Slide 1: Building a Multi-Asset +5Moz Western Australian Gold Producer
rsonal use only Building a Multi-Asset +5Moz Western Australian Gold Producer 2026 Annual General Meeting NOVEMBER 2026 ASX : BTR

Slide 2: Important Notices & Disclaimers
Important Notices & Disclaimers Important Notices • This presentation (Presentation) has been prepared by Brightstar and has been authorised for release by the Board of Directors of Brightstar on the basis it is to be read in conjunction with these important notices and disclaimers. • This Presentat

Slide 3: Important Notices & Disclaimers
Important Notices & Disclaimers Not Investment Advice • Each recipient of the Presentation should make its own enquiries and investigations regarding all information in this Presentation including but not limited to the assumptions, uncertainties and contingencies which may affect future operations

Slide 4: Investment Highlights
INVESTMENT HIGHLIGHTS WA gold developer | 5.2Moz in Mineral Resources | Two production hubs Goldfields first gold June 2027 with Sandstone to deliver scale; targeting Top 10 Australian gold producer1 Goldfields rsonal use only Near-term production: first gold targeted June 20273 Mineral Resource2 1.

Slide 5: Corporate Snapshot
CORPORATE SNAPSHOT Team & funding in place – platform for major production growth SHAREHOLDERS SHARE PRICE MARKET CAP NET CASH1 AVAILABLE, UNDRAWN DEBT $0.56 $712M $137M US$73M rsonal use only 7% 6% (AUD) at 23 November 2026 1,272M shares on issue Sep’26 quarterly Nordic Bond 5% REVENUE PROTECTION E

Slide 6: Sandstone Project
Visible Gold in Two Mile Hill diamond core (TMHRCD26020) rsonal use only Sandstone Project Emerging district-scale Western Australian gold development

Slide 7: The Sandstone Value Proposition
SANDSTONE PROJECT The Sandstone Value Proposition Emerging district-scale WA gold development opportunity Current MRE: 3.6Moz @ 1.4g/t Au, 1.5Moz Indicated1 rsonal use only Tier 1 jurisdiction District-scale development opportunity Granted Mining Leases Existing processing plant site +90% metallurgi

Slide 8: Critical Mass for development
SANDSTONE PROJECT Critical Mass for development Existing Mineral Resource of 3.6Moz Au provides critical mass for PFS evaluation and future development 1 Scale for development delivered: rsonal use only ▸ Current Mineral Resource provides sufficient scale for feasibility studies, permitting/approval

Slide 9: Delivering on a district-scale opportunity
SANDSTONE PROJECT Delivering on a district-scale opportunity Emerging district-scale WA gold development opportunity Milestone Completed rsonal use only Calendar Year 2026 2027 2028 Quarter MarQ JunQ SepQ DecQ MarQ JunQ SepQ DecQ MarQ JunQ SepQ DecQ Infill Drilling MRE upgrade Drilling Growth & Gree

Slide 10: Major Discovery at Depth Two Mile Hill
SANDSTONE PROJECT Major Discovery at Depth Two Mile Hill Significance of discovery confirmed by interim September 2026 MRE upgrade ahead of further group MRE upgrade in December 2026 1 DISCOVERY AT DEPTH: THE ‘SHIRVINGTON ZONE’ rsonal use only Material upside to the current Two Mile Hill Mineral Res

Slide 11: Interim Two Mile Hill MRE Upgrade
SANDSTONE PROJECT Interim Two Mile Hill MRE Upgrade Two Mile Hill MRE doubles to 1.45Moz @ 1.8g/tAu Indicated Inferred Total rsonal use only Cut-off Deposit (g/t Au) kt g/t Au koz kt g/t Au koz kt g/t Au koz Two Mile Hill open pit 0.4 2,252 1.2 87 308 0.9 9 2,560 1.2 96 Two Mile Hill underground 0.7

Slide 12: 1.5Mtpa Laverton Plant Construction
1.5Mtpa Laverton Plant Construction rsonal use only Goldfields Project Pathway to +75koz p.a. – Construction underway | First gold June 2027

Slide 13: 1.5Mtpa Laverton Plant advancing on schedule
GOLDFIELDS PROJECT 1.5Mtpa Laverton Plant advancing on schedule rsonal use only 13

Slide 14: De-risked development pathway – Seven months to first gold
GOLDFIELDS PROJECT De-risked development pathway – Seven months to first gold 1.5Mtpa processing plant under construction to unlock existing 1.6Moz @ 1.6g/t Au Mineral Resource 1 SIMPLIFIED BUSINESS MODEL rsonal use only Staged open pit and underground operations ▸ Operating model: One OP provides b

Slide 15: 1.5Mtpa Laverton Plant advancing on schedule
GOLDFIELDS PROJECT 1.5Mtpa Laverton Plant advancing on schedule1 Fixed-price EPC contract de-risks the construction phase ▸ Conventional 1.5Mtpa CIL plant with embedded engineering rsonal use only for expansion to 2.5Mtpa during operations ▸ Expansion case provides optionality for future mine expans

Slide 16: Gold pouring in eight months
GOLDFIELDS PROJECT Gold pouring in eight months First Gold targeted in June 2027 Potential Completed Calendar Year 2026 2027 rsonal use only Quarter MarQ JunQ SepQ DecQ MarQ JunQ SepQ DecQ Goldfields DFS 2.0 Studies & Funding Execution Funding Final Investment Decision (FID) MDCP Plant Approval Appr

Slide 17: DFS2.0 economics demonstrates a robust development case
GOLDFIELDS PROJECT DFS2.0 economics demonstrates a robust development case1 A high-margin, short-payback development with demonstrable mine life extension opportunities rsonal use only PRE-TAX NPV₈ PRE-TAX IRR LOM FREE CASH FLOW $454M 58% ~$0.8B A$5,500/oz Strong return on capital Over 6 years, undi

Slide 18: Brightstar's Market Position
Lady Shenton Open Pit rsonal use only Brightstar's Market Position An unparalleled opportunity

Slide 19: A robust platform to build a mid-tier Western Australian gold miner
BRIGHTSTAR’S MARKET POSITION A robust platform to build a mid-tier Western Australian gold miner A successful track record in M&A combined with aggressive exploration has placed Brightstar at the top end of the advanced developers and emerging producers with genuine multi-asset production scale pote

Slide 20: Undemanding valuation on every resource and reserve metric
BRIGHTSTAR’S MARKET POSITION Undemanding valuation on every resource and reserve metric¹ Brightstar EMERGING PRODUCER PEERS ESTABLISHED PRODUCER PEERS EXPLORER / DEVELOPER PEERS Resources Limited Black Cat Forrestania Pantoro Gold Ora Banda Catalyst Metals Minerals 260 Rox Resources rsonal use only

Slide 21: Limited mid-tier producers with scale of >200koz p.a.
BRIGHTSTAR’S MARKET POSITION Limited mid-tier producers with scale of >200koz p.a. M&A has diminished the pipeline of emerging producers with +200koz p.a. production potential Annualised Production (koz p.a.)¹ rsonal use only Northern Star 1,575 Evolution 695 Westgold 405 Regis 380 TARGET200 puts BT

Slide 22: Platform set for sustained growth
SUMMARY Platform set for sustained growth Advancing a multi-hub production growth - Tier-1 jurisdiction, 5.2Moz Au on granted Mining Licenses rsonal use only 1 GOLDFIELDS DEVELOPMENT 2 SANDSTONE TO DELIVER SCALE 3 EXPERIENCED TEAM ▸ Processing infrastructure construction underway. ▸ Additional MRE u

Slide 23: Appendices
Montague Open Pit rsonal use only Appendices

Slide 24: Experienced team in place to execute
LEADERSHIP Experienced team in place to execute BOARD OF DIRECTORS MANAGEMENT TEAM rsonal use only Richard Crookes Geologist · Finance · 35+ yrs Nicky Martin Finance · CPA · 20+ yrs Katherine Hughes Human Resources · 15+ yrs Non-Executive Chairman Chief Financial Officer Chief Human Resources Office

Slide 25: +75koz p.a. from a consolidated Laverton processing strategy
GOLDFIELDS PROJECT +75koz p.a. from a consolidated Laverton processing strategy1 Yielding ~$1.0B of pre-tax free cash flow² at A$6,000/oz over a six-year mine life Group Production (koz) 78 79 77 rsonal use only 80 75 76 Goldfields DFS 2.0 Unit Laverton Menzies Total 67 Key Production Outcomes² 60 O

Slide 26: Lord Byron Open Pit
GOLDFIELDS PROJECT Lord Byron Open Pit Oblique view of the Lord Byron open LORD BYRON OPEN PIT pit design with Mineral Resource block model (coloured by grade) JORC Mineral Resource of 5.4Mt @ 1.5g/t Au for 267koz Au1 rsonal use only Fully approved for mining operations to commence Two small histori

Slide 27: Cork Tree Well Open Pit
LAVERTON MINE Cork Tree Well Open Pit Oblique view of the Cork Tree Well open pit designs with Mineral Resource CORK TREE WELL OPEN PIT block model (coloured by grade) JORC Mineral Resource of 6.5Mt @ 1.4g/t Au for 292koz Au1 rsonal use only Mining to commence 2030 2.5 year mine life based on curren

Slide 28: Lady Shenton Open Pit
GOLDFIELDS PROJECT Lady Shenton Open Pit Oblique view of the Lady Shenton open LADY SHENTON OPEN PIT pit designs with Mineral Resource block model (coloured by grade) JORC Mineral Resource of 8.1Mt @ 1.4g/t Au for 352koz Au1 rsonal use only Fully approved for mining operations to commence Mining to

Slide 29: Yunndaga Underground
GOLDFIELDS PROJECT Yunndaga Underground Oblique view of the Yunndaga YUNNDAGA UNDERGROUND underground mine design with Mineral Resource block Set to be Brightstar’s next underground mine rsonal use only model (coloured by grade) JORC Mineral Resource of 3.1Mt @ 2.1g/t Au for 206koz Au1 (inclusive of

Slide 30: Appendix 1: Brightstar's Impressive M&A Track Record
APPENDIX Appendix 1: Brightstar’s Impressive M&A Track Record Comparable transactions for Western Australian pre-production gold assets - acquisition cost, A$/ounce BTR Transaction Non-BTR Transaction rsonal use only 664 642 568 400 EV / Resource ounce (A$/oz) 324 317 282 253 219 207 204 200 176 160

Slide 31: Appendix 2: Goldfields Mineral Resources
APPENDIX Appendix 2: Goldfields Mineral Resources LAVERTON Cut-off Measured Indicated Inferred Total rsonal use only g/t Au kt g/t Au koz kt g/t Au koz kt g/t Au koz kt g/t Au koz Alpha 0.5 - - - 371 1.9 22 1,028 2.8 92 1,399 2.5 115 Beta 0.5 345 1.7 19 576 1.6 29 961 1.7 54 1,882 1.7 102 Cork Tree

Slide 32: Appendix 3: Sandstone Mineral Resources
APPENDIX Appendix 3: Sandstone Mineral Resources Location Cut-off Measured Indicated Inferred Total rsonal use only g/t Au kt g/t Au koz kt g/t Au koz kt g/t Au koz kt g/t Au Koz Montague-Evermore 0.4 - - - 1,683 2.1 114 3,122 1.3 127 4,805 1.6 241 Whistler 0.4 - - - 1,258 2.0 79 565 1.4 25 1,823 1.

Slide 33: Appendix 4: Ore Reserves
APPENDIX Appendix 4: Ore Reserves Location Proved Probable Total rsonal use only Goldfields Ore Reserves1 kt g/t Au koz kt g/t Au koz kt g/t Au koz Cork Tree Well Open Pit (Laverton) - - - 2,137 1.5 104 2,137 1.5 104 Lord Byron Open Pit (Laverton) 308 1.6 15 1,530 1.4 68 1,838 1.4 83 Lady Shenton Op

Slide 34: Appendix 5: Comparable Transaction Data
APPENDIX Appendix 5: Comparable Transaction Data Resource Enterprise Value¹ Mineral Resource Acquiror Target Project Stage Ann. Date Multiple ASX Release Title (A$m) (koz Au) (A$/oz Au) Ramelius Resources Spartan Resources Resource Development Mar-25 2,094 3,152 664 Transformation Combination of Ram

Slide 35: Appendix 6: Peer Mineral Resource References
APPENDIX Appendix 6: Peer Mineral Resource References¹ Total Plant Market Enterprise EV/ EV/ EV/ Proved Probable Grade Production Ticker Company Stage Reserve Capacity Source & Date Cap Value Resource Reserve Production (koz) (koz) (g/t) (koz/year) (koz) (Mtpa) ($M) ($M) ($/oz) ($/oz) ($/oz) rsonal

Slide 36: Appendix 7: Peer Annualised Production References
APPENDIX Appendix 7: Peer Annualised Production References Annualised Production Ticker Company Source & Date (koz p.a.) rsonal use only NST Northern Star Resources 1,575(g) FY26 Financial Results (20 August 2026) EVN Evolution Mining 695(g) FY26 Full Year Financial results and Final Dividend (19 Au

Slide 37: Appendix 8: Peer WA Gold Developers – Resource vs Grade
APPENDIX Appendix 8: Peer WA Gold Developers – Resource vs Grade¹ Grade Enterprise Value EV/ Resource Ticker Company Total Resource (koz) Source & Date (g/t) ($M) ($/oz) rsonal use only MI6 Minerals260 6,200 1.0 September 2026 Quarterly Activities and Cashflow Report (27 October 2026) 1,174 189 AZY
Source: ASX announcement, Nov 24, 2026
More decks from Brightstar Resources Limited
North American Conference Presentation September 202637 slides · Sep 28, 2026
Diggers and Dealers (August 2026)38 slides · Aug 5, 2026
Investor Presentation (July 2026)38 slides · Jul 16, 2026
RIU Sydney Conference (May 2026)35 slides · May 6, 2026
Investor Presentation (March 2026)34 slides · Mar 18, 2026
RIU Explorers Conference 202633 slides · Feb 18, 2026