIC) Page 1

  11. Slide 11: EPC Rosmari-Marjoram Project

    Slide 11: EPC Rosmari-Marjoram Project

    [Open] Progress was at 86% as of March 2024 EPC Rosmari-Marjoram Project Client & Field Operator Sarawak Shell Location SK318, Offshore Sarawak Note: Engineering, Procurement and Construction (EPC) Page 11 11

  12. Slide 12: EPCIC Kasawari Carbon Capture & Storage (CCS) Project

    Slide 12: EPCIC Kasawari Carbon Capture & Storage (CCS) Project

    [Open] Progress was at 37% as of March 2024 EPCIC Kasawari Carbon Capture & Storage (CCS) Project Client & Field Operator PETRONAS Carigali Location SK316, Offshore Sarawak Note: Engineering, Procurement, Construction, Installation and Commissioning (EPCIC) Page 12 12

  13. Slide 13: EPCI Joint Development Area (JDA) Field Development Project (Phase 6)

    Slide 13: EPCI Joint Development Area (JDA) Field Development Project (Phase 6)

    [Open] Progress was at 35% as of March 2024 EPCI Joint Development Area (JDA) Field Development Project (Phase 6) Client & Field Operator Carigali-PTTEPI Operating Company (CPOC) Location Malaysia-Thailand Joint Development Area (MTJDA) Note: Engineering, Procurement, Construction and Installation (

  14. Slide 14: EPC OSS HVDC Platform for TenneT's 2GW Programme awarded in November 2023

    Slide 14: EPC OSS HVDC Platform for TenneT's 2GW Programme awarded in November 2023

    [Open] EPC OSS HVDC Platform for TenneT’s 2GW Programme awarded in November 2023 Scope EPC of OSS HVDC platform for IJmuiden ver Alpha Project, offshore wind farm Client & Field Operator Petrofac International (UAE) LLC Total Weight 40,000 MT Topside: 30,000 MT Overall Weight equivalent to Jacket :

  15. Slide 15: Notable marine repair projects delivered

    Slide 15: Notable marine repair projects delivered

    [Open] Notable marine repair projects delivered SERI CAMELIA PELITA ENERGY Client Client PT Jaya Samudra Karunia MISC Marine Shipping Type of vessel Type of vessel LNG Carrier (Moss) LNG Carrier (Mark III) Deadweight Deadweight 84,333 tonnage 10,951 tonnage Job scope Job scope Dry-docking and repair

  16. Slide 16: Financials

    Slide 16: Financials

    FINANCIALS

  17. Slide 17: MHB continued positive momentum supported by strong order book in hand

    Slide 17: MHB continued positive momentum supported by strong order book in hand

    [Open] Revenue MHB continued positive momentum supported by strong order book in hand Quarter-on-Quarter Lower revenue due to lower Figures in RM million Q1 2024 Q4 2023 Q1 2023 revenue from the Heavy Engineering segment Revenue 984.5 1,118.4 496.2 ​Higher PBT mainly contributed from the Marine segm

  18. Slide 18: Financial position remains intact

    Slide 18: Financial position remains intact

    [Open] Financial position remains intact Figures in RM million Assets 31 March 2024 31 December 2023 Non-Current Assets 1,794.5 1,797.9 Receivables 1,767.3 1,291.0 Cash & Bank 376.8 557.6 Inventories 3.1 2.8 Tax recoverable 1.1 0.0 Total 3,942.8 3,649.3 Liabilities & Equities Equity 1,277.8 1,267.3

  19. Slide 19: Robust backlog will sustain us until 2027

    Slide 19: Robust backlog will sustain us until 2027

    [Open] Robust backlog will sustain us until 2027 ORDER BOOK RM million neering 98. i g 2% avy En Marine RM5.4 billion 1.8% 6,220 6,324 March 2024 He 5,436 1,900 2,170 2020 2021 2022 2023 2024* Note: *As of March 2024 Page 19

  20. Slide 20: Environmental, Social & Governance

    Slide 20: Environmental, Social & Governance

    ENVIRONMENTAL, SOCIAL & GOVERNANCE

  21. Slide 21: Unwavering commitment to ESG reflected in our achievements

    Slide 21: Unwavering commitment to ESG reflected in our achievements

    [Open] Unwavering commitment to ESG reflected in our achievements Installation of rooftop solar panels with capacity of 24,220kg 290trees Environment 131 kWp planted at MMHE West Yard at MHB’s Pasir Gudang waste recycled from for the Yard in the Centre of Excellence offices and sites Garden project

  22. Slide 22: Strategic Focus

    Slide 22: Strategic Focus

    STRATEGIC FOCUS

  23. Slide 23: Continued pursuit of project delivery excellence and high quality order book

    Slide 23: Continued pursuit of project delivery excellence and high quality order book

    [Open] Continued pursuit of project delivery excellence and high quality order book with balanced portfolio Strategic Focus Achieve project Focus on high quality Balance between delivery excellence order book for traditional Oil & Gas and businesses Renewable Energy opportunities Heavy Engineering t

  24. Slide 24: Thank You

    Slide 24: Thank You

    | > I ii Zz 3 x :? & g

Source: Internet Archive copy of mhb.com.my

More decks from Malaysia Marine & Heavy Engineering Holdings Bhd.

All 35 Malaysia Marine & Heavy Engineering Holdings Bhd decks