Koninklijke Bam Groep Nv · EURONEXT:BAMNB

Koninklijke Bam Groep Nv — Royal BAM Group — Investor Day (April 2017)

84 slides from Koninklijke Bam Groep Nv's investor day presentation, Apr 6, 2017

  1. Slide 1: Capital markets event 2017

    Capital markets event 2017 Amsterdam, 6 April 2017

  2. Slide 2: Today's programme

    Royal BAM Group nv Today’s programme Strategy outline Rob van Wingerden – CEO Our people Rob Zuidema – Group HR Director Public private partnerships Chris Williams – Finance Director BAM PPP Stage gate tendering Erik Bax – COO Digital construction platform Rob van Kampen – Director BAM Startup Strat

  3. Slide 3: Strategy outline

    Strategy outline Rob van Wingerden – CEO

  4. Slide 4: Our mission and vision underpin the strategy

    Royal BAM Group nv Our mission and vision underpin the strategy … Building the present, creating the future Leading in Performance, Innovation, Sustainablility Mission Vision Why are we in business? Where do we want to be in 2020? We create sustainable environments that By 2020 we are recognised as

  5. Slide 5: Performance measures

    Royal BAM Group nv Performance measures Profit Planet People ROCE > 10% Net Positive Impact Safety IF < 3.5 Capital markets event | 6 April 2017 5

  6. Slide 6: Strategy execution Profit

    Royal BAM Group nv Strategy execution Profit Return on capital employed Trade working capital efficiency 15% 2.000 0% 0 10% 1.500 -2% -200 5% -4% -400 1.000 -6% 0% -600 -8% -5% 500 -10% -800 -10% 0 -12% -1.000 2014 2015 2016 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 2014 2015 2016 Capital employed Return on cap

  7. Slide 7: Strategy execution People & Planet

    Royal BAM Group nv Strategy execution People & Planet Safety CO2 Waste (IF) (kilotonnes) (kilotonnes) 7 300 250 6 250 200 5 4 200 150 3 2 150 100 1 0 100 50 2013 2014 2015 2016 2013 2014 2015 2016 2013 2014 2015 2016 Capital markets event | 6 April 2017 7

  8. Slide 8: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 Profit Planet People ‘Building the present, creating the future’ Focus Shape Create project business future portfolio portfolio portfolio Differentiating capabilities BAM’s unique culture Capital markets event | 6 April 2017 8

  9. Slide 9: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 Leading in Profit Planet Performance, People Innovation, Sustainablility ‘Building the present, creating the future’ Doing Doing Doing things better new better things things Focus Shape Create project business future portfolio portfolio portfolio We make Differe

  10. Slide 10: Unlock potential

    Royal BAM Group nv Unlock potential Scale Expertise Capital markets event | 6 April 2017 10

  11. Slide 11: Our people

    Our people Rob Zuidema – Group HR Director

  12. Slide 12: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 ‘Building the present, creating the future’ Focus Shape Create project business future portfolio portfolio portfolio Differentiating capabilities BAM’s unique culture Performance, Learning, Ownership and Capital markets event | 6 April 2017 Collaboration 12

  13. Slide 13: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 1 Capital markets event | 6 April 2017 13

  14. Slide 14: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 3 Capital markets event | 6 April 2017 14

  15. Slide 15: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 15 Capital markets event | 6 April 2017 15

  16. Slide 16: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 150 Capital markets event | 6 April 2017 16

  17. Slide 17: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 1,500 Capital markets event | 6 April 2017 17

  18. Slide 18: Royal BAM Group nv Capital markets event | 6 April 2017

    Royal BAM Group nv 20,000 Capital markets event | 6 April 2017 18

  19. Slide 19: Creating the multiplier effect

    Royal BAM Group nv Creating the multiplier effect ... my own experience Safety One company A/B testing International growth Strategic agenda embraced by Common language Tools, systems and leadership who lead and goals uniform processes by example Capital markets event | 6 April 2017 19

  20. Slide 20: Common language and goals

    Royal BAM Group nv Common language and goals Pro-active ownership “I take initiative to prevent Predictable performance rather than fix” “I deliver what I promise” Open collaboration “I share, so we all gain” Scalable learning “I ask, listen, and support, so that we learn collectively” Capital marke

  21. Slide 21: Tools, systems and uniform processes

    Royal BAM Group nv Tools, systems and uniform processes 15 Roadshows 85 project managers Monthly meeting cadence Safety first! > 1,500 colleagues reached participated since 2015 Roadshows PM Seminar MB Meetings World Safety Day Strategy newsflash Online dialogue with Strategy presentation to Focus i

  22. Slide 22: Strategy Action Results

    Royal BAM Group nv Strategy Action Results ‘Building the present, creating the future’ Profit Focus Shape Create 20,000 ` project business future portfolio portfolio portfolio Planet Differentiating capabilities BAM’s unique culture People Capital markets event | 6 April 2017 AMS

  23. Slide 23: Public private partnerships

    Public private partnerships Chris Williams – Finance Director BAM PPP

  24. Slide 24: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 ‘Building the present, creating the future’ Focus Shape Create project business future portfolio portfolio portfolio We make Differentiating capabilities it before we make it BAM’s unique culture Capital markets event | 6 April 2017 24

  25. Slide 25: Public private partnerships (1)

    Royal BAM Group nv Public private partnerships (1) Contracting Authority Advisers: Technical, Legal, Finance, Insurance Project Agreement Characteristics • Long term partnerships Equity Equity PPP Co Debt Senior provider Lenders • Private finance Advisers: Advisers: Legal, Finance, Technical, Legal,

  26. Slide 26: Public private partnerships (2)

    Royal BAM Group nv Public private partnerships (2) Gross Availability Payment Benefits • Solution to short term capital constraints Maintenance Opex • Public sector pays for availability CAPEX • Stimulates innovation through “whole life cost approach” • Value for Money Availability Completion End ce

  27. Slide 27: Overview BAM PPP

    Royal BAM Group nv Overview BAM PPP 31 5 Glasgow Operational Under Management 9 6 Kill Under Our Offices Construction Solihull Bunnik • RoE in 2016 > 12% • Recurring revenue Operations & Maintenance Brussels Frankfurt in excess of €100 million per year for BAM • Directors’ valuation portfolio €238 m

  28. Slide 28: BAM PPP role in BAM's strategy

    Royal BAM Group nv BAM PPP role in BAM’s strategy Differentiated & specialist activity Large multidisciplinary projects 01. 02. 03. Short term Long term Long term Entire project lifecycle construction operations / equity maintenance investment Digitalised construction and asset management Creating v

  29. Slide 29: Unique differentiating capability PGGM JV (1)

    Royal BAM Group nv Unique differentiating capability PGGM JV (1) Returns model PGGM returns € PGGM Equity 80% JV-Equity Equity stake bridge bridge repaid BAM PPP 20% Time Construction (~3y) Operations & Asset Management (~25y) BAM PPP € € returns Returns on BAM PPP 20% equity stake BAM PPP return pr

  30. Slide 30: Unique differentiating capability PGGM JV (2)

    Royal BAM Group nv Unique differentiating capability PGGM JV (2) Benefits Project cash flows ( € million) • Exclusive access to equity to support the 80 PPP bid pipeline 70 • Cost efficient structure 60 50 Success • Initial commitment €240 million 40 • Current commitment €775 million 30 20 10 2011 2

  31. Slide 31: Unique differentiating capability PGGM JV (3)

    Royal BAM Group nv Unique differentiating capability PGGM JV (3) Capital markets event | 6 April 2017 31

  32. Slide 32: Refinancing – creating value

    Royal BAM Group nv Refinancing – creating value Pre and Post Refinancing Shareholder Cashflows (€ million) • Cash flow improvements 20 • BAM PPP’s 20% investment 18 1.5 mln • BAM PPP - Project management fees 16 14 • BAM PPP - Financial advisory fees 12 10 8 6 4 2 Dec ´16 Dec ´20 Dec ´24 Dec ´28 Dec

  33. Slide 33: BAM PPP prospects

    Royal BAM Group nv BAM PPP prospects 10 28 Active Bids Imminent Bids Strong pipeline of investment opportunities Europe needs €1.5 - €2 trillion of infrastructure investments by 2020* * Source: Freshfields Bruckhaus Deringer LLP Capital markets event | 6 April 2017 33

  34. Slide 34: Our capabilities in PPP

    Royal BAM Group nv Our capabilities in PPP People Partnerships Performance Bid Win Ratio (since BAM PPP inception in 2005) 41% Capital markets event | 6 April 2017 Sea lock, IJmuiden, the Netherlands 34

  35. Slide 35: Stage gate tendering

    Stage gate tendering Erik Bax – COO

  36. Slide 36: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 ‘Building the present, creating the future’ Doing things better Focus Shape Create project business future portfolio portfolio portfolio Differentiating capabilities BAM’s BAM’s unique unique culture culture Capital markets event | 6 April 2017 36

  37. Slide 37: Focus project portfolio drives margin improvement

    Royal BAM Group nv Focus project portfolio … drives margin improvement • Focus on projects where we can use 2016 - 2020 scale or expertise to win • Improving order book quality Σ project results Average margin in 2-4% range Focus More predictable outcome Σ projects Capital markets event | 6 April 20

  38. Slide 38: Implementation of data driven tendering

    Royal BAM Group nv Implementation of data driven tendering Tender selection Sales funnel Tendering Execution CRM systems Stage gate database Project database Feedback Capital markets event | 6 April 2017 38

  39. Slide 39: Stage gate tendering

    Royal BAM Group nv Stage gate tendering Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 39

  40. Slide 40: Categorisation determines governance

    Royal BAM Group nv Categorisation determines governance Risk Governance Number of Category Stage gates & Control Tenders Exposure A Executive Board B COO C OpCo D BU Capital markets event | 6 April 2017 40

  41. Slide 41: Categorisation criteria

    Royal BAM Group nv Categorisation criteria Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 41

  42. Slide 42: Categorisation

    Royal BAM Group nv Categorisation • Contract value • Contract type • Our experience • Logistics • Organisational complexity • Ground conditions • Permits • Client track record & relationship Capital markets event | 6 April 2017 42

  43. Slide 43: Stage gate 1

    Royal BAM Group nv Stage gate 1 Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 43

  44. Slide 44: Decision to tender

    Royal BAM Group nv Decision to tender • Health, Environment and Safety • Client track record & relationship • Strategy to win • Track record project team • Type of bid: price only or price & quality • Anticipated contract terms • Funding and expected cash flow • Joint venture & supply chain partners

  45. Slide 45: Stage gate 2

    Royal BAM Group nv Stage gate 2 Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 45

  46. Slide 46: Validation to Tender

    Royal BAM Group nv Validation to Tender • Ground conditions • Permits • Contract terms • Pre qualified competition • Bonding requirements • Experience tender team • Lessons learnt from other projects • Decide for peer review • Decide for tender assessment Capital markets event | 6 April 2017 46

  47. Slide 47: Stage gate 3

    Royal BAM Group nv Stage gate 3 Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 47

  48. Slide 48: Decision to bid

    Royal BAM Group nv Decision to bid • Project margin • Cash flow • Risk & opportunity profile • Experience project team • Supply chain • Time table • Quality tender • Project planning • Insurance & bank guarantees Capital markets event | 6 April 2017 48

  49. Slide 49: Stage gate 4

    Royal BAM Group nv Stage gate 4 Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 49

  50. Slide 50: Approval final contract

    Royal BAM Group nv Approval final contract • Only if changes to set of conditions agreed in stage gate 3 Capital markets event | 6 April 2017 50

  51. Slide 51: Stage gate 5

    Royal BAM Group nv Stage gate 5 Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6 April 2017 51

  52. Slide 52: Quality assurance options

    Royal BAM Group nv Quality assurance options Peer Tender Operational review assessment audit Stage gate 1 Stage gate 2 Stage gate 3 Stage gate 4 Stage gate 5 Categorisation Decision Validation Decision Approval If won: to tender to Tender to bid final contract Reality check Capital markets event | 6

  53. Slide 53: Peer review

    Royal BAM Group nv Peer review • Knowledge sharing • Critical friend Characteristics • Tender team • Tender desk • BAM 'wide' experts Participants • 1-2 day meetings • Reporting to tender Execution manager Capital markets event | 6 April 2017 53

  54. Slide 54: Tender assessment

    Royal BAM Group nv Tender assessment • Independent check • Focus on high risk areas Characteristics • Tender team • Tender desk Participants • BAM ‘wide’ experts • Deep dive (~1 - 3 days) • Report to the Executive Execution Board Capital markets event | 6 April 2017 UK Antarctica research facilities

  55. Slide 55: Operational audit

    Royal BAM Group nv Operational audit • Independent check • Execution tender plan • Size & quality team Characteristics • Control high risk areas • Project team • Operational auditor Participants • BAM ‘wide’ experts • Selected A & B projects • Deep dive (~1 - 3 days) Execution • Report to Executive

  56. Slide 56: Quality order book is improving

    Royal BAM Group nv Quality order book is improving • Better project selection • Improving cash flow • Higher tender efficiency • Pricing identified risks • Understanding design, technical solutions and execution methods • Contractual awareness • Average margin on new order intake in 2016 within 2-4%

  57. Slide 57: Digital construction platform

    Digital construction platform Rob van Kampen – Director BAM Startup

  58. Slide 58: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 ‘Building the present, creating the future’ Doing new things Focus Shape Create project business future portfolio portfolio portfolio Differentiating capabilities BAM’s BAM’s unique unique culture culture Capital markets event | 6 April 2017 58

  59. Slide 59: Create future portfolio

    Royal BAM Group nv Create future portfolio Digital construction process Digital built environment Capital markets event | 6 April 2017 59

  60. Slide 60: Digital construction process

    Royal BAM Group nv Digital construction process Add digital Start digital Capital markets event | 6 April 2017 60

  61. Slide 61: The story of the BAM Startup

    Royal BAM Group nv The story of the BAM Startup Capital markets event | 6 April 2017 61

  62. Slide 62: How the construction industry works today

    Royal BAM Group nv How the construction industry works today Capital markets event | 6 April 2017 62

  63. Slide 63: Industry is reluctant to innovate and slow to improve

    Royal BAM Group nv Industry is reluctant to innovate and slow to improve The annual Large projects And take 51% R&D spending in productivity growth are typically construction industry only increased 1% 80% 20% 40% <1% over the past 20 over budget longer to finish 25% years Source: McKinsey&Company,

  64. Slide 64: BAM Startup at the edge of BAM

    Royal BAM Group nv BAM Startup at the edge of BAM Capital markets event | 6 April 2017 Startup in B.Amsterdam 64

  65. Slide 65: BAM's digital transformation: an integrated multi-stakeholder approach

    Royal BAM Group nv BAM’s digital transformation: an integrated multi-stakeholder approach Capital markets event | 6 April 2017 65

  66. Slide 66: Digital co-makers: partnering to grow

    Royal BAM Group nv Digital co-makers: partnering to grow Capital markets event | 6 April 2017 66

  67. Slide 67: We are creating a digital platform

    Royal BAM Group nv We are creating a digital platform We make it digital before we make it physical! Capital markets event | 6 April 2017 67

  68. Slide 68: Think Big, Act Small and Scale-up Fast

    Royal BAM Group nv Think Big, Act Small and Scale-up Fast Roadmap and investment • Start with 1 kitchen in April • Scale up to 50 kitchens • Renovate entire house €1,500,000 Facade Building services €500,000 Roof Bathroom MVP House Capital markets event | 6 April 2017 68

  69. Slide 69: Think Big, Act Small and Scale-up Fast

    Royal BAM Group nv Think Big, Act Small and Scale-up Fast Step 1 Step 2 Step 3 Step 4 51% Kitchen Entire Block of Neighbourhoods renovation house houses Capital markets event | 6 April 2017 69

  70. Slide 70: Creating value

    Royal BAM Group nv Creating value Shareholders Profit Clients ` Supply chain ROCE Planet Employees Society People Capital markets event | 6 April 2017 70

  71. Slide 71: BAM Startup: Let's create the future together

    Royal BAM Group nv BAM Startup: Let’s create the future together Capital markets event | 6 April 2017 71

  72. Slide 72: From unimaginable unpredictable to imaginable predictable

    Royal BAM Group nv From unimaginable unpredictable to imaginable predictable Capital markets event | 6 April 2017 72

  73. Slide 73: Strategy in action

    Strategy in action George Mazloumian – MD BAM International

  74. Slide 74: Strategy 2016-2020

    Royal BAM Group nv Strategy 2016-2020 ‘Building the present, creating Performance, the future’ Leading in Innovation, Sustainablility Doing Doing Doing things better new better things things Focus Shape Create project business future portfolio portfolio portfolio We make Differentiating capabilities

  75. Slide 75: BAM International has a long-standing track record of worldwide construction

    Royal BAM Group nv BAM International has a long-standing track record of worldwide construction Currently Active BAM International Area Office BAM International Office Head Office the Netherlands ... and uses that experience to pursue a diversification from near-shore expert to on-shore innovative s

  76. Slide 76: Near-shore marine infrastructure has been pivotal for BAM International

    Royal BAM Group nv Near-shore marine infrastructure has been pivotal for BAM International, strongly driven by resources … APM Container Terminal, Moín, Phase 2A - Costa Rica, APM Terminals Jebel Ali Terminal 4 Phase 1, United Arab Emirates, DP World Quay wall Limbe Shipyard, Cameroon, Cameroon Ship

  77. Slide 77: BAM International diversification strategy

    Royal BAM Group nv BAM International diversification strategy From near-shore expert to on-shore innovative specialist Focus project portfolio Shape business portfolio Create future portfolio Diversification Strengthened business development Innovative through Rigid tender selection (digital) client

  78. Slide 78: Focusing the portfolio by using differentiating capabilities

    Royal BAM Group nv Focusing the portfolio by using differentiating capabilities Sales funnel Tendering Execution CRM systems Stage gate database Project database +35% -8% Differentiation Strict control Client focus Partnering & BIM Capital markets event | 6 April 2017 78

  79. Slide 79: Shaping the project portfolio by open collaboration

    Royal BAM Group nv Shaping the project portfolio by open collaboration and leveraging on BAM’s capabilities Products & enablers Capatalise on capabilities First successes • Metro Tunnel tender (AUS) • Hospital project and tenders in and outside Europe (UK, IRE, DK, global) 1+1>2 • Stadium project an

  80. Slide 80: Creating the future portfolio by delivering cutting edge digital solutions

    Royal BAM Group nv Creating the future portfolio by delivering cutting edge digital solutions to our clients Capital markets event | 6 April 2017 80

  81. Slide 81: We make it before we make it

    Royal BAM Group nv We make it before we make it Museum of the Future Movie We make it before we make it Capital markets event | 6 April 2017 81

  82. Slide 82: The future is bright!

    Royal BAM Group nv The future is bright! BAM provides innovative digital solutions to its global clients by open collaboration and leveraging on its capabilities Capital markets event | 6 April 2017 82

  83. Slide 83: Q&A

    Q&A

  84. Slide 84: Wrap up

    Wrap up Rob van Wingerden – CEO