Alphamin Resources Corp. · TSXV:AFM
Alphamin Resources — Junior Indaba Conference 2016
21 slides from Alphamin Resources's conference presentation, June 2016
Slide 1: Smart Investment in DRC to Meet Growing Demand for World-Class Tin
BORIS KAMSTRA JUNIOR INDABA CHIEF EXECUTIVE OFFICER CONFERENCE 2016 ALPHAMIN RESOURCE CORP. SMART INVESTMENT IN DRC TO MEET GROWING DEMAND FOR WORLD-CLASS TIN
Slide 2: Disclaimer
The statements made in this presentation which are not historical facts contain certain forward-looking statements The mineral resource estimates referenced in this presentation are estimates only and no assurance can be given that concerning potential developments affecting the business, prospects,
Slide 3: Today's Agenda
The A new tin Project DFS inputs & beginning Tin market Project history of a tin producer metrics outputs producing province TODAY’S AGENDA
Slide 4: Global Tin Projects
GLOBAL TIN PROJECTS 5,0 500 000 Resource Contained Tin tonnes 4.49% 4,0 400 000 Grade %Sn 3,0 300 000 2,0 200 000 1,0 100 000 0,0 0 Grade Contained tin
Slide 5: Bisie Project
BISIE PROJECT Regional location Bisie project area 1km Mpama North Goma drill pads Underground mine Mombasa Process plant Exploration camp Mpama South Construction drill pads camp Dar es Salaam Access road Manoire village
Slide 6: Transition from Explorer to Tin Miner
TRANSITION FROM EXPLORER TO TIN MINER Corporate overview Board and management team Major Tremont Master Holdings 43% Chairman Charles Needham is the Chairman of the Board and has been involved in the DRC mining Shareholders industry for 10 years. Charles is also the Chairman of Ruashi Mining and Kin
Slide 7: Bisie Project Geology
BISIE PROJECT GEOLOGY Mpama North Long section showing chute geometry, high grade intercepts and mineralisation open at depth At Mpama North tin Mineralisation focused within mineralisation has been High grade mineralisation a high grade chute which delineated through drilling within two chutes whic
Slide 8: Alphamin's Mineral Resource Base
ALPHAMIN’S MINERAL RESOURCE BASE Mpama North Mineral Resource @0.5% Cut-off Grade Tonnes Sn Sn tonnes Classification (millions) % (thousands) Measured 0.46 4.31 19.6 Indicated 4.14 4.55 188.4 Inferred 0.54 4.25 22.8 Exploration – Mineral Resource Growth Potential Within Mining Permit PE13155 PR10346
Slide 9: Bisie Project Upside
BISIE PROJECT UPSIDE BLUE SKY Mpama Deeps Mpama South Regional targets § Well developed tin and copper in soil anomalies along 15km of the Bisie Ridge § Tin mineralization strongly associated with copper, arsenic, lead, zinc and silver § Significant Sn/Cu/Pb/Zn/As soil anomalies defined over § High
Slide 10: Bisie Project Feasibility Study: Mining and Process Methods
BISIE PROJECT FEASIBILITY STUDY MINING AND PROCESS METHODS Mining by sublevel caving methods Process flow sheet follows standard gravity separation methods Succefully piloted using full-scale equipment.
Slide 11: Bisie Project Feasibility Study Results
BISIE PROJECT FEASIBILITY STUDY RESULTS Key Economic Performance Indicators @$14,800/tSn Economic Sensitivities 180 ¡ Probable Mineral Reserves 3.04Mt @ 3.76%Sn As part of the Indicated Mineral resources 160 Project NPV at 15% discount ($ million) ¡ Tin output per annum 9,000t 140 120 ¡ Life of mine
Slide 12: The Elephant(s) in the Room
THE ELEPHANT(S) IN THE ROOM Managing and mitigating two distinct kinds of risks Binary risk with no redemption • Loss of life Redeemable risk • Exploration risk • Perceptions • Loss of tenure • Cash flow disruption or cost • Production or logistics challenges Smart investment based on sound risk ass
Slide 13: A Bright Future Awaits
A BRIGHT FUTURE AWAITS Phase 2 • Develop Mpama North 2017 to 2018 • Operate mine and plant at • Develop Mpama Deeps • All future output of 9,000t Sn per 2028 to 2031 annum from 2019 to 2027 • Develop Mpama South expansions are 2025 to 2026 expected to be self funded Phase 1 Phase 3
Slide 14: Social License to Operate
SOCIAL LICENSE TO OPERATE
Slide 15: What Are the Next Steps on Our Journey?
WHAT ARE THE NEXT STEPS ON OUR JOURNEY? Roll out of community Constructing development light vehicle projects access road • Process of • Labour intensive surveying 1400 process Appoint EPCM families in • Forms the Extended Bisie foundation for final • Detailed range road design On-going Start mine C
Slide 16: Building the Road to Prosperity
BUILDING THE ROAD TO PROSPERITY
Slide 17: Alphamin: A New Tin Producer with a Fresh Approach
ALPHAMIN A NEW TIN PRODUCER WITH A FRESH APPROACH Alphamin is a pioneering tin Alphamin is committed to exploration and mining contributing to the stability and business with the vision to be Alphamin will be a new viable and economic activity in North Kivu, respected in the international tin scalab
Slide 18: Ready to Deliver Ambitious Aims
READY TO DELIVER AMBITIOUS AIMS Be at steady state Majority of staff production in DRC nationals 2018 Increasing Producing ~9kt local ton Sn in businesses +60% con supporting mine
Slide 19: Expertise to Overcome Challenges and Unlock Potential
EXPERTISE TO OVERCOME CHALLENGES AND UNLOCK POTENTIAL
Slide 20: The Resolve to Succeed
THE RESOLVE TO SUCCEED Drillers’ Workshop Shower and Ablution» . Offices and Mess Facilities Main Accomodations . Fuel Storage Heli-Pad e i Core’ Area Drillers’ Accomodation New.Vodacom Tower servicing the area AALPHAMIN
Slide 21: From Here On Out Things Only Get Better
FROM HERE ON OUT THINGS ONLY GET BETTER ANY QUESTIONS?