Slide 1: Fourth Quarter and Year-End 2012 Financial Results
Fourth Quarter and Year-End 2012 Financial Results NYSE: CDE | TSX: CDM February 21, 2013
Slide 2: Cautionary Statement
Cautionary Statement This presentation contains numerous forward-looking statements relating to Coeur’s silver and gold mining business, including estimated production data, expected operating schedules, results of operations, ore reserves and resources, expected capital costs and other expected ope
Slide 3: Acquisition of Orko Silver
Acquisition of Orko Silver An Attractive Asset Orko’s key asset, the La Preciosa project, is one of the largest undeveloped silver deposits in the world Long-life mine potential with compelling economics assuming open pit mine plan Large-scale development opportunity with significant exploration ups
Slide 4: La Preciosa Key Inputs
La Preciosa Key Inputs Mining costs of US$1.45/t Processing costs of US$17.25/t Open pit cutoff grade of 25 silver g/t Total open pit mineral silver resource estimate: Indicated: 29.6 million tonnes @ 104 g/t = 99m ounces Inferred: 47.7 million tonnes @86 g/t = 132m ounces Average mill recoveries of
Slide 5: La Preciosa Key Inputs
La Preciosa Key Inputs Coeur’s Assumptions 10,000 tpd leach processing facility Estimated capital expenditures: Initial: $300 - $500 million LOM Sustaining: $60 - $90 million Estimated LOM strip ratio: 14:1 Average estimated annual production 7-9 million ounces Estimated mine life: 19 years Source:
Slide 6: Anticipated Timetable/Next Steps
Anticipated Timetable/Next Steps PEA/43-101 Technical Report: 2Q 2013 Feasibility Study: 2014 Construction: 2015/2016 Expected Initial Production: 2H 2016 NYSE: CDE | TSX: CDM 36
Slide 7: Contact Information
Contact Information Head Office: Main Tel: Tickers: Website: 505 Front Avenue Coeur d’Alene, Idaho 83816-0316 (208) 667-3511 CDE: NYSE; CDM: TSX www.coeur.com Wendy Yang Vice President, Investor Relations wyang@coeur.com (208) 665-0345 Stefany Bales Director of Corporate Communications sbales@coeur.