Slide 1: 2026 AGM
personal use only ASX:PNR 2026 AGM

Slide 2: Important Notes
Important Notes personal use only Nature of Document. This presentation has been prepared and issued by Pantoro Limited (Pantoro or Company) to Forward Looking Statements and future performance This presentation contains forward looking statements about provide general information about Pantoro. Pan

Slide 3: Important Notes (Continued)
Important Notes (Continued) personal use only Past performance. Past performance metrics and figures (including past share price performance of Pantoro), as For the purposes of ASX Listing Rule 5.19, Pantoro confirms that all material assumptions underpinning the well as pro forma financial informat

Slide 4: Corporate Overview
Corporate Overview personal use only A highly experienced Board and Executive Leadership Team, coupled with a simple capital structure Corporate Profile Capital Structure Board of Directors As at 23 November 2026 Share price $/sh 2.98 1 Paul Cmrlec Managing Director and CEO Fully-diluted shares on i

Slide 5: FY2026 Outcomes
FY2026 Outcomes personal use only Norseman is one of the highest-grade operations in Australia and has significant exploration upside Operational Outcomes Disciplined, cash flow-focused • Gold production of 77,600 ounces, below expectations. • Revenue increased 34.6% to $480.7 million. • Difficult l

Slide 6: Operations
personal use only Operations x

Slide 7: Norseman is a simple production story
Norseman is a simple production story personal use only A single processing facility, supported by high grade ore sources forming a large 4.7Moz Mineral Resource High grade ore sources processed at a central production facility Production underpinned by a large Resource base 90-105 koz1 A$2,800-3,40

Slide 8: Dominant Regional Position
Dominant Regional Position personal use only Focused on maintaining operational discipline with a goal to constantly improve and grow output Operating King of the Hills Laverton Granny Smith High grade mining fronts • Four producing deposits in Scotia, OK, Gladstone and Green Lantern. • All ore sour

Slide 9: 6Moz Au produced from Norseman tenure to date
6Moz Au produced from Norseman tenure to date personal use only WORLD-CLASS GREENSTONE BELT HIGHLY PROSPECTIVE GEOGRAPHY SIGNIFICANT EXPLORATION UPSIDE Pantoro Gold’s tenure is situated in the southern end The area south of Kambalda is highly prospective, Pantoro Gold’s Norseman tenure is a signific

Slide 10: Multiple producing areas feed the Norseman mill
Multiple producing areas feed the Norseman mill personal use only Pantoro is progressing mine development and drilling across the Norseman tenement package • Processing is currently running comfortably above 800 km2 Hinemoa Norseman Processing Processing 1.2Mtpa nameplate with excellent recovery of

Slide 11: Pathway to 200koz production
Pathway to 200koz production personal use only Through organic development of existing ore sources, unlocking higher feed grades and prioritising cash flow, Pantoro remains on track to deliver its long-term aspirational targets 2026 2027 Long-term Deliver on guidance Optimise mill capacity Become a

Slide 12: Processing plant recoveries remain very strong
Processing plant recoveries remain very strong personal use only Norseman annual production (koz, recovered) Sensitivity on grade and processing rate Power Station Crushing Circuit 1.2Mtpa 1.5Mtpa CIL Tanks ~200kozpa target achieved 367 321 293 275 257 229 220 206 Mill 183 183 160 165 137 128 147 11

Slide 13: OK Underground Mine
OK Underground Mine personal use only • Ore Reserve has increased every year since mining commenced, despite ongoing depletion • Producing in steady state • Large extensional exploration drilling program underway and set to continue OK for all of FY27 • Drilling extensions in both the Star of Erin a

Slide 14: Off to the Races……
Off to the Races…… personal use only High-grade zone expanded by ongoing drilling Discovery of high-grade ore at Racetrack • 0.49 m @ 2,726.49 g/t Au. • 4.52 m @ 64.65 g/t Au inc. 3.12 m @ 93.1 g/t Au. • 2.65 m @ 33.48 g/t Au inc. 0.3m 282.8 g/t Au. • 4.94 m @ 349.14 g/t inc. 0.91 @ 1,737.37 g/t and

Slide 15: Off to the Races……
Off to the Races…… personal use only High-grade zone expanded by ongoing drilling Bullen Mine produced approximately 500,000 Oz @ 10g/t Long section of Racetrack drilling with Bullen development overlaid for scale • Racetrack is a cross-linking structure with analogues to the Bullen deposit. Plan vi

Slide 16: Scotia Underground Mine
Scotia Underground Mine personal use only • Development of the South decline commenced May 2024 • Historic decline now rehabilitated providing two mine accesses • Now actively developing and producing ore from 3 areas for the first time – Central Scotia, Scotia Additional development Scotia and prod

Slide 17: Gladstone – Daisy Mining Area
Gladstone – Daisy Mining Area personal use only • Gladstone lies approximately 8 km East of the Norseman processing plant • GEV mining area Schedule now 526,000t @ 3.42 g/t Au for 58,000 oz with inclusion of Stage 3. Gladstone • Approximately 20,000 ounces in FY27 with remainder in FY28 and FY29. •

Slide 18: Green Lantern Open Pit
Green Lantern Open Pit personal use only • Clearing completed and grade control drilling well under-way. • Mining commenced during August 2026. • Long-life lower grade open pit providing high volume mill feed and ore stockpiles to secure Scotia Pit production profile. Green Lantern Stage 1 (Complete

Slide 19: Mainfield – Major Growth Opportunity
Mainfield – Major Growth Opportunity personal use only Mainfield is the most prolific mining area at Norseman Crown/ to date Mararoa St Pats • Initial mining areas focused on zones easily accessed from existing infrastructure. Mainfield • Very high-grade mineralisation encountered by 6km Crown Panto

Slide 20: Mainfield Plan View
Mainfield Plan View personal use only 1 ,7 50m O pen 350m 300m Open 1700m 20

Slide 21: Phoenix Development
Phoenix Development personal use only 21

Slide 22: Crown Reef – historical production 1.1 Moz @ 11.2g/t
Crown Reef – historical production 1.1 Moz @ 11.2g/t personal use only Longview of Crown Reef Refer to ASX release on 31 July 2021 for further details. 22

Slide 23: Greenfield Exploration Underway
Greenfield Exploration Underway personal use only Opportunities over 2km of strike • On Lake exploration has been extremely limited in Norseman with a short Hinem oa campaign by Western mining Between Leeders 1990 and 1992. Killahoe Hill Snapper Davros Tuna • Resulted in the discovery of Harlequin D

Slide 24: Summary
Summary personal use only Production delivery and Racetrack orebody definition are the major short term focus areas. Longterm sustainable growth is our core operational objective: Strong financial results and exploration delivery in FY2026 position Pantoro in an exceptional position to continue to i

Slide 25: Investor Enquiries
personal use only Investor Enquiries: Paul Cmrlec Managing Director admin@pantoro.com.au +61 8 6263 1000 Media Enquiries: Sam Macpherson VECTOR Advisors smacpherson@vectoradvisors.au +61 401 392 925 www.pantoro.com.au ASX: PNR

Slide 26: Mineral Resource & Ore Reserve
Mineral Resource & Ore Reserve personal use only Pantoro Global Mineral Resource Measured Indicated Inferred Total kt Grade koz kt Grade koz kt Grade koz kt Grade koz Norseman Gold Project 5,211 2.2 365 17,878 3.6 2,063 20,066 3.5 2,257 43,155 3.4 4,685 Total 5,211 2.2 365 17,878 3.6 2,063 20,066 3.
Source: ASX announcement, Nov 24, 2026
More decks from Pantoro Gold Limited
Investor Presentation (November 2026)27 slides · Nov 9, 2026
Q1 FY2027 Earnings Presentation15 slides · Oct 22, 2026
Corporate Update (September 2026)30 slides · Sep 21, 2026
Diggers and Dealers 202628 slides · Aug 5, 2026
Q2 2026 Earnings Presentation17 slides · Jul 30, 2026
Noosa Mining Conference 202628 slides · Jul 22, 2026