Hmc Capital Limited · ASX:HMC
Hmc Capital — Corporate Update (March 2026)
12 slides from Hmc Capital's corporate update, Mar 31, 2026
Slide 1: Victorian Big Battery Site Visit Presentation (ASX Release)
ASX RELEASE 31 March 2026 VICTORIAN BIG BATTERY SITE VISIT PRESENTATION HMC Capital (ASX: HMC) provides the attached presentation which will be given to attendees of a site visit to the Victorian Big Battery today. For personal use only This announcement is authorised for release by the Company Secr
Slide 2: VBB & VBB2 Site Visit
For personal use only VBB & VBB2 Site Visit HMC Capital | Energy Transition 31 March 2026 0
Slide 3: Acknowledgement of Country
Acknowledgement of Country For personal use only HMC Capital acknowledges the Traditional Custodians of Country throughout Australia and celebrates their diverse culture and connections to land, sea and community. We pay our respect to their Elders past and present and extend that respect to all Abo
Slide 4: HMC Energy Transition Platform Management Team
HMC Energy Transition Platform Management Team HMC has assembled deep internal management capability with significant industry experience and track record developing, delivering and operating renewable energy projects in Australia Energy Transition Platform Management Team Presenting Today For perso
Slide 5: HMC's Energy Transition Platform Overview
HMC’s Energy Transition Platform Overview One of Australia’s largest renewable generation and storage portfolios Platform Highlights For personal use only Bulgana Wind Farm ▪ Top 10 Australian operating platform with 652 MW installed wind, solar & BESS capacity – FY25 operating asset EBITDA of $64m
Slide 6: HMC's Energy Transition Platform Overview
HMC’s Energy Transition Platform Overview Top 10 operating renewable energy portfolio in NEM. Diversified across four NEM states and strategically weighted towards storage assets Portfolio Overview Technology Lifecycle For personal use only Capacity Ops / (max) Dev Total Wind Solar BESS Operating as
Slide 7: Critical energy infrastructure in a highly strategic location on the grid
Victorian Big Battery Critical energy infrastructure in a highly strategic location on the grid Project location For personal use only 5
Slide 8: Project highlights
Victorian Big Battery Project highlights Project highlights Key project partners and roles For personal use only • Location: Geelong, Victoria – with a footprint smaller than the football oval at Geelong’s GMHBA Stadium OEM and long-term service provider • Capacity: 300 MW / 470 MWh – enough to powe
Slide 9: Tesla Megapack and Autobidder technology
Victorian Big Battery (cont’d) Tesla Megapack 1 and Autobidder technology Tesla Megapack technology Autobidder dispatch software For personal use only Battery Modules Actual and forecast State of Charge Actual and forecast Energy and FCAS Controls, Thermal AC main breaker, Actual and forecast manage
Slide 10: Moorabool BESS (VBB2) in focus
Moorabool BESS (VBB2) in focus Approved BESS Located Adjacent to the Victorian Big Battery Project highlights Project commentary and highlights For personal use only • Project has secured Development Approval • Located adjacent to the VBB, 13km north-west of Geelong and 64km 1,200 MWh Q4 2026 DA sou
Slide 11: Moorabool BESS (VBB2) development timetable
Moorabool BESS (VBB2) development timetable Project remains on track with clear pathway to operations Program Status For personal use only Land Tenure/Planning Approval Design/Grid Connection Construction Key Workstream Secured In progress Mid-FY27 VBB2- 300 MW (4 hours) CY 2026 CY 2027 CY 2028 Stat
Slide 12: Disclaimer
Disclaimer This presentation (Presentation) has been prepared by HMC Capital Limited (ACN 138 990 593) (“HMC Capital”) Summary information This Presentation contains summary information about the current activities of HMC Capital and its subsidiaries as at the date of this Presentation. The informat