Slide 1: Building South Australia's Infrastructure Gateway
South Australian Resources & Energy Investment Conference 20 April 2016 Central Eyre Iron Project Building South Australia’s Infrastructure Gateway
Slide 2: Cautionary Statements
Cautionary Statements Forward Looking Statements This announcement contains certain statements with respect to future matters which may constitute "forward-looking statements". Such statements are only predictions and are subject to inherent risks and uncertainties which could cause actual values, r
Slide 3: The Central Eyre Iron Project
The Central Eyre Iron Project
Slide 4: Mining and Ore Processing Operations
Mining and Ore Processing Operations
Slide 5: Multi-Use Infrastructure
Multi-Use Infrastructure RON ROAD
Slide 6: Strengthening the Team – Emerald Grain
Strengthening the Team – Emerald Grain
Slide 7: Strengthening the Team – Local Relationships
Strengthening the Team – Local Relationships
Slide 8: Strengthening the Team – China Railway Group
Strengthening the Team – China Railway Group
Slide 9: Strengthening the Team – China Railway Group
Strengthening the Team – China Railway Group
Slide 10: Strengthening the Team – China Railway Group
Strengthening the Team – China Railway Group
Slide 11: Strengthening the Team – China Railway Group
Strengthening the Team – China Railway Group
Slide 12: Strengthening the Team – Shandong Iron and Steel
Strengthening the Team – Shandong Iron and Steel
Slide 13: Shansteel and Iron Road and China Railway
Shansteel and Iron Road and China Railway
Slide 14: Identifying Additional Strength and Opportunity
Identifying Additional Strength and Opportunity
Slide 15: Operating Costs
Operating Costs (US$/dmt FOB) PFS Operating Cost US$55/t DFS US$44.33/t Optimisation Value Drive US$37.72/t US$35.38/t Accuracy and Confidence
Slide 16: Capital Requirements
Capital Requirements $600-800 million of targeted reductions
Slide 17: Key project partners established
Key project partners established CEIP has been de-risked over 8 years Project essential to South Australia’s prosperity “This project has the potential to transform the Eyre Peninsula” Premier Weatherill September 2015
Slide 18: Appendix 1 – CEIP Ore Reserve Summary
Appendix 1 Table 1 – CEIP Ore Reserve Summary Metric Tonnes Fe SiO2 Al2O3 Resource Classification (Mt) (%) (%) (%) Proved 2,131 15.55 53.78 12.85 Probable 1,550 14.40 58.58 12.64 Total 3,681 15.07 53.70 12.76 The Ore Reserves estimated for CEIP involving mine planning is based on and fairly represen
Slide 19: Appendix 2 – CEIP Global Mineral Resource
Appendix 2 Table 2 – CEIP Global Mineral Resource Tonnes Fe SiO2 Al2O3 P LOI Location Classification (Mt) (%) (%) (%) (%) (%) Measured 2,222 15.69 53.70 12.84 0.08 4.5 Murphy South/Rob Roy Indicated 474 15.6 53.7 12.8 0.08 4.5 Inferred 667 16 53 12 0.08 4.3 Boo-Loo/Dolphin Indicated 796 16.0 53.3 12
Slide 20: Appendix 3 – Agreements summary
Appendix 3 Tripartite agreement with China •3 party agreement to work towards joint development of the Central Eyre Iron Project •Builds upon existing agreements with CREC and ShanSteel Railway and ShanSteel •Working towards Final Investment Decision Strategic cooperation agreement •Agreement to exe